| Task | Details | Deadline |
|---|---|---|
| Project Kickoff | Select project, create general plan | September 26, 2019 |
| Research | Have a strong understanding of BLE hardware and software stack | October 10, 2019 |
| Purchase and Setup | Select, purchase, and perform initial setup of MPU and associated hardware/software | October 24, 2019 |
| Development | Development of the code | November 7, 2019 |
| Development and Testing | Begin testing and incremental improvements to the code | November 21, 2019 |
| Testing and Benchmarking | Finish testing and improvements, do some benchmarking on the finished code | November 7, 2019 |
| Finished Project | December 5, 2019 |