Repository navigation
Replies: 4 comments
|
Hi @Isaina! Thank you for these proposals. It could be considered for an extension module, on top of the core IFCX. Or maybe a separate standard, or extension of existing IDS, part of the openBIM ecosystem. For now, I moved it from the Issues to the Wishlist. Let's see if there is a bigger demand for such a solution. |
|
Proposed Additions to IFC5 The proposal suggests introducing a standardized property set describing construction rule parameters associated with building elements. Suggested property set: Pset_ConstructionRule This property set could be applied to elements such as: Possible parameters may include: InstallationType These parameters would describe how related construction quantities should be derived. The IFC model would store the parameters, while external software tools would interpret them to generate construction quantities or BoQ items. ⸻ Example: Underground Pipe Installation A pipe segment may declare that it is installed underground and define trench parameters such as trench width and trench depth. Using these parameters together with the pipe length from the geometric model, software tools can derive excavation quantities required for pipe installation. The resulting excavation quantity can be associated with a BoQ item representing trench excavation. ⸻ Example: Pipe Installed Above Ground If a pipe segment is installed above ground, excavation is not required, but pipe supports may be necessary. A parameter specifying the number of supports required per meter of pipe length can allow software tools to derive the number of support elements or support-related BoQ items. ⸻ Example: HVAC Duct Supports Duct segments may declare the number of supports required per meter of duct length. Using the duct length from the model, software tools can derive the number of required support elements and generate the corresponding BoQ item. ⸻ Example: Ventilation Fans and Outdoor AC Units Mechanical equipment such as ventilation fans or outdoor air conditioning units often require mounting brackets or support frames. An equipment element may declare that one support is required per installed unit. When multiple units exist in the model, the total number of supports can be derived directly from the number of equipment elements. This enables deterministic generation of BoQ items describing equipment supports. ⸻ Example: External Walls External walls often contain multiple construction layers that correspond to separate construction works. A wall element may include parameters describing layers such as: Each layer may correspond to a separate BoQ item derived from wall surface area. For example, an external wall may generate separate BoQ quantities for masonry work, insulation installation, plaster application, and facade finishing. ⸻ Example: Foundations and Footings Foundation elements such as strip footings or slab foundations often require excavation and concrete works. A footing element may include parameters describing excavation width, excavation depth, and foundation dimensions. From these parameters and the geometry of the foundation element, software tools can derive excavation volumes and concrete quantities. The resulting quantities can be associated with BoQ items describing excavation, formwork, reinforcement, and concrete placement. ⸻ Requirement Modes To maintain compatibility with different modeling approaches, construction rule metadata may support different requirement modes. Construction dependencies may be declared as optional, required, or automatically derived if missing. If related construction elements are explicitly modeled, quantities may be taken directly from those elements. If they are not modeled but rules exist, quantities may be derived automatically. If dependencies are declared mandatory but not present in the model, validation tools may report an error. ⸻ BoQ Identification To ensure stable linking between derived quantities and cost systems, cost items may include a persistent BoQ identifier. This identifier allows deterministic mapping between IFC model elements, derived construction quantities, and external cost systems such as spreadsheet-based BoQ documents. ⸻ Key Principle IFC remains a neutral data container describing geometry, relationships, and construction parameters. The IFC schema does not perform calculations. External software tools interpret construction rule metadata to derive quantities and generate BoQ items. ⸻ Benefits Introducing standardized construction rule metadata would improve interoperability between BIM models and cost estimation systems. It would enable consistent quantity derivation, improve traceability between models and BoQ documents, and support lightweight tools capable of extracting construction quantities from IFC models without requiring proprietary BIM authoring software. |
|
Example 1 – Underground Pipe Excavation Element: IfcPipeSegment Properties: InstallationType = Underground Pipe geometry: PipeLength = 15 m Derived by software: ExcavationVolume = PipeLength × TrenchWidth × TrenchDepth Result: BoQ item – trench excavation This allows deterministic excavation quantities to be derived from pipe geometry and installation parameters. ⸻ Example 2 – Pipe Supports Element: IfcPipeSegment Properties: InstallationType = AboveGround Pipe length: Length = 10 m Derived by software: SupportCount = Length × SupportsPerMeter Result: BoQ item – pipe supports ⸻ Example 3 – HVAC Duct Supports Element: IfcDuctSegment Property: SupportsPerMeter = 3 Duct length: Length = 10 m Derived: SupportCount = Length × SupportsPerMeter Result: BoQ item – duct support elements ⸻ Example 4 – Ventilation Fan Installation Element: IfcUnitaryEquipment Properties: SupportType = WallBracket If the model contains three fan units: Derived: SupportCount = 3 Result: BoQ item – fan mounting brackets ⸻ Example 5 – Outdoor Air Conditioning Units Element: IfcUnitaryEquipment Properties: SupportType = WallBracket Two outdoor units exist in the model. Derived: SupportCount = 2 Result: BoQ item – outdoor unit mounting brackets ⸻ Example 6 – External Wall Construction Layers Element: IfcWall Wall area: SurfaceArea = 100 m² Construction layers may include: Derived quantities may include: Each derived quantity corresponds to a separate BoQ item. ⸻ Example 7 – Foundations and Footings Element: IfcFooting Geometry: FoundationLength = 10 m Additional excavation parameters: ExcavationMargin = 0.20 m Derived by software: ExcavationVolume = derived trench volume around the footing Result: BoQ item – foundation excavation Additional derived BoQ items may include: ⸻ Requirement Modes To maintain flexibility, construction rule parameters may include requirement modes: Optional – rule may be used but not required ⸻ Key Principle IFC remains a neutral data container describing geometry, relationships, and construction parameters. The IFC schema does not perform calculations. External software tools interpret construction rule metadata to derive construction quantities and BoQ items. |
|
Yes is a specific demand but is maybe better to be in that ifcx because this is enabler for use cases in ERP and cloud domain no so much on modeling and authoring platforms but if modeling and authoring platform provides data is easier to find and extract data or fill data in 3d model and government use friendly solution because contract are based on cost list not 3d models |
Uh oh!
There was an error while loading. Please reload this page.
Summary
This proposal introduces a standardized rule-based dependency and validation framework into IFC5 to support:
• Conditional cost items
• Parametric cost expansion
• Mandatory construction dependencies
• Model completeness validation
• Error and warning reporting for missing required elements
The objective is to enhance IFC from a passive geometry exchange schema into a construction-aware logical model capable of supporting procurement, cost control, and construction validation workflows.
⸻
IFC currently supports:
• Cost schedules
• Cost items
• Tasks and processes
• Object relationships
However, IFC lacks a formal mechanism to express:
• If an object exists, another object must also exist
• If a condition is met, additional cost items must be generated
• If required construction elements are missing, an error should be raised
• Dependencies between model elements and cost structure
Practical Example
An HVAC IFC model may include:
• Mechanical equipment
• Duct systems
• Cost items
But may omit:
• Structural supports
• Hanging systems
• Anchoring elements
From a construction standpoint, such a model is incomplete.
Currently, IFC provides no standardized way to declare:
“If ceiling-mounted equipment exists, structural supports must exist — otherwise raise a validation error.”
This creates risk in procurement and execution phases.
⸻
IFC5 should introduce a rule-based framework consisting of:
• Declarative model rules
• Conditional dependency definitions
• Cost dependency relationships
• Validation severity levels (info, warning, error)
• Optional validation result reporting
This framework should remain optional and backward-compatible.
⸻
3.1 Rule Definition
IFC5 should support declarative rules that define:
• A condition
• A resulting action
• A severity level
• A priority
Rules must be data-driven, not hard-coded.
⸻
3.2 Rule Conditions
Conditions should support:
• Property-based checks
• Object existence checks
• Quantity-based comparisons
• Logical operators
Example scenarios:
• Installation type equals “Underground”
• Equipment mounting type equals “Ceiling”
• Burial depth greater than zero
• Required object type does not exist
⸻
3.3 Rule Actions
Supported action types should include:
• Add cost item
• Add task
• Require object
• Trigger validation warning
• Trigger validation error
The schema defines rules; software implementations execute them.
⸻
⸻
Use Case 1 – Underground Pipe Requires Earthworks
Condition:
Pipe installation type = Underground
Action:
Automatically associate earthworks cost items including excavation, bedding, and backfill.
Result:
• Parametric cost expansion
• Reduced manual BoQ preparation
• Improved cost consistency
⸻
Use Case 2 – Ceiling-Mounted HVAC Requires Supports
Condition:
Mechanical equipment mounting type = Ceiling-mounted
AND no structural support element exists
Action:
Raise validation error
Result:
• Incomplete models are flagged
• Missing construction elements detected early
• Procurement risk reduced
⸻
Use Case 3 – High-Pressure System Requires Testing Task
Condition:
System pressure > defined threshold
Action:
Add mandatory pressure testing task and related cost item
Result:
• Construction logic embedded in model
• Compliance requirements enforced
⸻
Rules should support graded severity:
• Informational
• Warning
• Error
This allows flexible implementation depending on project maturity level.
⸻
Dependencies may be categorized as:
• Spatial dependencies (location-based)
• Geometric dependencies (dimension-based)
• Performance dependencies (load, pressure, capacity-based)
• Installation-type dependencies
Formalizing these categories improves interoperability.
⸻
For Engineers
• Reduced risk of incomplete design delivery
• Automated dependency checks
• Improved coordination
For Contractors
• Early detection of missing construction elements
• More reliable tender preparation
• Reduced change orders
For Public Procurement
• Better auditability
• Higher model reliability
• Reduced disputes
For Software Vendors
• Standardized validation framework
• Reduced need for proprietary rule engines
⸻
This proposal transforms IFC from:
A geometric and semantic exchange format
into:
A construction-aware logical model framework
It introduces:
• Structured dependency control
• Parametric construction logic
• Model completeness validation
• Cost-integrated design verification
This aligns IFC5 with:
• Digital twin requirements
• Automated compliance checking
• Procurement transparency
• Construction risk reduction
⸻
• Fully optional
• No breaking changes to IFC4.3
• Existing models remain valid
• Rule layer activates only when implemented
⸻
Introducing rule-based cost and dependency validation in IFC5:
• Solves real-world construction workflow gaps
• Prevents incomplete model deliveries
• Strengthens IFC relevance in procurement
• Bridges BIM modeling with execution logic
This proposal aims to make IFC5 not only a data container, but a structured and reliable construction intelligence framework.
All reactions