Monday 10/21

  • Design ERD
  • Pivotal Tracker: User Stories/Acceptance Criteria/Assign Points/Tasks
  • Setup GitHub repo
  • Setup PostgreSQL database
  • Setup Java EE and Maven app for Spring framework, Hibernate, and Mockito
  • Test simple spring app with Rest controller
  • Set up Entity
  • Link entity with PostgreSQL under CRUD principle
  • Implement USER

Tuesday 10/22

  • Implement USER, PROFILE
  • Setup SecurityConfig to pass request Authentication with JWT

Wednesday 10/23

  • Implement POST, COMMENT
  • Functionality test with the postman
  • Link backend with frontend
  • Setup CORS

Thursday 10/24

  • Minor fix
  • Complete integrating with Front-End
  • Functionality test with front-end
  • Implement Unit Testing
  • Implement Exception Handling

Friday 10/25

  • Minor fix for backend
  • Implement Unit Testing
  • Implement Exception Handling
  • Front-End functionality test 2

Saturday (12pm) 10/26

  • Minor fix for backend
  • Update README

Sunday 10/27

  • Update README
  • Prepare for presentation
  • Front-End functionality test 3