๐Ÿ—บ๏ธ Production Readiness Roadmap

Executive Summary

This roadmap consolidates all technical debt and implementation gaps identified in the comprehensive audit. Following this plan will transform ModularHomeInventory from a prototype to a production-ready iOS application.

๐Ÿ“Š Current State Metrics

  • Test Coverage: 0% (target: 80%)
  • Critical Issues: 6 epics, 20+ sub-issues
  • Estimated Timeline: 8-12 weeks with 2-3 developers
  • Business Impact: Currently unusable in production due to data loss

๐ŸŽฏ Implementation Phases

Phase 1: Critical Foundation (Weeks 1-3)

Goal: Fix data persistence and security

Phase 2: Core Features (Weeks 4-6)

Goal: Complete essential functionality

Phase 3: Quality & Polish (Weeks 7-9)

Goal: Production-quality UX

Phase 4: Optimization & Testing (Weeks 10-12)

Goal: Performance and reliability

๐Ÿ“ˆ Success Metrics

  • Week 4: Data persists, tests compile
  • Week 8: All core features working
  • Week 12: 80% tests, <100ms operations

๐Ÿš€ Deployment Criteria

Before TestFlight release, must have:

  • Data persistence working
  • Security vulnerabilities fixed
  • 80% test coverage
  • All placeholders replaced
  • Performance benchmarks met

๐Ÿ‘ฅ Resource Requirements

  • iOS Lead: Architecture, Core Data, security
  • iOS Developer: Features, UI/UX
  • QA Engineer: Test coverage, automation
  • Designer: Complete UI screens

๐Ÿ”„ Weekly Milestones

Week Focus Deliverables
1-2 Core Data Persistence working
3-4 Security Biometric auth, PIN removed
5-6 Services CloudKit, Gmail, StoreKit
7-8 UI/UX All screens functional
9-10 Testing 80% coverage achieved
11-12 Performance Optimization complete

๐Ÿ“ Notes

  • This roadmap assumes full-time development
  • Priorities may shift based on user feedback
  • Each phase has Go/No-Go criteria
  • Regular stakeholder updates required

๐Ÿ”— Related Documents

  • Technical Audit Report
  • TESTING_ARCHITECTURE.md
  • Original requirements

Track Progress: Follow the epic issues for detailed status
Questions: Reach out to the development team

Metadata

Metadata

Assignees

Labels

P0Production blocker - must fix immediatelydocumentationImprovements or additions to documentationepicEpic issue tracking multiple sub-tasksroadmapProduct roadmap and planning

Projects

No projects

Milestone

No milestone

Relationships

None yet

Development

No branches or pull requests

Issue actions