5b/6a Task 1 Project Management (milestone)

  • Anything to discuss?

5b Task 2 Strategic Planning (milestone)

  • Thoughts and next steps from the partners discussion

5b Task 10 Support for Three Zone Systems and TVPB (milestone)

  • Jeff working on caching strategies
  • Jeff checked in latest examples so I'm going to start on QA/QC/verification

6a Task 2 Complete Estimation Mode (milestone)

  • Newman starting on non-mandatory tour frequency EDB larch reader

6a Task 3 Telecommute Model in Cooperation with SEMCOG (milestone)

  • Joel started on the design based on what was done for SANDAG
  • Mobility model that predicts days per week typically telecommute
  • Based on SEMCOG's 2018 data
  • Still need to work on considerations related to telecommuting under COVID
  • Plans to talk with Jilan this week and then the ActivitySim team next week

6a Task 8 Maintenance and Support (milestone)

  • Only a couple quick emails with BYU about their Salt Lake model
  • They had a running model but updated to latest version and ran into a couple issues that I'm helping them resolve