Iteration 3
Pre-release
Pre-release
Main Achievements
Advanced the integration efforts, including containerizing services and setting up GeoServer, SonarQube, and PostgreSQL. UI mockups were created, and team members started implementing UI components in preparation for Release 1, despite midterms impacting progress.
Closed Issues
-
Completed Tasks:
-
Expected Work vs. Actual Work:
- Accomplished as Planned: Tasks or user stories completed as expected.
- Pushed to Later:
- Containerize GeoServer with Docker and ensure integration with backend services (#36) (5 points): Pushed due to changing requirements; rescheduled for Release 1.
- Set up unit testing framework for frontend and backend (#39) (3 points): Delayed due to PR processing time; pushed to Release 1.
Velocity and Contractor Estimate
-
Velocity Calculation:
- Total Story Points for Closed Tasks:
- Total Velocity for Iteration 3: 11 points
-
Contractor Estimate:
- Estimated Hours: 11 points x ~3 hours per point = 33 hours
-
Estimated Cost: 33 hours * 35.50
$/hr = 1171.50 $
Contractor Estimate for Iteration 3: $1,171.50 CAD
What's Changed
- #34 - feat(nx-cloud): setup nx workspace by @XavierGuertin in #50
- #37 - feat(docker): Setting Up Docker by @XavierGuertin in #49
Full Changelog: iteration2...iteration3