What went well?

  • We finished the project on time and met our deadlines. Every member of the group contributed.
  • Each person did their jobs on time.
  • Team members helped each other with challenges and took time to show each other the correct way.

What went wrong?

  • Learning took more than expected, started implementation a bit late.
  • We should have met with TA earlier.
  • We should have created more frequent deadlines for smaller tasks.

Actions

  • Putting more frequent deadlines.
  • Being more systematic to be more efficient in terms of time.
  • Arranging more meetings with the TA.