Updated PrimaveraXERFileWriter to allow a list of projects to be written to an XER file.
Updated PrimaveraPMFileWriter to allow a list of projects to be written to a PMXML file.
CHANGES
Include all available baselines when reading Asta Powerproject PP files (Contributed by gitgood88).
MPXJ will now store an arbitrary number of baselines rather than the hard limit of 11 previously in place. Only baselines numbered 0-10 will be interpreted by MPXJ, other baselines can just be stored and retrieved.
Added the Last Scheduled Date and Activity Percent Complete Based On Activity Steps attributes to ProjectProperties and ensured these are read from and written to P6 schedules (Based on a contribution by danielfromCL).
Header rows for empty tables are no longer written to XER files.
Add support for the Project attribute Activity Default Calendar Unique ID.
Added the ProjectCalendar#getDefault method. This returns true if the current calendar is the default calendar for the project file (e.g. MPP files) or project database (e.g. P6 database).
Added the ProjectCalendar#setDefault method. Calling this method sets the calendar as the default for the project file or project database.
Added the ProjectCalendar#isParent method.
Added the ProjectCalendar#getDerivedCalendarsForProject method.
Added the ProjectCalendar#getProjectUniqueID and ProjectCalendar#setProjectUniqueIDmethods. This attribute is used to indicate that a calendar belongs to a specific project.
When writing PMXML files, ensure that OriginalProjectObjectId is populated for baseline projects.
Added the ProjectContext class to represent common context data which can (depending on the source application) be shared across multiple projects.
Added the ProjectFile#getProjectContext method to retrieve the ProjectContext instance to which a project belongs.
Added the Resource#getProjectContext method to retrieve the ProjectContext instance to which a resource belongs.
Added the ProjectCalendar#getProjectContext method to retrieve the ProjectContext instance to which a calendar belongs.
Added the ProjectFile#getCalendarsForProject method. This retrieves global calendars, and any project-specific calendars relevant for this project.
Added the Rate#valueOf method.
Added the TimeUnitDefaults class to allow time unit related default values to be held as part of the ProjectContext class.
Updated to POI 5.5.0
Updated to Jackcess 4.0.10. Removed explicit Commons Lang 3 dependency.
Updated to JUnit 5.14.1
BREAKING CHANGES
The ProjectFile#getBaselines method now returns a Map instance keyed by baseline index.
When using the readAll method to read PMXML files, only projects will now be returned. Any baseline ProjectFile instances will now only be linked to their parent projects, and will not be present in the list returned by readAll.
For P6 projects the ProjectFile#getCalendars method will include all calendars from the file or database being read. To retrieve only calendars relevant to the project use the ProjectFile#getCalendarsForProject method.
For P6 projects the ProjectCalendar#getDerivedCalendars method will include all derived calendars from the file or database being read. To retrieve derived calendars relevant to a specific project use the ProjectCalendar#getDerivedCalendarsForProject method.
Removed the ProjectEntity class. The ProjectProperties, Resource, ResourceAssignment and Task classes no longer inherit from this class. The ProjectProperties, ResourceAssignment and Task classes provide a replacement for the ProjectEntity#getParentFile method. The Resource class no longer has a getParentFile method.
Removed the ProjectCalendar#getParentFile method. Calendars no longer belong directly to projects, but instead belong to a ProjectContext instance.
Removed the Resource#addResourceAssignment method. This method was originally only intended for internal use within MPXJ.
The ResourceAssignment class no longer provides a public constructor. The Task#addResourceAssignment method should be used instead.
Removed the Task#addResourceAssignment(ResourceAssignment) method. Use the Task#addResourceAssignment(Resource) method instead.
Removed the Task#setSplits method. This method was originally only intended for internal use.