Hi @phobo3s,

Thanks for your question! There's an important distinction worth explaining here. 🙂

ProjectEngine doesn't currently provide three separate Gantt views for Baseline, Actual, and Forecast. Instead, these are three types of scheduling inputs used by the calculation engine to produce the Calculated dates displayed in the Gantt.

Here's how they work:

  • Baseline represents the original project schedule, typically established at the beginning of the project or agreed contractually. It provides a historical reference against which future changes can be measured.
  • Actual represents what has really happened. When an activity actually starts or finishes, those dates record real events and…

Replies: 1 comment 3 replies

Comment options

You must be logged in to vote
3 replies
@TMailletFR
Comment options

@phobo3s
Comment options

@TMailletFR
Comment options

Answer selected by phobo3s