I'm trying to translate the logic from our ERP (Tryton) to Frepple. To ease out the example, let's assume that all the things are done in the same location as the stock.
I have a bom list like:
And the routing steps are without any intermediate products, there are just a list with times and sequence / priority:
We don't have, and if it's possible we don't prefer to have intermediate products, that I'm sure it's the best aproach to consume in the union and also produce on the union. Did not have any problems creating the locations, demand, inventory, customers, employees.
For operationmaterial:
Also I have created the resources and operationresource relating the op_XYZ with time in each resource but I don't think are relevant by now, because the problem I found is not having any supply path on the item Personalized table XYZ. |
Beta Was this translation helpful? Give feedback.
Replies: 4 comments
-
If these are on the top routing operation, try moving them to the child step operation of the routing. |
Beta Was this translation helpful? Give feedback.
-
|
Following the proposal, I moved the materials to |
Beta Was this translation helpful? Give feedback.
-
|
I don't know as I can not see any guideline about how Frepple community expects to use the discussions, I mention you @jdetaeye to know if I should create a new discussion since now the problem is not about the same subject as the topic? |
Beta Was this translation helpful? Give feedback.
-
So I auto-reply me, I just need to use |
Beta Was this translation helpful? Give feedback.
If these are on the top routing operation, try moving them to the child step operation of the routing.