This documentation outlines the Windows 11 Deployment Project conducted by me at multiple HCA Healthcare locations. The project simply involved upgrading existing workstations from Windows 10 to Windows 11, ensuring a seamless transition and minimal disruption to daily operations.
- Start Date: [07/17/2023]
- End Date: [07/18/2023]
- Worked on 24 workstations
- Limited network bandwidth slowed the download and installation process.
- Compatibility issues with older hardware required additional troubleshooting.
- Successfully upgraded all workstations within the allocated time frame.
- Implemented pre-configured settings to streamline user experience.
- Importance of pre-assessment for hardware compatibility.
- Improved communication with end-users mitigated resistance to change.
- Start Date: [07/21/2023]
- End Date: [07/22/2023]
- Worked on 37 workstations
- Software conflicts required manual resolution on several machines.
- Temporary service interruptions during the deployment process.
- Developed a step-by-step guide for end-users, minimizing disruptions.
- Implemented a rollback plan for unforeseen issues, ensuring business continuity.
- Comprehensive software inventory is crucial for anticipating conflicts.
- Proactive communication minimizes end-user concerns.
- Start Date: [07/24/2023]
- End Date: [07/24/2023]
- Worked on 8 workstations
- Limited hardware resources on some workstations required adjustments.
- Antivirus conflicts resulted in temporary service disruptions.
- Implemented hardware upgrades where necessary to meet Windows 11 requirements.
- Collaborated with antivirus vendors to resolve conflicts and ensure smooth operation.
- Pre-assessment of hardware resources is crucial for a seamless deployment.
- Maintaining open communication with vendors helps resolve software conflicts promptly.
- Start Date: [07/24/2023]
- End Date: [07/26/2023]
- Worked on 54 workstations
- Network firewall restrictions impeded the deployment process.
- User resistance due to lack of awareness and communication.
- Collaborated with IT security to adjust firewall settings for smoother deployment.
- Conducted user training sessions to address concerns and encourage collaboration.
- Proactive communication and user training are critical for user acceptance.
- Engaging with IT security early in the project helps prevent unexpected roadblocks.
- Start Date: [07/28/2023]
- End Date: [07/31/2023]
- Worked on 63 workstations
Legacy software incompatibility issues required additional troubleshooting. Limited availability of on-site staff for user communication and support.
Implemented a phased deployment approach to minimize user disruptions. Successfully addressed software compatibility issues with custom scripts.
- Importance of thorough testing for legacy software compatibility.
- Improved coordination with on-site staff for enhanced user support.
- Consistent challenges included bandwidth limitations and unforeseen software conflicts.
- Coordination with on-site staff proved essential for efficient problem resolution.
- Standardized deployment procedures improved efficiency.
- End-user education reduced resistance and enhanced overall user satisfaction.
- Continuous monitoring and communication are vital for successful deployment.
- Regularly updating deployment strategies based on lessons learned is essential.
The Windows 11 Deployment Project was successfully executed across HCA Healthcare multiple locations, reflecting my adaptability and problem-solving skills. The challenges encountered provided valuable insights, contributing to the continuous improvement of future deployment projects. The positive outcomes demonstrate the effectiveness of a well-coordinated and communicative approach to large-scale system upgrades.