ItEr67week01

Jeroen Baten edited this page Mar 9, 2018 · 1 revision

TWiki> LibrePlan Web>ItEr67week01 (20 Aug 2012, ManuelRego)EditAttach

Summary Iteracion 67
Team LibrePlanTeam
Start 03/01/2011
End 09/01/2011

Iteration Details >>

Iteration summary

Story FEA Estimate Spent PhpReport ToDo Progress Done Overrun Completion Developer Reviewer
ItEr67S01Coordination
Coordination
ItEr67S01Coordination 2.5 1.5 0 0
smile
100% -40% Acceptance JavierMoran JavierMoran
ItEr67S02Analysis
Analysis
ItEr67S02Analysis 0 0 0 0
smile
100% 0% Acceptance JavierMoran JavierMoran
ItEr67S03CommunityMaterialItEr66S03
Community material
ItEr67S03CommunityMaterialItEr66S03 20 33 0 0
smile
100% +65% Acceptance ManuelRego JavierMoran
ItEr67S04BugFixing
Bug fixing
ItEr67S04BugFixing 70 82.25 0 0
smile
100% +17% Acceptance ManuelRego OscarGonzalez SusanaMontes JavierMoran LorenzoTilve JavierMoran
ItEr67S06WaterMarkProjectCalendar
Update water mark in gantt according project calendar
ItEr67S06WaterMarkProjectCalendar 5.75 5.75 0 0
smile
100% 0% Acceptance LorenzoTilve JavierMoran
Team totals   98.25 122.5 0 0
smile
100% +24%      

Developer velocity for iteration ItEr67week01

Who Assigned Spent PhpReport Remaining Completition   Assigned Tasks Remaining Tasks
LorenzoTilve 20.75 17.5 0 100%   2 0
ManuelRego 30 37.5 0 100%   3 0
SusanaMontes 10 20 0 100%   1 0
OscarGonzalez 20 25.75 0 100%   1 0
JavierMoran 17.5 21.75 0 100%   3 0