Workflows

Workflows turn a group objective into a durable dependency graph. Each step has a stable numeric ID, an owner, a milestone, dependencies, an optional stall threshold, state, timestamps, and a linked task while it is actionable.

The engine coordinates execution; it does not decide whether an agent's work is technically correct. Completion evidence, error recovery, and independent verification make that decision explicit.

Lifecycle

stateDiagram-v2
    [*] --> draft: create
    draft --> running: start
    running --> done: all steps complete
    running --> halted: error
    halted --> running: fix + verify OK
    halted --> halted: verify FAIL
    running --> aborted: abort
    halted --> aborted: abort
Loading

Workflow states are draft, running, halted, done, and aborted. Step states are pending, active, done, error, and fixed.

Structural edits are draft-only. A running plan changes through ordinary completion, the error/fix/verify protocol, or abort. Workflow options such as strict completion evidence and stall thresholds remain adjustable while the plan is draft, running, or halted.

Build a graph

Create a workflow for an existing group:

tiza wf create release-check release
tiza wf step release-check builder "Build candidate" --after 0 --eta 2h
tiza wf step release-check tester "Run system tests" --after 1 --eta 1h
tiza wf step release-check reviewer "Review security boundary" --after 1
tiza wf step release-check console "Approve publication" --after 2,3
tiza wf show release-check

--after 0 declares a root. Omitting --after on an appended step makes it depend on the previous step. A comma-separated list declares a join. Several steps depending on the same predecessor form parallel branches.

flowchart LR
    B[1 Build candidate] --> T[2 Run system tests]
    B --> R[3 Review security boundary]
    T --> A[4 Human approval]
    R --> A
Loading

The engine checks the complete graph after every structural mutation and rejects cycles, missing dependencies, invalid owners, and malformed step IDs. Step IDs are stable: insertion and removal splice dependency references without silently renumbering existing work.

Levels and activation

On start, the hub snapshots the group's current members and activates the ready roots. Started membership remains stable even if the group is edited later.

A pending step activates only when:

  1. all of its direct dependencies are done;
  2. all of its cross-workflow dependencies are done; and
  3. every step in every lower topological level is done.

The third rule is a deliberate level barrier. It prevents one branch from advancing into the next phase while a sibling in the current phase is still open. All ready steps in the same level activate together.

Activation creates a durable linked task and sends the owner an instruction to start. Other group members receive the plan but must wait until the hub marks their own steps active. A reconciliation pass recreates a missing task or retries a pending notification after a partial failure or restart.

Run and complete work

Start the plan and inspect its projection:

tiza wf start release-check
tiza wf show release-check
tiza wf tasks release-check

An owner closes its single active step without naming it:

tiza wf done release-check "Built and checked the release artifact."

Name the stable step ID when the actor owns several active steps or when an authorized administrator is acting explicitly:

tiza wf done release-check 2 "System suite passed on the supported targets."

Only the step owner, group administrator, or console can close a normal active step. A step owned by console is a human approval gate and only the console may close it.

With strict mode enabled, completion without evidence is rejected:

tiza wf set release-check strict on
tiza wf done release-check 3 "Reviewed access boundaries and negative cases."

Closing a step first commits workflow truth, then projects the result onto its linked task and activates newly ready work. If that projection fails, the workflow transition is not rolled back or repeated; reconciliation repairs the projection later.

Error, repair, and independent verification

Any current workflow member can report a problem on an active step. A completed step may also be flagged when later work exposes a defect:

tiza wf error release-check "Candidate checksum does not match." --step 1

The hub immediately:

  • snapshots the pre-error state and active set;
  • changes the workflow to halted;
  • marks the affected step error;
  • stops all advancement, including unrelated branches;
  • projects the error to the linked task; and
  • notifies the affected owner, active owners, and relevant group members.

The owner repairs and tests the affected step, then records both facts:

tiza wf fixed release-check "Rebuilt from a clean tree; checksum now matches."

That moves the step to fixed, but the plan stays halted. Verification must come from another party: normally the original reporter, otherwise the group administrator, otherwise the human console. The fixer cannot approve its own repair, even if it is also the group administrator. The console has an explicit, logged override.

tiza wf verify release-check ok "Reproduced the clean build and checksum."

An ok result restores the affected step to its state before the error and resumes the frozen work. If the error was found in a previously completed step, the engine also names downstream active or completed steps that were built on top of it so operators can reassess them.

A failed verification returns the step to error and keeps the workflow halted:

tiza wf verify release-check fail "Mismatch remains on a second host."

The owner must fix and test again. There is no automatic retry or silent resumption.

Cross-workflow dependencies

A dependency may refer to a stable step in another workflow as workflow-name#step:

tiza wf step deploy-check deployer "Deploy approved release" \
  --after release-check#4

Cross-workflow dependencies are checked globally for cycles. Completing the source step reevaluates dependent running workflows and activates newly ready work. Renaming is intentionally absent because it would invalidate durable references.

Draft editing

Use the stable step IDs displayed by wf show:

tiza wf insert release-check builder "Generate manifest" --after 1 --eta 30m
tiza wf set release-check 2 milestone "Run release system tests"
tiza wf set release-check 2 after "1,5"
tiza wf set release-check 2 team tester
tiza wf set release-check 2 eta 90m
tiza wf remove release-check 5

Removing a draft step splices its predecessors into its dependants, then revalidates the complete graph. after accepts a dependency expression; durations accept s, m, h, or d suffixes.

Clone a plan into a pristine draft when the executed plan should remain an immutable record:

tiza wf clone release-check release-check-next release

The clone retains structure and options but resets state, tasks, timestamps, error data, notifications, and logs.

Stalled-step reminders

Each active step can have an ETA threshold. Resolution order is:

  1. step eta;
  2. workflow default eta;
  3. factory default of 24 hours.

Use off to disable reminders and factory to restore the default:

tiza wf set release-check eta 4h
tiza wf set release-check 2 eta 45m
tiza wf set release-check 3 eta off

The watchdog measures silence since the newest of activation, a linked-task note, or the previous reminder. It nudges the owner and, when different, the group administrator. Halted workflows are never nudged. Add a task note to record progress and reset the silence clock.

Snapshots, undo, restore, and export

The engine snapshots the full workflow store before every successful mutation and retains the newest 30 snapshots per workflow. Inspect history and restore a point:

tiza wf history release-check
tiza wf undo release-check
tiza wf undo release-check <snapshot-id>

Undo is itself a mutation, so the current state is snapshotted before the jump. This permits a later jump back to the state that was replaced.

Save a restorable JSON document or export for external review and tooling:

tiza wf save release-check release-check.wf.json
tiza wf restore release-check release-check.wf.json
tiza wf export release-check release-check.sqlite
tiza wf export release-check release-check.sql
tiza wf export release-check release-check.mmd
tiza wf export release-check release-check.dot

The saved JSON form is restorable. SQLite and SQL are structured exports; Mermaid and DOT are visualization exports. Restore validates the complete plan before replacing durable state.

Abort and delete

Abort stops a running or halted plan and cancels its open linked tasks:

tiza wf abort release-check "Publication was withdrawn."

Deletion removes an eligible workflow and unlinks its task projections. It does not erase task history. Prefer keeping completed and aborted plans as audit records unless retention policy requires deletion.

Operating rules

  • Never start work merely because a step appears in the plan; wait for active.
  • Record meaningful test evidence, especially in strict workflows.
  • Report a discovered defect on the plan, even when its original step is done.
  • Do not bypass a halt by manually reopening or closing linked tasks.
  • After an unknown command outcome, read wf show before trying again.
  • Use task notes for progress; they feed both human history and stall detection.
  • Back up workflow state and snapshots together; see Operations Runbook.