refactor(pmo-pert): 4-sheet output, PD-only effort, PMI-correct MR#7
MrBogomips merged 9 commits into
mainfrom
worktree-feature+pmo-pert-refactor

Conversation

@MrBogomips
Copy link
Copy Markdown
Owner

Summary

Refactor of the pmo-pert-estimate skill: the generated workbook is now a
4-sheet PMI-compliant deliverable — WBS · Resource Plan
(Pianificazione Risorse) · Risks (Rischi) · Summary (Riepilogo)
— with
PD as the single effort unit, correct Management Reserve base, native
PM/DevOps overhead, calendar-aware duration, and i18n-ready labels.

Why

Five issues observed in real-world usage drove the refactor:

  1. Resources sheet held % allocations presented as effort → caused
    meaningless Summary rollups (e.g. "Effort by Team = 2400" from
    summing percentages).
  2. Total PERT Duration summed leaf durations sequentially
    over-stated calendar duration by 2–3× when phases ran in parallel.
  3. Management Reserve was Contingency × pct, not
    (Tech + Overhead + Contingency) × pct → violates PMI PMBOK §4.3.
  4. Timeline (sequential Gantt) wasn't actionable — no dependencies,
    no real parallelism, misleading for clients.
  5. PM and DevOps overhead had no native config — users had to hack
    them as fake WPs.

The 4-sheet layout, the new Resource Plan (role × week PD matrix), and
the correct MR base resolve all five issues at the root.

Key changes

  • New helpers: i18n.py (en/it labels), config_compat.py (legacy
    JSON detection + soft backfill with stderr warning),
    wb_pianificazione_risorse.py (role × week PD matrix).
  • Refactored: wb_summary.py (Fascia BASSA/MEDIA/ALTA, calendar
    duration, effort by team via WBS primary role, sensitivity scenarios),
    wb_risks.py (MR formula on WBS!H{total} × (1 + pm_pct + devops_pct) + Contingency).
  • New config fields (all optional, with defaults): pm_overhead_pct,
    devops_overhead_pct, alta_uplift_pct, calendar_total_weeks,
    phase.start_week/end_week, top-level scenarios[].
  • Removed: wb_timeline.py, wb_resources.py, and their test
    modules.
  • Backward-compat: legacy v1 JSON still produces a valid 4-sheet
    workbook with sensible defaults and a single stderr warning.
  • Docs: SKILL.md, references/excel-schema.md, references/workflow.md,
    references/template-criteria.md rewritten for the 4-sheet layout.
  • Examples: scenarios 1-5 regenerated with v2 fields; new
    anonymized scenario-6-pa-portal-integration (Italian, 8 phases,
    parallel build/integrations, 20% MR) added.
  • Template: assets/pert-template.xlsx regenerated from the
    v2 sample-input.json.

Test plan

  • Unit tests pass (135 tests, was 133 baseline + new modules - removed legacy)
  • Structural CI passes (bash tests/ci/run-structural-tests.sh)
  • E2E smoke: python3 generate_excel.py --input examples/sample-input.json --output /tmp/x.xlsx produces 4 sheets in canonical order
  • E2E smoke (IT): scenario-6 generates Italian sheet names (Pianificazione Risorse, Rischi, Riepilogo)
  • validate_template.py accepts the regenerated template (valid: true, no errors)
  • Legacy JSON (no v2 fields) still generates a valid workbook with stderr warning
  • All examples open and parse without #REF! errors
  • Reviewer: open one generated .xlsx in Excel/LibreOffice and verify Resource Plan totals match WBS!H{total} (±1 PD)
  • Reviewer: verify the Summary MR cell matches the Risks MR cell (cross-sheet consistency)

Foundation for the 4-sheet workbook refactor. The i18n module ships en/it
label dicts and a t(lang, key, **fmt) accessor; config_compat backfills
modern fields (pm/devops/alta uplift, calendar) on legacy JSON input and
emits a single stderr warning so users know they're on the old format.
Replaces the legacy Resources (%-allocation) and Timeline (sequential Gantt)
sheets with a single PD-based role × week matrix. Primary role per leaf is
activity.resources[0]; phase weeks come from phase.start_week/end_week or
fall back to a sequential layout sized by PERT duration. Cells flag
overcommit (>5 PD/week per role) in red and warn (>=4.5 PD) in yellow.
… calendar duration

- New rows: Tech PERT, PM Overhead, DevOps Overhead, Subtotal, Contingency,
  Fascia BASSA, Management Reserve, Fascia MEDIA, Fascia ALTA. MR is
  computed on the Fascia BASSA cell (Tech+Overhead+Contingency), no longer
  on Contingency alone (Issue #3, PMI PMBOK §4.3 compliant).
- Calendar Duration is a single explicit number derived from
  config.calendar_total_weeks or phase start_week/end_week (Issue #2).
  Sequential-sum CI Duration block dropped.
- Effort by Team computed from WBS primary role of each leaf in real PD,
  not as a %-allocation cross-ref to Resources (Issue #1).
- Sensitivity Scenarios listed as text rows when provided in config.
- Sheet name localized via i18n (Riepilogo in IT).
build() now accepts an optional wbs_info argument. When provided, the
Management Reserve cell uses the PMI PMBOK §4.3-compliant base:
=(WBS!H{total}*(1+pm_pct+devops_pct)+L{contingency_total})*mr_pct

When omitted (legacy callers/tests without WBS), the cell falls back to
the original =L{total}*pct formula. The pipeline (generate_excel.py) is
wired in the next batch to always pass wbs_info.
generate_excel.py now:
- routes JSON through helpers.config_compat.normalize_config() (legacy
  warning + default backfill);
- builds WBS, Resource Plan, Risks, Summary in that order;
- passes wbs_info into wb_risks.build() so the MR formula picks up the
  PMI-compliant base.

Risks sheet name is now localized (Rischi in IT). Summary cross-references
the Risks sheet by its actual name (single-quoted when needed). The
validate_template.py script and its tests accept the 4-sheet layout and
both English / Italian sheet-name aliases.
SKILL.md, workflow.md, template-criteria.md, excel-schema.md updated to
describe the 4-sheet layout (WBS, Resource Plan / Pianificazione Risorse,
Risks / Rischi, Summary / Riepilogo) and the v2 JSON schema fields:
pm_overhead_pct, devops_overhead_pct, alta_uplift_pct,
calendar_total_weeks, phase.start_week/end_week, scenarios[]. Includes a
migration example for legacy JSON, the PMI-correct MR formula, the
primary-role convention (resources[0]), and Resource Plan capacity rules.
…ation

- sample-input.json updated with v2 fields (pm/devops overhead, alta
  uplift, calendar_total_weeks, phase start_week/end_week, scenarios).
- Scenarios 1-5 backfilled with v2 defaults and phase weeks; xlsx
  regenerated against the 4-sheet generator.
- Scenario 6 (PA portal integration) added as an anonymized public-
  sector scenario in Italian (lang=it). Exercises overlapping phases,
  20% MR on the PMI-correct base, PM/DevOps overhead, and the alta
  uplift band — the new capabilities together.
- validation-summary.md rewritten to cover the 4-sheet layout and the
  five real-world issues that motivated the refactor.
…rate template

- Delete scripts/helpers/wb_timeline.py and scripts/helpers/wb_resources.py
  along with their test modules. Both modules implemented sheets that the
  v2 refactor removed (Issue #1 — Resources held % presented as effort;
  Issue #4 — Timeline Gantt was sequential and misleading).
- Regenerate assets/pert-template.xlsx by running the v2 generator on the
  updated sample-input.json so the bundled reference template matches the
  4-sheet layout.
- Test suite is green (135 tests) and the structural CI test suite passes.
- End-to-end smoke: sample workbook opens with 4 sheets, Resource Plan
  totals are =SUM formulas over per-week PD numerics, Summary shows the
  Low/Medium/High bands plus Calendar Duration = 12 weeks.
Copy link
Copy Markdown

@chatgpt-codex-connector chatgpt-codex-connector Bot left a comment

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

💡 Codex Review

Here are some automated review suggestions for this pull request.

Reviewed commit: 7d31d29514

ℹ️ About Codex in GitHub

Your team has set up Codex to review pull requests in this repo. Reviews are triggered when you

  • Open a pull request for review
  • Mark a draft as ready
  • Comment "@codex review".

If Codex has suggestions, it will comment; otherwise it will react with 👍.

Codex can also answer questions or update the PR. Try commenting "@codex address that feedback".

Comment on lines +286 to +289
starts = [int(p["start_week"]) for p in phases if "start_week" in p]
ends = [int(p["end_week"]) for p in phases if "end_week" in p]
if starts and ends:
return max(ends) - min(starts) + 1
Copy link
Copy Markdown

Choose a reason for hiding this comment

The reason will be displayed to describe this comment to others. Learn more.

P1 Badge Derive calendar duration from all phases

The starts/ends shortcut returns max(end)-min(start)+1 as soon as any phase has explicit weeks, which undercounts duration for mixed inputs where other phases omit start_week/end_week and are scheduled sequentially in the Resource Plan. In that case Summary can report a shorter calendar duration than the generated plan (e.g., one explicit phase W1–W2 plus one implicit 2-week phase still shows 2). This breaks the new calendar-duration metric and should fall back to rp_info["total_weeks"] unless every phase has explicit bounds.

Useful? React with 👍 / 👎.

@MrBogomips MrBogomips merged commit 0844a7d into main May 20, 2026
1 check passed
@MrBogomips MrBogomips deleted the worktree-feature+pmo-pert-refactor branch May 20, 2026 07:24
Sign up for free to join this conversation on GitHub. Already have an account? Sign in to comment

Labels

None yet

Projects

None yet

Development

Successfully merging this pull request may close these issues.

1 participant