Skip to content

Tools inspired by construction industry processes including man-hour estimator, scheduler, critical path analyser and progress tracker.

Notifications You must be signed in to change notification settings

abd00s/Construction-Suite

Folders and files

NameName
Last commit message
Last commit date

Latest commit

 

History

58 Commits
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 
 

Repository files navigation

Construction Suite

In this project I’m aiming to build several applets inspired by construction industry processes, however, applicable to any industry concerned with scheduling, budgeting and resource allocation.

On the agenda:

Man-hour Estimator

Estimates the number of work weeks required to complete an activity when provided the following input:

  • The amount to be carried out (e.g Cubic yards of excavated dirt, tons of steel to be erected, etc. )

  • The productivity rate (e.g. cubic yards per hour, man-hour per ton, etc.)

  • Crew size

  • Number of crews per shift

  • Number of shifts (Morning and/or evening)

Scheduler

Automates the scheduling of activities with known dependencies. An activity dependent on another cannot commence until activities it is dependent upon are complete. Considerations include what tasks must be complete before the current task begins, what tasks should be completed at the same time, and what tasks should begin after current task is complete.

Critical Path Analyzer

After activities are scheduled, the tool will identify the critical path. The critical path represents the longest route (duration) from beginning to end. Delays of activities falling on the critical path cause a delay on the overall project completion.

Earned Value Method Progress Tracking

A tool to allow monitoring of budget and schedule efficiency at individual progress periods and for the overall project cumulatively. At the beginning of a project, a baseline schedule is set.

  • Each progress period is allocated mahours required to complete the tasks in that period (Budgeted Cost of Work Scheduled or Planned Value)

At the end of each period, the following are updated:

  • (Budgeted Cost of Work Performed or Earned Value)

  • (Actual Cost of Work Performed or Actual Cost)

With these three figures, metrics for project performance can be deduced, namely Cost Performance Index and Schedule Performance Index

Further considerations may include:

  • Ability to track number of crews on-site per given shift to reduce jobsite clutter.

  • Ability to list activities by crew.

About

Tools inspired by construction industry processes including man-hour estimator, scheduler, critical path analyser and progress tracker.

Resources

Stars

Watchers

Forks

Releases

No releases published

Packages

No packages published