CSIT analytics plan through July 31, 2026
Planning window
csitrepositoryContext
This plan defines the work required to publish clear, reproducible
analytics dashboards for
SLIM,Directory, andA2Afrom thisrepository. The emphasis is not generic benchmarking for its own sake.
The emphasis is:
This repository already contains the main building blocks needed for that work:
benchmarks/agntcy-slim/integrations/agntcy-dir/tests/integrations/agntcy-dir/tests/conformance/.github/workflows/test-integrations.yaml.github/workflows/publish-test-reports-pages.yamlintegrations/agntcy-a2a/integrations/agntcy-slim/kind-slim-multi-host/Objective
By 2026-07-31, produce a small but credible CSIT evidence package
that answers:
SLIM,Directory, andA2Avalue?analytics dashboard on GitHub Pages for
agntcy/csit, withdedicated views for
SLIM,Directory, andA2A?July exit criteria
The plan is successful only if all of the following are true by
2026-07-31:
SLIMbenchmarks,Directorytests and conformance, andA2Ainteroperability.documented and runnable.
human-readable analytics dashboard.
SLIM,Directory, andA2A.agntcy/csitrepository, not left only as workflow artifacts.
can review and contribute.
Scope
In scope
SLIM,Directory, andA2Ascenariosinteroperability runs
agntcy/csitOut of scope for this window
Workstreams
1. Scenario selection
Choose a small set of scenarios that answer what should be shown on the
published CSIT analytics site and why.
Target scenario set:
benchmarks/agntcy-slim/integrations/agntcy-dir/tests/its results in the analytics story
integrations/agntcy-dir/tests/conformance/can be published on GitHub Pages
integrations/agntcy-a2a/integrations/agntcy-slim/andkind-slim-multi-host/benchmark
2. Metrics and evidence
Define a short metric set that maps to user value.
Primary metrics:
Secondary metrics:
Metrics to avoid leading with:
3. Automation and reporting
Use the existing task structure as the default public interface.
Expected command paths:
task benchmarks:slim:benchmark:suitetask benchmarks:slim:reports:dashboardtask integrations:directory:testtask integrations:directory:tests:client-server:test:alltask integrations:a2a:testtask integrations:a2a:reports:dashboardintegrations/agntcy-slim/and
kind-slim-multi-host/Target reporting outputs:
SLIM,Directory, andA2Aartifactssite/directory/index.htmlscenarios
4. GitHub Pages publication
The authoritative July deliverable should be a static analytics site
published from the
agntcy/csitGitHub Pages setup that alreadyexists in this repository.
Relevant existing implementation:
.github/workflows/test-integrations.yaml.github/workflows/publish-test-reports-pages.yaml.github/workflows/test-benchmarks-slim.yaml.github/scripts/build-site-landing-page.shTarget publication model:
site/treesite/directory/index.htmlsource workflow runs
Target site structure by the end of July:
site/index.html: landing page for the published analytics sitesite/a2a/index.html: A2A interoperability dashboardsite/directory/index.html: Directory conformance dashboardsite/benchmarks/slim/index.html: SLIM benchmark dashboardscenarios, key metrics, and main conclusions
5. Public planning and issue flow
The execution model should be:
Timeline
Phase 1: bootstrap and scope lock
2026-05-19 to 2026-05-31
Goals:
conformance flows, interoperability, and topology flows already
present
Deliverables:
docs/plans/Definition of done:
Phase 2: baseline automation
2026-06-01 to 2026-06-14
Goals:
reproducible
three dashboard areas
Deliverables:
Definition of done:
site/output is understoodPhase 3: SLIM distributed-topology evidence
2026-06-15 to 2026-06-30
Goals:
illustrates SLIM value
Candidate focus:
kind-slim-multi-host/integrations/agntcy-slim/Deliverables:
Definition of done:
Phase 4: tighten metrics and comparisons
2026-07-01 to 2026-07-17
Goals:
hard to consume
Deliverables:
SLIM,Directory, andA2AvalueDefinition of done:
Phase 5: publishable July package
2026-07-18 to 2026-07-31
Goals:
them implicit
Deliverables:
SLIM,Directory, andA2ADefinition of done:
to rerun it
Suggested issue breakdown
plan: maintain the execution plan and keep dates currentbenchmarks: stabilize the SLIM benchmark run path and report outputsdirectory: stabilize the existing Directory integration andconformance run paths and published outputs
interop: stabilize the A2A run path and report outputstopology: select and automate the July SLIM topology scenariometrics: define metric semantics and acceptance criteriadashboard: shape the Pages site, landing page, and cross-projectsummary view
docs: write the July summary and rerun instructionsDependencies and risks
Dependencies
conformance jobs, and interoperability suites
hand-fixing the setup each time
Risks
before the baseline paths are stable
project?" question for
SLIM,Directory, orA2Afragmented results
Risk response
afterthought on top of raw reports