Material Preparation
Published from the source document. Propose an edit through a pull request; direct wiki edits are replaced by the next publication.
APEX separates quantity/lot expansion, material allocation and finite-capacity scheduling; see the overall planning workflow. The material.prepare tool allocates existing usable stock, confirmed receipts and outputs of supplied production operations. It never creates lots or generates procurement proposals, forecasts, replenishment quantities or missing manufacturing orders.
- In
ProductionInput, workplan task and mode material maps are per unit. Expansion multiplies by lot quantity and template task quantity.$jobgives job-local intermediate item IDs when needed. - In canonical
Problem,consumeandproducecontain total quantities for that operation. Modes may override them. Do not infer yield/output from processing time or automatically treat a job's item label as a supply quantity. - Map released-order BOM requirements onto the consuming operations. Map actual outputs onto their producing operations. A multilevel BOM is represented by successive output/input relationships among the supplied orders. Material-only master BOMs without released production orders do not cause order creation.
-
inventorymust be usable opening stock after external reservations.receiptsare confirmed available quantities/times, not hypothetical purchase proposals. Already allocated external production output must be represented as unavailable/net supply by the source adapter; there is no separate external-reservation object yet. - Missing processing times remain blocking input diagnostics. Missing material causes diagnostics in the preparation preview or blocks a fully selected allocation. Units must be normalized before import.
Production expansion preserves resources, calendars, opening stock and confirmed receipts from the input's shared problem header and scales the workplan material maps to operation totals; see production input. Neither production.import nor apex expand automatically invokes material.prepare. The explicit preparation step runs after concrete operations exist and before scheduling. It allocates supply to consumers; calendar-aware placement happens during scheduling.
- Import canonical tasks or expand production templates.
- Leave route and differing-material main-mode alternatives free, or supply
options.route_choicesandoptions.mode_choicesto pin them. Fixed and started choices cannot be overridden. - Call
material.preparewithscenario_id,expected_revisionand optionaloptions. These use the narrowerDispatchOptionscontract (route/mode selections), not the full planning-options schema. - The result gives a new scenario, allocation count, added dependency count and
report_id. For flexible routes or material modes, this report is a preview; inspectallocation_previewandpreview_diagnostics, then page actual saved allocations throughmodel.page/materials. The original revision is unchanged. Pageartifact.readwithpointer: "/allocations"to inspect consumer, item, quantity, stock/receipt/producer source, receipt index and timing. - Use
schedule.createorschedule.improveon the prepared scenario; validate and compare as usual. Flexible models reallocate supply after each actual route and material-mode selection, while material-identical machine modes retain their resource choices. New internal tokens ensure another dispatch order cannot steal a quantity reserved to a particular consumer.
| Material path | When allocation happens | What scheduling enforces |
|---|---|---|
No explicit preparation and no material_policy
|
There is no separate consumer-specific allocation pass. | The normal decoder checks material balances and availability as it places operations in dispatch order; independent validation checks the result. |
| Preparation with all routes and material-relevant mode choices fixed |
material.prepare assigns supply and creates a materialized problem with internal allocation tokens and precedence edges. |
Those allocations bind the prepared snapshot and are enforced during scheduling and validation. |
| Flexible routes or modes with different material requirements | Preparation keeps alternatives open and sets material_policy: "reallocate_routes". Its initial report is a preview. |
Allocation runs again after actual route/material-mode choices are resolved for each evaluation, before placement. Saved schedules carry their actual allocation report. |
This is the same for expanded production orders and directly imported operations. Simply importing either input does not enable the separate allocator. A problem carrying material_policy: "reallocate_routes" activates allocation during evaluation; general engine readiness checks alone do not. Skipping separate preparation does not disable material constraints.
Materialized snapshots retain physical material maps and add internal @apex/pegging/… balances and precedence edges; those tokens are not new physical items. Preparing an already prepared scenario is rejected. Material/routing edits to a materialized snapshot require preparing the original input again; never manually edit the internal tokens. Flexible models reallocate during evaluation after typed scenario changes. Goals and calendars may be varied on either kind of prepared scenario.
Readiness considers explicit predecessors and currently allocatable material. Ready tasks are examined by derived chain due date, then descending chain priority, then stable input order. Pending production is exhausted before falling back to late receipts. Multiple sources may supply one consumer and one producer may supply several consumers. No unbounded recursive BOM walk is used; cyclic and blocked networks produce diagnostics. Due dates are not silently rewritten upstream.
The policy is deterministic and conservative. It is not an optimal global pegging algorithm and may require another allocation/routing choice for a difficult instance. MATERIAL_UNRESOLVED reports shortages or blocked/cyclic supply; it does not prove global infeasibility. Preparation is a whole-snapshot operation with a 10-million candidate-check guard, not a streaming optimizer. Large imports still use files/chunks and bounded reports, while the model remains in server memory.
Running operation input is treated as consumed before the snapshot, matching current core semantics. Its output becomes available only after remaining work and required post-work. Partial output already in stock must be represented by the adapter without double-counting the future output.
The migration audit records the comparison with the former v2 material dispatcher, intentional semantic differences and remaining acceptance work. Existing-supply allocation does not establish complete legacy preprocessing or search equivalence.
APEX documentation
Use APEX
- APEX documentation
- Rust implementation and operating guide
- Chat-led scheduling
- Agent integration
- Server configuration and customization packages
- Start APEX with Docker Compose
- Control platform
- MCP App insights and customization views
Reference
- Executable scheduling data model
- Material preparation: scheduling, not MRP
- Search and objectives
- Combined improvement
- Direct schedule evolution
- Declarative scheduling
Development and evidence
- Current architecture
- Demo model boundary
- Migration audit: legacy v2 to Rust
- Source distribution
- Wiki publication
- Repository layout and distribution
Licensing