Current Responsibilities

schweize8940 edited this page Oct 28, 2019 · 39 revisions

Welcome to the GroupProject wiki!

Current Work to be done is

Till Halfway: 3 Sprints. In order to get to the halfpoint mark of our product backlog we need to have 7 Story points done per sprint

1st Sprint:21-27th

US 01.01.01 As a participant, I want to add a mood event to my mood history, each event with the current date and time, a required emotional state, optional reason, and optional social situation so that I can keep detailed track of my moods. - Nicholas - Done

US 01.02.01 As a participant, I want consistent emoticons and colors to depict and distinguish the emotional states in any view so that I can at a glance easily see what my moods have been like recently. - Maria Done

Profile US 03.01.01 As a user, I want a profile with a unique username so that I can access specifically my own moods. - Chris Mostly

UI Storyboard Redesign - Tim Done

UML Redesign - Ansh

Total: 7 Points

2nd Sprint: 28th-3rd

3rd Sprint:4th-8th

Done

Have these 4 things done by next monday, 14th. Has to be done by the 18th at 5pm
Product Backlog: Tim - Done (Monday)
https://github.com/CMPUT301F19T03/GroupProject1/wiki/Product-Backlog User Interface Mockups and Storyboard Sequences: Tim, Maria - Done (Monday)
https://github.com/CMPUT301F19T03/GroupProject1/blob/master/doc/Storyboard.png Object-Oriented Analysis: Chris, Allen, Ansh
https://github.com/CMPUT301F19T03/GroupProject1/blob/master/doc/301Project2UML.PNG Glossary and Information Sources: Nicholas https://github.com/CMPUT301F19T03/GroupProject1/wiki/Glossary