Iteration 9

Choose a tag to compare

@XavierGuertin XavierGuertin released this 13 Feb 15:38
07c44ff

Main Achievements

Iteration 9 focuses on enhancing configuration management, data persistence, and addressing critical bug fixes to improve the overall user experience. Key highlights include:

  • Improved Configuration Management: Enhancements were made to configuration management, data persistence, and factory reset functionality, ensuring a more robust and user-friendly system.
  • Bug Fixes: Fixed issues related to the loading bar and load dataset functionality, as well as data display on the map to allow for quick alternation between different geometries.
  • Documentation Update: Added a video to the README to provide a visual overview of Release 2.

What's Changed


Velocity and Contractor Estimate

Velocity Calculation

  • Closed Tasks with Story Points:

    Total Story Points:
    10

Contractor Estimate

  • Estimated Hours:

    • 10 points × ~3 hours/point = 30 hours
  • Estimated Cost:

    • 30 hours × 35.50 CAD/hour = 1065.00 CAD
    • Contractor Estimate for Iteration 9: $1065.00 CAD

Full Changelog: release2...iteration9