Schedule
i3az0kimchi edited this page Dec 9, 2012
·
7 revisions
The current schedule for Bulletin's development:
- First Cycle (10/22 - 11/05)
- Posting to a group: 3 days (Kyle)
- Viewing groups: 3 days (Brian)
- Login/registration: 3 days (Andrew)
- Back-end model development: 7 days (Kyle, Andrew, Brian)
- Front-end coding and modification: 10 days (Ivan, Peter)
- Second Cycle (11/05 - 11/19)
- Creating groups: 3 days (Andrew, Kyle)
- Inviting members: 3 days (Andrew, Kyle)
- Editing groups: 3 days (Andrew, Kyle)
- Commenting on a post: 1 day (Andrew, Kyle)
- Testing: 10 days (Brian)
- Front-end redesign: 10 days (Ivan, Peter, Caylan)
- Third Cycle (11/19 - 12/03)
- Inbox: 3 days (Andrew, Kyle)
- Revising: 10 days (Everyone)
Additional features, as time permits, will have estimates assigned, as well as priorities.
- File attachment
- Mobile access
- Highlighting or prioritizing specific posts
- Tree-style comment system
- Direct messages
- Editing/deleting posts and comments
- Project agenda
- Task lists