Period: 2026-07-10 — 2026-08-09 · Proposal: #82 (discussion) · Next unlock: 2026-08-13
Workstream A — DevNet infrastructure (M1: Setup)
gonka-devnet-community; live state on the status siteDelivered beyond the M1 bar:
1.0.0-alpha.1(net-deployment-runbook/) — reproducible baseline ontestnet-0.2.14(phased CLI: prepare → identities → qualify-ml → genesis → join → verify), governed0.2.14 → 0.2.15upgrade rehearsal, single-node stop/start/verify/reset, network reset contract. The M2 artifact "runbook sufficient to reproduce a node" (ROLE-JOIN.md) is already published.All images and binaries are pinned by digest; DevNet keys are fully isolated from mainnet.
Blockers encountered (documented and resolved)
0.2.14baseline. Resolved with a pinned hardware-runtime exception: a newer upstream MLNode runtime for that host only, while the chain release and model overlay stay on the baseline (documented in the runbook release profile).No hard procurement blockers were encountered during Month 1. One recurring friction: some datacenters and GPU neoclouds require KYC before activating servers, which adds delay to provisioning and slows down multi-provider deployment.
Workstream B — Testing lab (M1: Setup and QA onboarding)
Hiring. 60+ CVs screened, 8 candidates interviewed, one QA / infrastructure engineer hired, started on July 28. As part of onboarding he took on the DevNet deployment itself: the runbook, observability, and gateway work above; onboarding continues in Month 2. The search for the second engineer restarts in Month 2, likely with paid listing promotion; one candidate is in the pipeline and receives a test assignment once the DevNet stabilizes.
Incidents
The network spent most of the period in initial deployment and stabilization; instability during bootstrap was expected and was resolved as part of deployment work rather than tracked as incidents. Public monitoring is live (status site with per-node state and validator map, dashboards).
Spending (budget lines per proposal §14)
Infrastructure breakdown (paid invoices; receipts available for review on request):
gonka-dev.netregistrationMonth 2 plan (M2 targets)