Complete plans #1
Comments
6/4 ~ 6/9 Scheduling and purchasing
6/10 ~ 6/17 Scaffolding, prep work
6/18 ~ 6/25 Framing or more prep workWhat we do on here depends on multiple factors. Framing probably wouldn't take more than a few days.
|
Based on the above June is mainly prep and framing related work. July will be insulation, electrical. |
The only styrofoam we need immediately is for the floor. The rest can wait, but let's still calculate how much we need anyway. Then discuss with Yokoyama and how we can reduce costs. |
Discussed with Yokoyama about insulation. He agrees with me about using neolite for the roof and blue styro for the walls and floors. This settles the planning. |