How to change between actual, planned and forecasted gantt charts #20
|
Is there an option to update gantt chart for baseline, actual or forecast. As far as i understand theese are the different options for visualizing gantt. |
Replies: 1 comment 3 replies
|
Hi @phobo3s, Thanks for your question! There's an important distinction worth explaining here. 🙂 ProjectEngine doesn't currently provide three separate Gantt views for Baseline, Actual, and Forecast. Instead, these are three types of scheduling inputs used by the calculation engine to produce the Calculated dates displayed in the Gantt. Here's how they work:
How does the Gantt decide which dates to display?ProjectEngine applies the following input priority: Actual > Forecast > Baseline These inputs are then processed by the scheduling engine, which also considers dependencies, calendars, constraints, and predecessor relationships. The result is a set of Calculated Start and Finish dates, which are used to render the Gantt. The Gantt therefore displays the calculated schedule, rather than switching directly between three independent sets of dates. Why keep three types of dates?The objective is to preserve the original project reference while allowing the current schedule to evolve. For example, imagine an activity that was originally planned to start on March 1:
Once the Actual Start is recorded, it takes priority for that event, while the original Baseline and Forecast values remain available for reference. Want to visualize your original Baseline Gantt? Here's a workaround!Although there isn't currently a dedicated Baseline display mode, you can reconstruct the original schedule using the existing calculation engine:
Since Actual and Forecast dates are no longer provided, the calculation engine will use the remaining Baseline inputs and scheduling logic to rebuild the Gantt. You'll then have a visual representation of the baseline-based schedule that you can compare with your current project. Important: Always do this in a separate copy, since clearing Actual and Forecast data in your working project would remove valuable planning information. Also, this reconstructs a schedule from the remaining inputs. It isn't necessarily an exact historical snapshot if dependencies, durations, calendars, constraints, or other scheduling inputs have changed since the original baseline was established. Could a Baseline overlay be added in the future?Potentially, yes! Displaying the original Baseline alongside the current calculated schedule could be a useful improvement. However, ProjectEngine renders its Gantt using Excel graphics. Adding another graphical representation for every activity would increase the rendering and maintenance workload, especially on large projects containing hundreds or thousands of tasks. For now, I've prioritized keeping the interactive Gantt responsive rather than adding additional graphical layers. Baseline, Actual, and Forecast information remains accessible through the WBS and existing planning analytics and reporting features. In short: one calculated Gantt, three types of scheduling inputs, and a simple workaround if you want to visualize your baseline separately. Hope this helps! Best regards, |
Hi @phobo3s,
Thanks for your question! There's an important distinction worth explaining here. 🙂
ProjectEngine doesn't currently provide three separate Gantt views for Baseline, Actual, and Forecast. Instead, these are three types of scheduling inputs used by the calculation engine to produce the Calculated dates displayed in the Gantt.
Here's how they work: