Date: 2020-02-07
Duration: 12:00-1:15
Present: Basile Fengos, Adam Richard, Patrick Godbout, Chris Sotirakos, Michael Nareg Arabian
Absent: No absentees
What was done
- It was decided that user stories were to be divided into sub tasks to facilitate work distribution.
- Made sure everyone's development environment was set-up and ready to use.
- Reorganized which tasks were to be completed for sprint 2 (registration, login, image uploaded); some user stories were pushed back to sprint 3, but their tasks will be started early in sprint 2.
- Decided that Firebase will be the database used moving forward.