VSTS | TFS 2018 | TFS 2017 | TFS 2015
Each team can determine the backlog levels that they use. For example, feature teams may want to only focus on their product backlog, while a management team may choose to only show feature and epics (the two default portfolio backlogs). You configure which backlog levels appear from your team settings dialog.
::: moniker range="vsts" If you want additional portfolio backlogs, see the following topics based on the process model you use:
- Inheritance: Customize your backlogs or boards for a process
- Hosted XML: Add portfolio backlogs.
For an overview of process models, see Customize your work tracking experience.
::: moniker-end
::: moniker range="tfs-2015 <= tfs-2018"
If you want additional portfolio backlogs, see Add portfolio backlogs.
::: moniker-end
Note
Feature availability: The team setting for choosing which backlog levels are available is available from TFS 2015 and later versions. For TFS 2013, the Feature portfolio backlog level is enabled for all teams.
Because this setting affects all team members' view of the team backlogs and boards, you must be a team administrator to change the setting. Changing the setting is disabled if you're not a team administrator. Go here to get added as a team administrator.
::: moniker range="vsts || >= tfs-2018"
-
From your team's backlog page, click the (gear icon) to open the common configuration team settings.
-
Click the Backlogs tab and check the boxes of those backlog levels you want your team to manage.
-
To see the changes, open or refresh your team's backlog web page.
::: moniker-end ::: moniker range="tfs-2017"
-
From your team's backlog page, click the (gear icon) to open the common configuration team settings.
-
Click the Backlogs tab and check the boxes of those backlog levels you want your team to manage.
-
To see the changes, open or refresh your team's backlog web page. ::: moniker-end ::: moniker range="tfs-2015"
Requires TFS 2015.1 or later version.
-
From your web portal, click the , (gear icon) to open the administration page.
-
From the Overview tab, choose the team whose settings you want to configure, and then click Settings.
-
Click the Backlogs tab and check the boxes of those backlog levels you want your team to manage.
-