Project Meeting 2020.10.29
Ben Stabler edited this page Oct 29, 2020
·
6 revisions
5b/6a Task 1 Project Management (milestone)
- Anything to discuss?
5b Task 2 Strategic Planning (milestone)
- Thoughts and next steps from the partners discussion
5b Task 10 Support for Three Zone Systems and TVPB (milestone)
- Jeff working on caching strategies
- Jeff checked in latest examples so I'm going to start on QA/QC/verification
6a Task 2 Complete Estimation Mode (milestone)
- Newman starting on non-mandatory tour frequency EDB larch reader
6a Task 3 Telecommute Model in Cooperation with SEMCOG (milestone)
- Joel started on the design based on what was done for SANDAG
- Mobility model that predicts days per week typically telecommute
- Based on SEMCOG's 2018 data
- Still need to work on considerations related to telecommuting under COVID
- Plans to talk with Jilan this week and then the ActivitySim team next week
6a Task 8 Maintenance and Support (milestone)
- Only a couple quick emails with BYU about their Salt Lake model
- They had a running model but updated to latest version and ran into a couple issues that I'm helping them resolve