Notifications
You must be signed in to change notification settings - Fork 5
Vibratory Conveyor Stand
Note: The Vibratory Conveyor Stand is no longer being used with the extruder.
Image | Name | Description | Source | Files | Qty |
---|---|---|---|---|---|
![]() |
Stand Base for Vibratory Conveyor | Made | step, drawing | 1 | |
![]() |
Support Arm Weldment | Made | step, drawing | 1 | |
![]() |
Thumb Nut 1-4 in Large | Printed | stl, step | 1 | |
![]() |
Flat Heat Screw 1-4 in 2 in long | Purchased | step | 4 | |
![]() |
Floor Flange 1 in | Purchased | step | 1 | |
![]() |
Hex bolt 1-4 in by 1-1-2 in long | Purchased | step | 1 | |
![]() |
Nipple 1 in by 24 in long | Purchased | step | 1 | |
![]() |
Nipple 3-4 in by 12 in long | Purchased | step | 1 | |
![]() |
Nut 1-2 in | Purchased | step | 8 | |
![]() |
Nut 1-4 in | Purchased | step | 4 | |
![]() |
Pipe Coupling 1 in to 3-4 in | Purchased | step | 1 | |
![]() |
Tap Bolt 1-2in 5 in long | Purchased | step | 4 | |
![]() |
Washer 1-2 in | Purchased | step | 8 | |
![]() |
Washer 1-4 in | Purchased | step | 5 |
Item No. | Image | Name |
---|---|---|
1 | ![]() |
Pipe - short piece |
2 | ![]() |
Pipe Wrench |
3 | ![]() |
Screwdriver Phillips |
4 | ![]() |
Vise |
5 | ![]() |
Wrench 3-4 in |
6 | ![]() |
Wrench 7-16 in |
Go to Making the Vibratory Conveyor Stand Parts for information on how to build the following parts:
- Stand Base for Vibratory Conveyor
- Support Arm Weldment
Step 1: Attach four 1/2 in bolts to the vibratory conveyor stand base. These bolts will be used for the feet. Secure them with the bolt heads down using two nuts and two washers per bolt. Only tighten finger tight as they will be adjusted during final assembly of the machine.
Step 2: Attach the floor flange to the vibratory conveyor stand base. Use four 1/4 in counter sunk bolts with one nut and washer each.
Step 3: Using pipe wrenches, couple the 3/4 in. pipe nipple to the 1 in. pipe nipple with a 3/4 to 1 in. coupler. couple the lower end of the 1 in. pipe nipple to the floor flange.
Step 4: Attach the handle to the adjustable pipe clamp. First press a 1/4 in bolt into the thumbnut using a vice (or hammer with light taps) and a short section of pipe. Then place a washer on the protruding end of the bolt and screw it into the clamp. Note: The video shows a nut and washer on the clamp. These are unnecessary as the clamp should be tapped.
Step 5: Place the adjustable clamp over the 3/4 in. pipe nipple. Don't worry about it's exact position as this will be adjusted during the final assembly.
The vibratory conveyor stand is now complete.
- Zephyris at the English language Wikipedia [GNU]
- By RIDGID - Own work, CC BY-SA 3.0, Link
- By The original uploader was SCEhardt at Wikipedia. (Derived from w:File:Schraubenzieher.jpg) [Public domain], via Wikimedia Commons
Build Documentation:
- Purchasing BOM
- Extruder Body
- Auger Motor and Gear Box
- Extruder Stand
- Drying Hopper
- Water Bath
- Outfeed
- Thunderboard Shield
- Electronics - Low Voltage
- Electronics - High Voltage
- Final Assembly and Wiring
Firmware Installation and Use
Testing the Machine
Preparing the Plastic:
Extruding Filament:
Maintainance
Troubleshooting
Obsolete Parts and Code