Executable scheduling data model

This is the current APEX model reference. The schemas are generated from Rust types in model.rs and production.rs.

This guide describes the current input contract. Historical input formats are not supported or automatically migrated. Saved results must be regenerated when input or evaluation semantics change. The migration audit preserves historical scheduler comparisons and their limits.

Schema roles and tool releases

The three schemas describe different inputs to one workflow, not three datasets that must all be imported. The engine ultimately schedules a Problem; the workflow below shows how it reaches that input.

Schema Describes Used by
Production orders and workplans ProductionInput: shared problem settings, reusable workplans and order demands production.import or apex expand, which generates concrete lots and operations
Scheduling problem Problem: resources, calendars, concrete operations, material, constraints and objectives Direct scenario import or the result of production expansion, then the scheduling engine
Planning options Options: search settings and requested choices for one run Scheduling and improvement calls on a problem

Production input is optional: an adapter that already supplies concrete operations can import a complete scheduling problem directly. A production input document embeds its shared settings in problem; it does not require a second problem file. Expansion fills that problem with the generated work. See quantities, workplans and orders for the exact boundary.

The production schema includes shared problem types so a production document can be validated on its own. This overlap does not require duplicate factory data. Planning options are optional overrides for one run; omitted options use defaults. Supply them inline in tool arguments or through a CLI options file, not as another factory dataset.

The main application release is the only version stream for these schemas. Its version comes from the application's Cargo.toml / runtime version. Problem, its nested planning vocabulary, production input and planning options have no independent format-version fields. Use the schemas generated by the installed tool. The parser accepts the current typed contract and rejects unknown fields; it does not choose a parser by version or promise compatibility with arbitrary older or newer inputs.

Schema filenames describe their roles and have no version suffix. Only the current snapshots are shipped; the application release tag identifies their exact contents, and development builds additionally need their source revision. Schema changes follow the application release policy instead of a separate format counter. The JSON Schema $schema URI identifies the standard schema dialect, not an APEX data-format version.

The runtime parses Rust types and performs semantic checks; it does not load these schema files when scheduling. Editors and integrations can use the files for structural validation. apex schema and the agent tool schema.get generate descriptions from the installed build's types. An agent can request a named definition through schema.get instead of loading all three schemas into context.

From source data to a schedule

flowchart TD
    Orders["Orders + workplans + shared problem header"] -->|"Optional production expansion"| Problem["Scheduling problem with concrete operations"]
    Direct["Adapter supplies concrete operations + shared facts"] --> Problem
    Problem -->|"Optional material.prepare"| Prepared["Prepared problem: fixed allocation or flexible allocation policy"]
    Problem -->|"Without separate preparation"| Schedule["Scheduling: choices, calendars and material availability"]
    Prepared --> Schedule
    Options["Planning options or defaults"] --> Schedule
    Schedule --> Validation["Independent result validation"]
Loading

Choose one input path. Orders and workplans go through production.import or CLI apex expand, which generates lots and operations while retaining the shared factory facts. Continue with the returned scenario or expanded problem. Do not import another independently maintained problem for the same work.

Existing operations from an ERP/MES or adapter go directly into a complete Problem, through problem.import, chunked import or the CLI planner. This skips only production expansion. The adapter owns lot sizing, operation identities, quantities, dependencies and any alternative routes; APEX does not split those tasks into more lots. Supply jobs and orders when grouping and their completion metrics are needed; ungrouped tasks are supported. Both paths still need resources, calendars, processing requirements and the relevant inventory, receipts and material maps.

An operation (Task) is concrete work; a workplan is a template for generating it. Scheduling rules constrain or rank that work and apply with either input path. Supported rules belong in the problem, including its typed planning block. Supplying rules does not replace operations, calendars or material facts, create lots or trigger material preparation. Planning options configure a run rather than replace persistent business rules; see declarative scheduling.

After either import path, optionally request material preparation to bind existing supply to consumers. Production expansion creates the lots; material preparation allocates supply to their operations. Scheduling then places operations against calendars and material availability and independently validates the result. Skipping separate preparation still leaves the normal material constraints active.

These tool names refer to the engine-facing apex service. The control platform stores the resulting scheduling problem as scenario facts and invokes the same engine.

Relationships and mapping

Source concept Canonical representation Decision freedom / enforcement
Production order Order references jobs Order readiness is the latest job readiness; due date is soft, deadline hard
Production lot Job with item, quantity, due/deadline/priority One or more operations reference Task.job; job readiness is the latest active task's product readiness
Alternative routing RouteChoice with named alternatives Exactly one alternative per choice; each controls task presence and its additional dependencies
Operation Task with quantity, modes, family, source Optional route membership; otherwise mandatory; mode and resource choices remain decisions
Machine/resource allocation Mode with primary resource and phases Main mode selects the complete allocation and its pre/post work and optional material overrides
Staffing/tooling Phase.requirements with amounts Simultaneous capacity requirements, including pools; explicit retention through interruptions
Shift/break/productivity Processing and retention calendars Available capacity and rate by interval; no work outside processing windows
Preparation/inspection/cleanup Task- or mode-specific pre and post activities Own resource alternatives, calendars and phase requirements; optional conditional DAG
Technological sequence Dependency Predecessor product readiness to successor main start, with min/max elapsed lag
Sequence-dependent setup Transition, sequence_pattern, native sequence hook Extra predecessor post-work / successor pre-work and independent penalty
Material availability Inventory, receipts, task or mode consume/produce maps Temporal balance by normalized item key; selected mode overrides the complete task map
Existing/running plan Execution, mode/resource/start/order locks Immutable actual work and explicit remaining work; separately selectable freeze dimensions
Factory-specific rule Typed rule or versioned CustomizationRef Shared construction, evaluation and independent validation semantics

Time values are integer seconds relative to the optional display epoch. Intervals are half-open. Work is normalized productive seconds; resource rates affect elapsed time. Source adapters normalize timezones and physical units and preserve provenance in Task.source. A machine identifier, family or workplan ID does not acquire special meaning from its spelling.

Routes and presence

{
  "id": "JOB-1/routing",
  "selected": null,
  "alternatives": [
    { "id": "standard", "tasks": ["cut", "assemble"], "dependencies": [{ "before": "cut", "after": "assemble" }] },
    { "id": "external", "tasks": ["subcontract", "assemble"], "dependencies": [{ "before": "subcontract", "after": "assemble" }] }
  ]
}

Tasks may be shared by alternatives of the same choice. A task cannot belong to two different choices. Nonmembers are always active. Edges whose endpoints are inactive are removed; selected alternative edges are added to the active graph. Use explicit alternative edges when a dependency changes with the route. This is guarded presence, not automatic substitution of an absent predecessor with another task.

selected pins an alternative in the input. Planning options also accept route_choices and mode_choices. Locked, running or explicitly mode-selected tasks must remain active. Contradictory choices fail. The active graph is checked for cycles; readiness validation does not enumerate all combinations of routes or prove feasibility of every combination.

XG initially favors the route with the lowest estimated work. XH varies route/mode choices with reproducible seeds alongside dispatch strategies. Selection is heuristic, not exhaustive optimization.

Quantities, workplans and orders

For each phase, required work is work + task.quantity * work_per_unit. Either term can be omitted; both absent is MISSING_PROCESSING_TIME. The fixed term occurs once per operation/lot, including setup if modeled there. Use explicit conditional activities when setup has different resources, calendars or sequence semantics.

Canonical consume/produce values are already total quantities for that task. Setting Task.quantity does not multiply these maps again. By contrast, workplan template material values in ProductionInput are per unit and are scaled during expansion. Template task quantity is a multiplier on lot quantity. $job in a material key becomes a lot-specific key, preventing accidental sharing of internal work in progress across lots.

ProductionInput contains a shared problem header, reusable workplans, and demands. The header carries the planning horizon/epoch, resources and their calendars, opening inventory, confirmed receipts, and applicable rules and objectives. Only the generated collections (tasks, jobs, orders, routes and dependencies) must be empty; expansion rejects pre-existing entries in them. The adapter supplies these shared facts once, and expansion retains them while adding concrete work. It does not merge two independently maintained scheduling problems or fetch missing calendars or material from external systems.

Each demand chooses permissible workplans and an optional max_lot. Expansion conserves the last lot's remainder, produces stable order/job/task identities, and keeps alternative workplans selectable. predecessors names supply orders and expands completion-before-start dependencies across their tasks; it is an all-order relationship, not automatic partial-lot pegging.

For example, one demand for 25 units with max_lot: 10 produces lots of 10, 10 and 5 units. With one two-operation workplan, this creates six operations. Without max_lot, that demand becomes one lot. This is explicit quantity expansion, not economic lot-size optimization.

Use production.import directly, or:

apex expand customization/demo/model/production-orders.json --out .apex/production-expanded.json
apex plan .apex/production-expanded.json --out .apex/production-schedule.json

Job completion aggregates active task product readiness, not just main processing end. Order completion aggregates its jobs. job_weighted_tardiness and order_weighted_tardiness count each respective group once. Explicit objective declarations control the score; when omitted, tardiness defaults to orders, then jobs, then tasks, followed by makespan. A member task inherits its job's priority; missing task due dates inherit the job due date, then the order due date. Job/order deadlines constrain all member tasks.

Expansion does not infer BOMs, units, yield or economic lot sizes from ERP data. Source adapters must supply these facts. The separate material.prepare step allocates declared existing supply after expansion; see material preparation. Running execution is imported as canonical tasks, not copied through templates. This is not a raw v2 JSON importer.

Conditional activity graphs

Task.pre/post applies across modes. Mode.pre/post applies only when that main mode is selected. owner_resource records and validates the associated main-mode requirement; it does not implicitly reserve that resource for the conditional. The conditional's own phases declare actual occupancy.

{
  "id": "join-preparation",
  "after": [
    { "before": "tool-preparation", "min_lag": 0 },
    { "before": "program-loading", "min_lag": 0, "max_lag": 600 }
  ],
  "modes": [{ "id": "inspect", "primary": "INSPECTION", "phases": [{ "id": "check", "work": 30, "requirements": [{ "resource": "INSPECTION" }] }] }]
}

after omitted/null preserves serial list order. after: [] creates an independent branch within the stage. Explicit dependencies reference another conditional ID in the same active pre or post stage. Pre branches must finish before main work; post branches begin after main work. releases_product: true makes post completion part of product readiness. Other post-work can continue after release. Resource reservations and readiness are separate, so independent inspection need not block the original machine.

Nested conditional modes with their own pre/post or material overrides are rejected. Cross-task links target task readiness/main start, not arbitrary internal activity endpoints. Represent independent cross-task operations as ordinary tasks. This boundary is explicit; the model is not an unrestricted temporal event language.

Sequence context and customizations

Transition tables match neighboring families on a primary resource and separately declare penalty, previous_post and next_pre. Required initial/final transitions and terminal cleanup remain enforced. sequence_pattern rules match a family suffix ending at the current task, allowing effects beyond one neighbor. setup_penalty is distinct from processing duration, transition work and mode cost.

Native customization hooks receive the complete selected primary-resource sequence and can add activities and charges. They also provide model lowering, dispatch rank, extra objective metrics and hard result validation. Independent validation reconstructs the context, regenerates decorations and recomputes metrics. The linked demo@1 policy is a synthetic example; unknown versions fail explicitly.

Markdown records the domain knowledge and counterexamples. It is not executable code. A coding agent can extend the Rust customization, registry, tests and optional UI, then rebuild. Existing typed attribute objectives automatically create a dispatch signal; arbitrary new objectives still need an explicit heuristic implementation and quality tests.

Locks, pauses and diagnostics

Processing calendars, retention calendars, rates, interruption policy, phased staffing, running/restart work, material readiness, temporal lags and terminal effects share the same construction and validation semantics. scenario.freeze accepts global until and until_by_resource; a resource override replaces the global cutoff before task selection. Freeze dimensions are mode, resource, main start and relative order. Consecutive resource blocks prevent interleaving while allowing time gaps and mode alternatives on that resource.

Unknown fields, unknown references, cycles, missing processing work and incompatible selections are explicit diagnostics. Estimates must be supplied and recorded; no missing parameter is silently invented. Successful construction always passes independent validation. Failed construction is not a mathematical infeasibility proof.

Objectives, queues and replay

Location Fields and purpose
Problem queue_policy, queue_definitions, freeze_zones, planning, material_policy
Task stage (JSON default default) and hard conditional_modes commitments
Objective metric, weight, priority, maximize (default false), scale (default 1)
Options Staged Q policy, route/main/conditional choices, decision prefix/order, XH, XT, combined-improvement and XE settings
Schedule Replay options, actual construction order, search evidence, objective values and material allocation report

tardiness is the unweighted sum of task lateness in seconds. For compatibility, on_time_delivery counts due-dated tasks completed on time. The explicit task_on_time_delivery, job_on_time_delivery and order_on_time_delivery metrics use fractions as described in the KPI catalog. Never silently map a legacy delivery percentage to a count.

The search contract specifies directions, scales, queue semantics, limits and reproducibility. Example staged policy:

{
  "normalization": "robust",
  "candidate_limit": 64,
  "stages": {
    "*": { "deadline_interval_fit": 4, "apparent_tardiness": 4, "setup_penalty": 1 },
    "assembly": { "shortest_work": 2, "slack": 4 }
  }
}

A Q ranks candidates; it is not a hard constraint. Mandatory production rules belong in typed constraints, locks, dispatch policies or validated native hooks. decision_prefix is a hard choice; decision_order is a soft task-priority order decoded under those rules. See direct schedule evolution for the latter's search and replay contract.

Material allocation

material.prepare allocates existing stock, confirmed receipts and declared production output. It preserves free workplans and differing-material main modes with material_policy: "reallocate_routes"; each complete evaluation allocates supply after its actual route and material-mode selection. The saved allocation report is independently reconstructed during validation.

A flexible model's preparation report is a preview, not the final allocation. Fully selected routes and material modes use the materialized-snapshot contract. Exact workflow, quantities, source preference and re-preparation rules are documented in material preparation. No missing production or purchase orders are generated, and pegging itself is not globally optimized.

Urgency through job and order chains

The core derives two dispatch signals per active task: the earliest relevant due date and the highest priority. Tasks within a job share urgency. Explicit job/order dates and priorities contribute, even when the operation has a more relaxed date. Signals propagate backwards over physical dependencies, including actual material-allocation links. Resource sequence locks do not propagate demand urgency.

This affects initial ranking, due/slack/priority/apparent-tardiness Qs, material preparation ordering and urgency exceptions in mandatory policies. Native Q hooks receive Context.dispatch_urgency. task.inspect returns dispatch_urgency separately from the original task.

Business dates and priorities are not overwritten by this propagation. Final task/job/order metrics retain their existing due-date semantics. This is not critical-path backward date scheduling: the propagated date does not subtract all downstream duration, calendars or lag. The existing remaining-work proxy supplies a separate estimate. An explicit new chain-slack metric would need its own semantics and validation.

Searchable conditional resource alternatives

Each conditional already declares modes, including its resources, work, calendars and resource-retention requirements. An optional hard commitment selects a mode:

{"conditional_modes": {"pre:setup": "independent-technician"}}

This field belongs to a Task. A scenario patch uses {"kind":"conditional_modes","task":"PRODUCE-FAST","choices":{"pre:setup":"independent-technician"}}; the map replaces that task's conditional commitments. An empty map removes those commitments. Existing resource/mode/start/order locks remain separate.

Search/replay options use conditional_choices: {"PRODUCE-FAST":{"pre:setup":"independent-technician"}}. Keys are exact activity suffixes: pre:ID, post:ID, restart:ID, transition:TRANSITION:pre:ID / post:ID, and pattern:RULE:pre:ID / post:ID. Unknown choices, conflicting commitments, absent activities and incompatible routes fail explicitly. A commitment to a task in a route requires that task to remain active. A main mode must support the selected mode-specific conditional.

  • Quick planning: uncommitted conditionals retain the local earliest-finish choice.
  • XH: optional conditional-mode genes join staged Qs and workplans. Mutation changes one unprotected conditional mode with probability 0.6 when such alternatives exist; crossover exchanges per-task conditional maps. Main-mode/sequence-dependent choices may be infeasible and then count as failed evaluations. Input and explicitly supplied option commitments are protected.
  • XT: branches on actually present uncommitted conditional alternatives in the selected prefix, then on subsequent task/main-mode decisions. Conditional branching also works at the configured task-prefix depth boundary. The full evaluation/time limits still apply.
  • Combined improvement: carries conditional choices from XH/incumbent into XT seed policies. Those choices define that XT branch's policy; another portfolio seed can explore other alternatives. The optional XE also evolves conditional choices under the same hard commitments; see direct evolution.

Full decoding, mandatory dispatch policies, replay and independent validation enforce the choices. Static alternatives created by a native compile hook are searchable. Sequence-generated alternatives are searchable when a native Customization::conditional_modes hook declares a stable catalog in advance. The declaration does not create the activity: decoding must produce the selected activity and mode, or evaluation fails. Undeclared sequence-generated alternatives remain local decoder choices. See the native extension contract.

KPI catalog and units

model.page {schedule_id, section: "metrics", offset: 0, limit: 40} lists values, units and proxy status. The viewer's collapsed All KPIs section reads this endpoint. No new planning controls are required. Saved custom metrics are included with extension_defined units unless the built-in catalog defines them.

Family Metrics Semantics
task_, job_, order_ tardiness, max_tardiness, late_count, due_count, on_time_delivery, flow_time Completion uses product readiness; tardiness/flow in seconds. Group flow starts at the earliest release of its participating active tasks.
Delivery fraction *_on_time_delivery On-time entities divided by entities with an explicit applicable due date. No due entities yields 1; inspect *_due_count to distinguish an empty denominator. Existing on_time_delivery remains a task count for compatibility.
Conditional operations conditional_time, conditional_mode_cost, total_mode_cost Productive conditional segment seconds, excluding pauses; sum of selected conditional mode costs; main plus conditional mode cost.
resource:ID: makespan, productive_time, occupied_time, available_time, utilization, utilization_7d Makespan is last reservation end. Productive time counts main/actual processing × required capacity. Occupied time also includes preparation and retention. Capacity-time denominators use positive-rate calendar capacity.
Resource utilization utilization, utilization_7d Productive capacity-seconds / available capacity-seconds. First uses [0, resource makespan]; second uses [0, min(horizon, 604800)]. Zero available capacity yields 0. These are not OEE or throughput efficiency.
stage:ID: tardiness, conditional_time, processing_time, utilization_mean, utilization_stddev Time sums for active tasks in that stage; mean/population deviation of the utilization of the primary resources actually used by that stage. Shared-resource utilization includes its other stages too.

All built-ins can be explicit objectives with direction, weight, priority and scale. Exact evaluated metrics determine fitness. New group-delivery/max-lateness/count proxies are experimental, reusing local due/slack/short-work signals. The held-out diagnostic exposes counterexamples. Resource utilization and conditional/total mode-cost objectives have no automatic standard proxy; unmapped remains visible. Adding a metric does not manufacture a well-correlated Q.

Schedules carry metric_version: 1. Validation requires the expanded KPI set and detects corrupted values. Version-0 stored schedules may omit the new metrics. JSON parsing enables exact floating-point round trips, including fractional objectives and native extension metrics.

Reproduce a chat-first scenario

  1. Import the synthetic chain model with problem.import.
  2. Call material.prepare and retain the returned scenario ID. Routes remain free.
  3. Use schedule.create or schedule.improve with a bounded budget.
  4. Inspect PRODUCE-FAST: its business due date is 800, while the downstream order produces derived due 75 / priority 9.
  5. Page actual material links and KPIs, then open the returned viewer link.
  6. Fork before a what-if commitment to a different setup technician. Replan, validate and compare against the original saved result.

An adapter maps source operation resources to conditional modes and BOM lines to explicit operation quantities. An agent can create this input artifact, but missing work, units or unsupported semantics require a diagnostic or an explicit modeling decision.