Iteration 2
Pre-release
Pre-release
Main Achievements
Delivered the project's infrastructure setup, including both frontend and backend frameworks with Docker and Nx for development efficiency. The initial CI/CD pipeline was configured, and the team aligned on issue tracking and task documentation standards.
Closed Issues
-
Completed Tasks:
-
Setup Tasks (No Story Points):
-
Expected Work vs. Actual Work:
- Accomplished as Planned: Tasks or user stories completed as expected.
- Pushed to Later:
- Class Diagrams (#16): Closed due to lack of concrete requirements, replaced by relevant diagrams like domain and flowchart diagrams.
- Define and document API endpoints for data interaction between frontend and backend (#42) (3 points): Pushed due to lack of precise requirements or dataset samples from the stakeholder.
- Closed (Requirements Changed):
Velocity and Contractor Estimate
-
Velocity Calculation:
-
Total Story Points for Closed Tasks:
- Completed Tasks with Story Points:
- Setup Tasks without Story Points (Estimated):
- Establish ReadMe (#4): 1 point (low complexity)
- Overall Architecture (#15): 2 points (medium complexity)
- Update Testing Plan and Continuous Integration (#17): 2 points (medium complexity)
- Deployment Plan and Infrastructure (#10): 3 points (higher complexity)
- Total Estimated Points for Setup Tasks: 8 points
- Total Velocity for Iteration 2: 16 points
-
Total Story Points for Closed Tasks:
-
Contractor Estimate:
-
Estimated Hours:
- Tasks with Story Points: 8 points x ~3 hours per point = 24 hours
- Setup Tasks Estimate: 8 points x ~3 hours per point = 24 hours
- Total Estimated Hours: 48 hours
-
Estimated Cost: 48 hours * 35.50
$/hour = 1704 $
-
Estimated Hours:
Contractor Estimate for Iteration 2: $1,704 CAD
What's Changed
- #35 - feat(setup): Setting up project with Nx, containing NextJS, e2e testing, and Spring boot projects by @adissuu in #44
- #4 - docs(setup): Addition of initial readme by @im-samwong in #45
Full Changelog: iteration1...iteration2