Bug in task complete calculation #21

Closed
mahmad2504 opened this issue Jan 11, 2017 · 2 comments
Closed

Bug in task complete calculation #21

mahmad2504 opened this issue Jan 11, 2017 · 2 comments
Assignees
Labels

Comments

@mahmad2504
Copy link

Group task is showing wrong work progress, probably because weighted average is not considered while computing the completion progress. It would be good if there is option of just showing what user has mentioned in XML file and bypass the implemented
untitled
group completion logic

@RickCardoso RickCardoso self-assigned this Jan 13, 2017
eduardomourar pushed a commit that referenced this issue Jan 17, 2017
Now the completion of a task is the average of its subtasks weighted by the duration of each one.

In addition to changing the logo as requested, the NumKid property was kept and the vWeight parameter was added to be used for the weighted average.
@eduardomourar
Copy link
Collaborator

eduardomourar commented Jan 17, 2017

@mahmad2504, thanks for your input. We have released v1.7.5.3 with a weighted average. Let us know if that was what you had in mind.

@mahmad2504
Copy link
Author

Great.