Hi @Isaina! Thank you for these proposals. BoQs can be made directly from IFC (4.3) models, and cost codes are often modelled in IFC. This is partially up for the implementation, not sure if there are actual changes needed to the IFC in those regards. If so, please be more specific - what changes and technical solutions do you propose? Inconsistencies stem from complexity, granularity and localisation of the construction processes. The fact that IFC would contain a standard way to do something does not mean it would be commonly in use, as we observe with many current IFC4.3 solutions that are rarely in use. The spreadsheet-compatible export view is an interesting idea. I don't see why the current IFC would not be sufficient. Can you please be more precise on the limitations and solutions? I see you also raised the part about validation rules in #113 For now, I moved it from the Issues to the Wishlist. Let's see if there is a bigger demand for such a solution. |
Uh oh!
There was an error while loading. Please reload this page.
Summary
Across the European Union, Bills of Quantities (BoQs) are predominantly prepared, submitted, and contractually managed using spreadsheet formats (typically Excel-based structures).
A standard EU BoQ commonly includes:
• Item code
• Description of works or equipment
• Unit of measure
• Quantity
• Unit price
• Total price
Although IFC supports cost-related entities (such as cost schedules and cost items), there is currently no standardized and interoperable mechanism to:
• Automatically generate structured BoQs from IFC models
• Maintain a persistent and unique identifier linking IFC elements to spreadsheet rows
• Synchronize quantities when the model changes
• Validate consistency between model geometry and contractual BoQ
This proposal introduces a standardized BoQ integration and validation framework for IFC5.
⸻
In current workflows:
• BoQs are maintained outside the IFC model
• Cost codes are project-specific and inconsistent
• There is no guaranteed persistent link between model elements and BoQ rows
• Quantity updates are manual or semi-automated
• Changes in geometry do not reliably propagate to cost documentation
This leads to:
• Tendering inconsistencies
• Quantity mismatches
• Missing cost items
• Legal and contractual disputes
• Reduced trust in BIM-based procurement
In EU public procurement environments, this disconnect remains a major obstacle for full BIM adoption.
⸻
IFC5 should introduce a standardized framework for:
1. Persistent BoQ item identifiers
2. Explicit quantity derivation methods
3. Structured linkage between IFC objects and BoQ rows
4. Spreadsheet-compatible export view
5. Model-to-BoQ validation rules
The objective is not to replace spreadsheets, but to formalize their integration with IFC.
⸻
Each BoQ-related cost item in IFC5 should contain:
• A unique BoQ code (national or project classification reference)
• A persistent global identifier
• A reference to generating IFC objects
• A declared quantity derivation rule
This enables:
• One BoQ row linked to multiple IFC objects
• Full traceability from cost to geometry
• Stable references across model revisions
⸻
IFC5 should formalize quantity derivation types:
• Length-based (pipes, ducts, cables)
• Area-based (insulation, finishes)
• Volume-based (concrete, excavation)
• Count-based (equipment, fixtures)
Each BoQ item should explicitly define:
• Measurement rule
• Source property or geometry
• Unit of measure
• Aggregation logic
This ensures consistent and auditable quantity generation.
⸻
IFC5 should define a standardized BoQ export structure compatible with common EU spreadsheet practice.
Recommended structure:
• BoQ Code
• Description
• Unit
• Quantity
• Unit Price (optional)
• Total (derived)
• Linked IFC Object IDs
This ensures that Excel remains a contractual document while IFC becomes the authoritative quantity source.
⸻
IFC5 should support model-driven quantity updates.
If geometry changes:
• Lengths, areas, or counts are recalculated
• BoQ quantities are updated
• Inconsistencies are flagged
Validation scenarios:
• IFC object exists but is not referenced in BoQ → warning
• BoQ row references zero IFC objects → warning
• Quantity mismatch between declared and calculated value → warning or error
This supports transparent model-to-contract alignment.
⸻
EU projects often rely on:
• National cost coding systems
• Project-based classification frameworks
• Harmonized European standards
IFC5 should support:
• Multiple classification mappings
• External cost classification references
• Cross-system interoperability
This ensures adaptability across EU member states.
⸻
IFC5 should allow rule-based completeness validation such as:
If an HVAC system exists but no associated insulation BoQ item exists → warning
If equipment requires supports but no related structural element exists → error
If quantity derivation cannot be resolved → error
This prevents incomplete model deliveries in procurement workflows.
⸻
For Engineers:
• Automatic BoQ generation
• Reduced manual spreadsheet work
• Transparent quantity traceability
For Contractors:
• Reduced tender risk
• Clear link between geometry and cost
• Improved reliability of quantity take-offs
For Public Authorities:
• Increased transparency
• Reduced disputes
• Better auditability
For Software Vendors:
• Clear interoperability framework
• Reduced proprietary implementations
⸻
This proposal connects:
Geometry → Quantity → Cost → Contract
It bridges the gap between BIM modeling and EU procurement practice.
By formalizing BoQ integration within IFC5:
• IFC becomes relevant to real-world tendering
• Spreadsheet workflows remain supported
• Digital procurement maturity increases
• BIM adoption barriers are reduced
⸻
Standardized BoQ integration in IFC5:
• Solves persistent quantity management issues
• Aligns IFC with EU construction economics
• Improves transparency and legal reliability
• Strengthens IFC’s role in digital public procurement
This proposal aims to ensure that IFC5 supports not only geometric exchange but also structured and contract-ready cost documentation.