Purpose
Define a repeatable testing flow for DevShard releases, with clear ownership and handover criteria. The flow covers development testing, parallel independent and internal validation, final sign-off, and release rollout.
Participants:
Flow Overview
flowchart TD A["Phase 1: Development and Feature Testing"] --> B["Release Candidate"] B --> C["Phase 2: TestLab Validation on DevNet"] B --> D["Phase 3: Internal Test and Validation"] C --> E["Final Sign-off"] D --> E E --> F["Governance Vote"]Phases 2 and 3 run in parallel against the same release candidate. Final sign-off requires results from both tracks for the candidate being released.
Phase 1: Development and Feature Testing
Owner: Dev team
During active development, the Dev team implements new functionality and runs:
Exit Criteria and Handover
Once development is complete, all required tests pass, and CI is green, the Dev team creates a release candidate Git tag. The tag automatically produces the binaries and container images used for testing.
The handover to TestLab and the internal validation team includes:
Phase 2: Independent Validation on DevNet
Owner: TestLab
TestLab deploys the tagged release candidate on DevNet and validates the release as a whole. The Dev team and TestLab agree on the test scope based on the changes and risks introduced by the release.
Common Test Scope
Bug Reports and Testing Tools
When an anomaly is detected, TestLab promptly provides the Dev team with a bug report containing the candidate tag, environment details, workload, reproduction steps, timestamps, full relevant log archives, metrics, and available profiles. The report should give developers enough context to investigate without repeating the initial evidence collection.
Use and maintain automated tooling for running tests, collecting logs and profiles, and comparing results with a baseline.
Operator Instructions
TestLab validates clear, step-by-step operator instructions by exercising the deployment, upgrade, verification, and rollback procedures on DevNet. Gaps found during testing are corrected before handover.
Exit Criteria and Results
TestLab provides a test report identifying:
The proposed exit criteria are that the agreed scope passes and no release-blocking issues remain. Fixes produce a new candidate tag; TestLab reruns the affected checks and the regression coverage needed to validate that candidate.
Phase 3: Internal Test and Validation
Owner: Internal validation team
This phase runs in parallel with Phase 2 and validates how the new DevShard version works with the other system components. The team selects integration checks based on the affected interfaces, dependencies, and workflows.
Test Scope
Exit Criteria and Results
The internal validation team provides a report identifying the candidate, component versions, environment, checks performed, results, and any open issues or coverage gaps. The agreed integration scope must pass with no release-blocking issues remaining.
Issues are reported to the Dev team with reproduction details and supporting logs. When a new candidate is produced, both validation tracks reassess the affected checks and rerun the coverage needed to confirm readiness.
Final Sign-off and Release
After Phases 2 and 3 are complete, the Dev team, TestLab, and internal validation team review the results for the same candidate and record a final readiness decision.
Sign-off requires:
If a governance vote is required, the approved candidate and supporting release information are submitted for voting. Rollout proceeds only after the proposal is approved. Otherwise, rollout proceeds through the applicable release approval process after sign-off.
During rollout, the release owners monitor service health, errors, performance, and resource usage and verify the critical workflows. If the agreed rollout criteria are not met, they stop further deployment and follow the documented recovery or rollback procedure.