Following our discussions in #9990, let's start working on a report based on the Earned Value Management technique.
In order to implement this report, we need to calculate the planned value of each task linked to a project.
The project estimated cost will be calculated based on the planned value of all tasks.
This methodology can be found here: https://en.wikipedia.org/wiki/Earned_value_management https://edward-designer.com/web/pmp-earned-value-questions-explanined/
The text was updated successfully, but these errors were encountered:
No branches or pull requests
Following our discussions in #9990, let's start working on a report based on the Earned Value Management technique.
In order to implement this report, we need to calculate the planned value of each task linked to a project.
The project estimated cost will be calculated based on the planned value of all tasks.
This methodology can be found here:
https://en.wikipedia.org/wiki/Earned_value_management
https://edward-designer.com/web/pmp-earned-value-questions-explanined/