Iteration 1
Pre-release
Pre-release
Main Achievements
Focused on establishing a foundational structure, including the repository organization, initial project documentation, and a basic understanding of the software architecture and tech stack. The team also set up essential development tools and outlined the risk management approach.
Closed Issues
-
Completed Tasks:
- Setup Tasks (No Story Points):
- Meet with CRIM regarding tech stack (#1)
- Create Google Drive to store documents (#2)
- Add necessary pages structure to the GitHub Wiki (#3)
- Tech Stack and Software Architecture Proposition (#5)
- Risks (#6)
- Legal and Ethical Issues (#7)
- Economic (#8)
- Personas (#9)
- Testing Plan and Continuous Integration (#11)
- Name Conventions (#12)
- Diversity Statement (#13)
- Infrastructure and tools (#14)
- Setup Tasks (No Story Points):
-
Expected Work vs. Actual Work:
- Pushed to Later:
- Overall Architecture (#15)
- This task was completed, but the stakeholder never responded, so it was pushed to Iteration 2 to wait for approval and officially close the task.
- Overall Architecture (#15)
- Pushed to Later:
Velocity and Contractor Estimate
-
Velocity Calculation:
-
Total Story Points for Closed Tasks: No specific story points were assigned for setup tasks. Estimated Velocity:
- Legal and Ethical Issues setup: ≈ 2 points
- Risks setup: ≈ 2 points
- Infrastructure and Tools setup: ≈ 3 points
- Other foundational tasks (Google Drive setup, CI/CD outline, Diversity Statement, etc.): ≈ 1 point each
- Total Velocity for Iteration 1: 10 points.
-
Total Story Points for Closed Tasks: No specific story points were assigned for setup tasks. Estimated Velocity:
-
Contractor Estimate:
-
Higher Complexity Tasks (≈ 2-3 points each):
- Legal and Ethical Issues setup: 5 hours
- Risks setup: 5 hours
- Infrastructure and Tools setup: 7 hours
-
Lower Complexity Tasks (≈ 1 point each):
- Meet with CRIM regarding tech stack: 2 hours
- Create Google Drive to store documents: 1 hour
- Add necessary pages structure to the GitHub Wiki: 1 hour
- Tech Stack and Software Architecture Proposition: 3 hours
- Economic setup: 2 hours
- Personas setup: 2 hours
- Testing Plan and Continuous Integration outline: 3 hours
- Name Conventions setup: 1 hour
- Diversity Statement setup: 2 hours
-
Total Estimated Hours:
- Higher Complexity Tasks: 17 hours
- Lower Complexity Tasks: 17 hours
- Total Hours: 34 hours
-
Estimated Cost: 34 hours x 35.50
$/hour = 1207 $
-
Higher Complexity Tasks (≈ 2-3 points each):
Contractor Estimate for Iteration 1: $1,207 CAD
Full Changelog: https://github.com/XavierGuertin/WildfireVisualizationProject/commits/iteration1