Talk about scheduling and timeline -- when are our goals for MVP deployed, when do we want fuller version in use, when do we want to just be occasionally logging in to fix bugs?
Figure out benchmarks / milestones to strive for, to orient the project work on dev side
** 1m and 3m goals for code side
** 1m and 3m goals for design side
Discuss prelim testing plan
** User testing
** Unit / Integration
Discuss any git issues tagged in-person
For Mollie/Colin:
Are current co-lead arrangements going okay?
Is there anything we need from the CM corps generally?
Is there anything we need from Jenn and Lisa?
Notes from mtg:
MVP - replication of what we have at present -- getting CMs to enter the data and being able to spit out a CSV for dumping into the shared spreadsheet.
Two weeks of testing on one line. Would like to be on call / co-ride with a CM and sit with them while they do their calls.