Iteration 6

Pre-release
Pre-release

Choose a tag to compare

@XavierGuertin XavierGuertin released this 20 Jan 23:19
5649aee

Iteration 6

Main Achievements

During this iteration, the team focused on expanding core frontend functionality to enhance user interaction and control. Highlights include:

  • Introducing a Load Dataset button in the Metadata panel, streamlining dataset selection.
  • Enabling users to modify endpoint settings directly in the UI for flexible backend configurations.
  • Adding a project license to clarify usage rights and project governance.

What's Changed


Velocity and Contractor Estimate

Velocity Calculation

  • Closed Tasks with Story Points:

    • #101 → 3 points
    • #100 → 3 points
      Total Story Points: 3 + 3 = 6
  • Setup Tasks (Estimated):

    • Create LICENSE: 0 point

Total Velocity for Iteration 6: 6 (story-pointed) + 0 (setup) = 6 points


Contractor Estimate

  • Estimated Hours:

    • Story-Pointed Tasks: 6 points × ~3 hours/point = 18 hours
    • Setup Tasks: 0 point × ~1 hours/point = 0 hours
    • Total Estimated Hours: 18 hours
  • Estimated Cost:

    • 18 hours × 35.50 CAD/hour = 639.00 CAD
    • Contractor Estimate for Iteration 6: $639.00 CAD

Full Changelog: iteration5...iteration6