MEME 0.2.0-alpha
Pre-releaseAdded
-
Power flow as a PyPSA run mode (ADR-0008):
experiment.mode: power_flow
solves the AC network for a fixed dispatch withlpf()andpf()instead
of optimizing. The canonical model describes the network itself —
node.electrical.v_nom,transmission.electrical(kindline or
transformer,r,x,s_nom,num_parallel,tap_ratio) and
technology.dispatch(overridable per node) — andexperiment.power_flow
names theslack, themethod(newton_raphsonorlinear),
distribute_slackand thetolerance. The run writesoutput/power_flow/:
convergence.csv, per-bus voltage magnitude, angle and power, per-line and
per-transformer flows and loading, generator dispatch and asummary.json;
a snapshot that does not converge fails the run. The API consumer chains a
plan and a power flow as two calls; MEME holds no state between them. -
Gates around the new inputs: the mode routes through the
power_flow
capability (PyPSA only); power-flow inputs in an optimization mode (a
dispatch, theelectricalblocks) are kept and named in one warning
while the arcs stay transport links (see Changed); in modepower_flow
expandable capacities, trade,
constraints, emission limits and scenarios are rejected, and
distribute_slackrequires a dispatch on the slack technology (PyPSA
shares the balance in proportion to each generator's set-point, so a slack
without one would receive none of it). -
Scenario
pypsa_power_flow, the example payloads
examples/pypsa_power_flow*.json(the reference network, the smallest
valid power flow, a meshed ring with per-node dispatch, and the options:
linear method, distributed slack, storage sign, a second carrier) and E2E
checks for convergence, the linear method and a diverging load. The
examples walkthrough documents the options, the result files and the
rejected requests. -
Reactive power, voltage control, shunts and controlled transfers for the
power flow (ADR-0009):technology.electricalwithreactive_dispatch
orpower_factor(+leading),control: pvandvoltage_setpoint;
node.electrical.shunt;transmission.dispatchas a controlled HVDC
transfer on an arc without impedance;b,g,phase_shiftand
r_per_length/x_per_lengthontransmission.electrical. The result
folder gains the reactive tables, the load and link tables and the shunt
tables. Gates: one way to give Q, voltage set-points forpvgenerators
and the slack only and agreeing per bus, an electricity arc needs an
impedance or a transfer, every AC island needs a generator (an island
without the named slack is reported as balanced by PyPSA), and the linear
method says what it ignores. Scenario and example payload
pypsa_power_flow_reactive, E2E-pinned on the held voltages. -
The electrical network inside the optimization (ADR-0010):
experiment.network.model: linear_power_flowmakes PyPSA solve under
Kirchhoff's voltage law with Lines and Transformers (expansion from the
arc'scapacity,electrical.max_loadingass_max_pu), and
network.security.outagesruns the security-constrained solve; other
targets reject the model like a mode. Transmission gainslifetime,
interest_rateandcost_basis, and PyPSA prices the arc's investment
and fixed O&M on Links and Lines. Every optimization run writes
output/results/(dispatch, flows, storage states, marginal prices,
capacities.csv,statistics.csv,summary.json). -
PyPSA optimization completeness (ADR-0011): an energy-sized storage
(storage.energy_capacity) is a Store with charger and discharger Links,
which honors independent rates, depth of discharge and the energy-capacity
cost (_storage.jsoncarries the equal-power and rate constraints);
storage.soc_profilepins a StorageUnit's state of charge;
capacity.per_unitbuilds integer modules;decommission.mode: continuousretires existing capacity at its fixed O&M and builds new
capacity above it;allow_unmet_demandadds priced slack generators;
copperplatejoins every node through a free hub;operation.ramp_start_up,
ramp_shut_down,standby_cost,initial_uptime,initial_downtimeand
costs.<class>.variable_om_quadraticmap onto PyPSA's unit-commitment and
cost attributes;model.periodswith years are investment periods with
build_year,lifetimeand new builds per period. Scenarios and goldens
for every claim, E2E on the real framework, and the example
examples/pypsa_planning.json.
Changed
- PyPSA no longer rejects independent storage rates, depth of discharge,
continuous retirement, unmet demand or copperplate; the energy-capacity
cost is priced instead of dropped. Calliope and AdOpT-NET0 keep every
mapping they had; the new fields they have no slot for (soc_profile,
the unit-commitment extras, the quadratic cost, investment periods) are
ignored there with a warning. The validation matrix records every verdict
that moved. time.subsetandcosts.<class>.purchaseare rejected on PyPSA and
AdOpT-NET0 instead of being dropped without a word: neither target has a
slot (narrowtime.start/end; fold the purchase cost into
investment_per_capacity). Calliope 0.7 warns thatarea.per_capacity
is not emitted (0.6 emitsresource_area_per_energy_cap). The validation
matrix records the moved verdicts.- Power-flow inputs —
dispatch, theelectricalblocks on technologies,
arcs and nodes — are ignored with one warning wherever no power flow runs:
on Calliope and AdOpT-NET0 and in PyPSA's optimization modes alike. A
dispatchin an optimization mode was rejected before; now one payload
serves the planning call and the power-flow call (ADR-0009). - The PyPSA driver parses its run configuration as JSON (
json.loads)
instead of pasting the JSON in as a Python literal, which broke on the
first boolean setting.
Fixed
- PyPSA
state_of_charge_initialis absolute (MWh), but the canonical
fractionstorage.initial_socwas written into it unchanged, so a
half-full 24 MWh unit started at 0.5 MWh. The fraction is now applied to
the installed energy (p_nom×max_hours); an expandable storage is
told it starts from its existing capacity.