Iteration 3

Pre-release
Pre-release

Choose a tag to compare

@XavierGuertin XavierGuertin released this 10 Nov 21:27
353f869

Main Achievements

Advanced the integration efforts, including containerizing services and setting up GeoServer, SonarQube, and PostgreSQL. UI mockups were created, and team members started implementing UI components in preparation for Release 1, despite midterms impacting progress.

Closed Issues

Velocity and Contractor Estimate

  • Velocity Calculation:

    • Total Story Points for Closed Tasks:
      • Set up Docker environment for backend and frontend services (#37): 5 points
      • Create Mockups for the Wildfire Visualization Platform (#46): 3 points
      • Define and document API endpoints (#42): 3 points
      • Total for Story Pointed Tasks: 11 points
    • Total Velocity for Iteration 3: 11 points
  • Contractor Estimate:

    • Estimated Hours: 11 points x ~3 hours per point = 33 hours
    • Estimated Cost: 33 hours * 35.50 $/hr = 1171.50 $

Contractor Estimate for Iteration 3: $1,171.50 CAD