Labor Assignment Optimization

Concept

The factory produces 7 days a week with 3 shifts a day: morning, afternoon and evening. The factory has the production plan for next week with estimated the workforce daily workforce requirement:

  • Monday (6,4,3)
  • Tuesday (5,5,5)
  • Wednesday (6,4,4)
  • Thursday (5,5,5)
  • Friday (5,5,3)
  • Saturday (6,5,4)
  • Sunday (5,5,4).
  • The total workforce is 20 people.
  • According to the labor rights:
    • A labor can only work 1 shift a day and each week
    • A labor must take leave at least 2 days
    • If a labor works on evening shift today, he/she cannot work on the morning shift tomorrow.

Therefore, as a production planner, how can we assign each labor to each day and each shift to minimize the cost, satisfy the demand but still follow the rights?

Mathematical model

Sets

  • I is the set of the factory workforce, $I = {1, 2, 3, \dots, 20}$
  • J is the set of weekday, $J = {1, 2, 3, \dots, 7}$
  • K is the set of each shift in a day, $K = {1, 2, 3}$

Parameters

  • $D_{jk}$ is the labor demand in day j at shift k

Decision variable

  • $x_{ijk}$ is the binary decision variable on assigning labor i to day j at shift k, $x_{ijk} = {0, 1}$

Constraints

  • For each shift k in each day j, the number of labor to be assigned must fulfill the demand: $\sum_{i=1}^{20} x_{ijk} = D_{jk}, \forall k \in K, \forall j \in J$
  • For each labor i in each day j, the maximum number of shift he/she can work is 1: $\sum_{k=1}^{3} x_{ijk} \leq 1, \forall i \in I, \forall j \in J$
  • For each labor i, the maximum day and shift he/she can work is 5: $\sum_{j=1}^{7} \sum_{k=1}^{3} x_{ijk} \leq 5, \forall i \in I$
  • For each labor i in each 2 days j and j+1, if he/she works on evening shift (k = 3) today, he/she cannot work on the morning shift (k = 1) tomorrow: $x_{ij3} + x_{i(j+1)1} = 1, \forall j \in J, \forall j+1 \in J$

Objective function

  • Minimizing the total workforce assigned: $\min \sum_{i=1}^{20} \sum_{j=1}^{7} \sum_{k=1}^{3} x_{ijk}$