Story summary Analysis
Iteration ItEr63week45To46
FEA ItEr63S02Analysis
Story Lead  
Next Story  
Passed acceptance test No

Acceptance Criteria

Additional Specification Comments

Implementation Notes

 

Delay Causes

Final or Pending Considerations

 

Entregables de código

%RPSHOWGITCOMMITS%

Tasks in this story

Tasks Est Spent To do Risk Reviewer Developer Task Name Start Date Est End Date End Date
Task 40 0 0 Low JavierMoran JavierMoran Analysis      
Task 10 0 0 Low JavierMoran JoseMariaCasanova Analysis      

Total Hours in this Story

User Spent in XpTracker Spent in phpReport Ok?
JoseMariaCasanova 0 0 DONE
JavierMoran 0 0 DONE
Total 0 0 DONE