Project Retrospective

This page reflects on the team's work from the start of the semester through the MVP Milestone. This page focuses on what worked, what slowed us down, what we would do differently, and the decisions we decided on for the final milestone.


What Went Well

CI/CD pipeline set up early Automated testing and deployment on every PR to main was established before the MVP. As noted in the MVP Report D6-D7, all three platforms had separate CI jobs with test-gated deployment. This meant broken code rarely stayed in the codebase for long and the team could merge with confidence.

Real production deployment The system runs on EC2 with HTTPS, Nginx, Docker Compose, and automatic deploys. Having a live, publicly accessible product at emergencyhub.duckdns.org made our tests more realistic.

Three-platform delivery Delivering a working Django backend, React web frontend, and Android app in parallel within a single semester was ambitious. As detailed in the MVP Report D6-D7, all three were functional and demonstrated at the milestone with full end-to-end user flows.

Backend test coverage Backend tests were written covering the forum, help requests, and accounts modules. Many bugs caught and fixed during testings before the demo which is an evidence that the testing culture caught real problems.

Offline map feature This was one of the technically hardest features in the project, caching map tiles and gathering points for use without connectivity. It was delivered and demonstrated at the MVP despite its complexity.

Effective parallel development The team operated in specialised subgroups (Authentication, Forum & Help Requests, Profile & Web Info, Offline Features, DevOps) as outlined in the MVP Report D6-D7. This structure allowed parallel development across platforms without members constantly blocking each other.

Good separation of dependencies of requirement tasks Within subgroups, separation of tasks were handled cleverly to ensure independent development between subgroups was possible.


What Held Us Back

Only one customer meeting A single customer meeting took place at the beginning of the project. For the rest of the process, development continued without external validation. The MVP Report D6-D7 itself notes that "requirement-to-implementation traceability" was identified as needing improvement — a direct consequence of requirements not being re-validated with the customers as the project evolved.

Core auth features left incomplete Email verification and password reset, which are baseline features in any production system, remained as draft issues going into the final milestone. They were deprioritised in favor of more visible features.

Branch integration left too late Several reverts and conflict-fix commits in the history indicate that some branches were merged without sufficient coordination. Integration problems that could have been caught early accumulated and surfaced at the last moment before the demo.

Push notifications only partially implemented The Firebase / FCM integration exists but full delivery across all relevant flows was not achieved by the milestone. Current version only sends notifications to experts, but in some cases standard users should also get notifications. These cases have to be determined with discussion.

Weak coordination in offline implementation File structures on mobile app were not agreed upon among the mobile implementers, causing refactoring and compatibility issues (which were eventually fixed without any problems) in mobile features.


What We Can Improve

More frequent customer contact At least one mid-semester check-in would have allowed us to validate whether what we were building matched what the customer actually needed. Any scope change or ambiguity going forward should be resolved with the customer directly, not assumed internally.

Define done before starting Several features were merged in a partially working state and required follow-up fixes. The bugs documented in the MVP Report D6-D7 could have been caught earlier with a clearer definition of done that includes a working UI check before merge.

Keep branches short-lived Branches should be opened, reviewed, and merged within a few days. Large features should be split into independently mergeable pieces from the start. This reduces the cost of integration and prevents the revert patterns visible in the git history.

Balance feature work with test coverage Tests should be written alongside features, not deferred as separate cleanup tasks. The open test issues at the end of the milestone indicate that testing was deprioritised under time pressure, which compounds risk during the final stretch.

Live the scenario, don't just present the app During the MVP demo, the team focused on walking through the application's features and screens. However, the expectation was to embody the scenario, acting as the defined personas experiencing a real emergency, with the app as a natural part of that story. For the final demo, the team should fully commit to the narrative: introduce the characters, set the scene, and let the features emerge through the story rather than explaining them from the outside.


Final Decisions

The following decisions were made as a team based and we will be working on them in the remaining time before the final milestone.

In scope for the final milestone:

  • Email verification and password reset will be completed
  • Admin role with user moderation and reporting functionality will be implemented
  • Multi-language support will be added.
  • Application logo will be delivered for both web and mobile.
  • Push notification delivery will be completed across all remaining flows, building on the partial infrastructure already in place.
  • Direct message system between help requester and helper will be implemented.
  • Hubs will be defined in more detail.
  • Help request notifications will be matched to necessary expert classes. Necessary expert classes will be discussed and defined as a team.

Process commitments going forward:

  • No branch should stay open for more than one week without a review.
  • Every feature merged before the final demo must include at least one test and a working UI verification.
  • Environment setup steps will be kept current in the README so any team member can run the project independently.