1. Charter

The PMO does:

  • Maintain the program board below and keep it reconciled with TODOS.md, GitHub issues/PRs, and the CHANGELOG after every release.
  • Hold the dated milestones and report distance-to-date honestly, including when a date is already lost.
  • Surface blockers that are not engineering work (an API key, a business decision, a signature) with the same weight as code, because those are what have actually stalled this project.
  • Name the critical path and refuse work that isn't on it during a gate crunch.
  • Record decisions so a reversal is visible as a reversal.

The PMO does not:

  • Re-open settled strategy. The CEO plan, the never-build list, and the Study Arena freeze are decisions, not proposals.
  • Estimate in story points, run ceremonies, or add process to a one-person engineering team.
  • Invent status. Anything marked verified here has a commit, a test, a CI run, or an HTTP response behind it.

2. Operating cadence

When What
Every release (/ship) Reconcile TODOS.md against the CHANGELOG — close what shipped, re-file what didn't.
Weekly (Mon) Run npm run metrics:weekly, update §5 runway, re-rank the board.
At each gate date Write a pass/fail line in §7. A missed gate gets a written cause, not a slip.
On any new QA/review pass File findings into the board with a workstream tag, not just into TODOS.md.

3. The scoreboard this program serves

From docs/win-plan-eoy2026.md §6. Five proofs, not revenue:

  1. WTP is real — ≥5 schools invoiced AND paid.
  2. Adoption is real — ≥60% teacher weekly-active, founder absent.
  3. Channel is real — ≥2 schools by referral.
  4. Founder is free — ≤1 school-day/week support.
  5. Cash survives — infra ≤ credits; SISFS filed.

Everything on the board below must trace to one of these. Work that traces to none is on the frozen list (§9).

4. Runway (as of 2026-08-18, Tuesday)

Milestone Date Distance
First invoice paid (money moved) 2026-08-14 4 days past — status unknown to PMO
30-school-day streak must start 2026-09-08 21 days / 15 weekdays
Adoption read (≥60% teachers, ≥4 days, founder absent) 2026-09-30 43 days / 31 weekdays
School #2 signed 2026-10-31 74 days / 53 weekdays
EOY scoreboard 2026-12-31 135 days / 97 weekdays

15 weekdays is the real budget. Everything in §6 is sized against that number.

5. Open decisions blocking the PMO (need a human answer)

# Question What it unblocks
D1 Did a school pay or sign by 2026-08-14? (Branch A = paid, Branch B = not paid) Roughly a third of TODOS.md is explicitly payment-gated. Branch B stops it all.
D2 Is a real pilot school onboarded on production today, and is PILOT_SCHOOL_CODE set there? Whether the Sep-30 adoption gate can be measured at all.
D3 Mobile/accessibility floor — unblock now or keep gated? TODOS.md records this gating as "an accident of drafting, not a decision".
D4 Is docs/BETA_LAUNCH_PLAN.md live or superseded by the wedge-first plan? Two plans currently describe the launch. Only one can be the schedule.

6. Program board

Ranked by whether it blocks a dated gate. WS-0 blocks everything.

WS-0 — Production cannot onboard a school (BLOCKER)

Item Evidence Status
Signup email dead in production (#322) — ops half Production still holds an invalid Resend key. Rotate → SMTP_PASS in Secret Manager → redeploy → re-test signup on prod. Only the founder can do this; it needs credential access. Open 39 days. OPEN P0, founder
Email failures are silent (#322) — engineering half DONE 2026-08-17. One deliver() path logs at error level with mail type + recipient and throws EmailDeliveryError; signup returns verificationEmailSent, resend returns 502 not 401, /verify-email stops claiming a dispatch that didn't happen. 12 regression cases. SHIPPED
At-risk cron crashes every run (#324.1) Stale issue. The SQL was fixed in 4ace341 on 2026-07-13 — inside the Azure migration PR, unlabelled — and has been in production since. What was genuinely open: the scheduler's floating promises (any failure became an anonymous unhandledRejection) and the absence of any guard that could catch SQL drift. Both closed 2026-08-17. SHIPPED
GET /api/chat/dms → 404 (#324.2) DONE 2026-08-18. The client asked for a path the router has never registered (/users/me/dms), so the DM list was empty for everyone with no error shown. Also fixed the blank-row bug behind it: conversations were titled with username, empty for every seeded and invited account. A contract test now checks every chat-api.ts path against the router's real route table. SHIPPED
Fabricated header badges (#324.3) DONE 2026-08-17. Both counts were literals on buttons that did nothing. The bell now shows the real unread count (no badge at zero) and both buttons navigate; the messages badge was removed rather than invented, since no server-side unread total exists. Verified in a browser against a live database, both directions. SHIPPED
Attendance copy over-promises WhatsApp (#324.6) DONE 2026-08-18. The register's own toast was already honest (v1.9.0.0) — the real gaps were /absentees saying nothing at all about dispatch state, and the public marketing promising alerts "instantly" and "from the very first morning". /absentees now reports the server's real alerts.enabled; marketing keeps the capability but drops every already-running claim (founder decision). SHIPPED
CSP blocks blob: worker / data: font (#324.4/5) Console errors on every page. OPEN

A paid pilot cannot be onboarded through the front door until the key is rotated. The engineering half landed on 2026-08-17 — the failure is now loud in logs and honest on screen — but loud is not working. Until the key is replaced in production, the new banner simply tells a school the truth: no code was sent.

WS-1 — Wedge integrity (the register must not lie)

Of the seven P0 gaps from the 2026-08-11 /autoplan, three closed in v1.9.4.0 and TODOS.md has not been updated to say so:

  • ✅ Blank editable register on read failure — fixed (register locks, retry prompt).
  • ✅ Save count reported submitted-not-written — fixed (server's written count).
  • ✅ Adoption denominator contaminated — mitigated via PILOT_SCHOOL_CODE cohort scoping.
  • ⚠️ Partly — pgGetAttendanceByClassDate now rethrows (verified at server/lib/db/pg-queries.ts:2790), but 38 return [] sites remain in the same file. The class of bug is not closed, only its worst instance.
  • ❌ Metric semantics frozen + metric-version stamp — no metric_version anywhere in scripts/metrics-weekly.ts.
  • ❌ Repair/invalidate already-persisted partial snapshots — no evidence of work.
  • ❌ Versioned migration ledger — server/db-pg.ts still re-applies one idempotent schema file; no migrations table.

WS-2 — Measurement readiness (Sep 8 / Sep 30 gates)

  • Set and verify PILOT_SCHOOL_CODE in the production environment (blocked on D2).
  • Freeze metric semantics before the streak starts: cohort, timezone, week boundary, adjacency, baseline, partial-week. Changing these after Sep 8 rewrites the experiment while it runs.
  • schools.is_synthetic — replace the LIKE 'E2E%' heuristic, via expand/backfill/contract, not a naive ADD COLUMN (which recreates the same false-positive and re-runs it every deploy).
  • Weekly metrics correctness nits: week-adjacency check, mid-week partial snapshots, UTC vs IST week windows.

WS-3 — Test and CI trust

  • Vitest flake ~1 in 3, confirmed empirically across the v1.9.2.0 ship. The accepted gate is a 10–15 run burn-in at zero failures, not "5 greens".
  • No real-Postgres unit lane — export tests mock the whole data layer, so broken SQL and schema drift cannot be caught (this is exactly how #324.1 reached production).
  • No client test infra at all (vitest.config.ts is server-only, node env).
  • No mobile Playwright project (desktop Chromium only).
  • server/tests/setup.ts:54 manufactures empty mocks for unexpected helper calls — should throw.

WS-4 — Mobile & accessibility floor

Teachers mark the register on phones. Currently: 64px dead sidebar gutter on a 360px viewport (18% of screen), touch targets at 24–40px against a 44px floor, two fixed floating controls colliding with the mobile bottom nav and with each other. Same bug class as the quest-panel defect that made the register unusable in v1.9.3.0 — that one was found by QA, in production code, on the wedge workflow.

WS-5 — Dependency & security hygiene

  • 13 open Dependabot PRs, oldest 2026-08-09. Checks are green on the ones sampled. Several are majors (ioredis 6, google-auth-library 11, azurerm 5, pg) and need reading, not bulk-merging.
  • image-size audit allowlist (2 advisories, no patched release exists) — re-check periodically, delete when one lands.
  • Determine whether untrusted image bytes can reach generatePPTX (decides whether the allowlist is safe or a live hole).
  • CodeQL now passing on schedule; #272/#300 (code scanning enablement, Trivy CRITICAL triage) still open.

WS-6 — Register hygiene (PMO's own first task)

DONE 2026-08-17. TODOS.md was stale by one release: all seven /autoplan P0s still read as open when v1.9.4.0 had closed three and partly closed a fourth. Reconciled against the code, not the changelog — each verdict carries the file and line that proves it. The [~] marker now distinguishes "partly done" from "done", which is what let the read-failure item look closed when 38 sibling sites remain. Cadence in §2 exists so this does not recur.

7. Gate log

Date Gate Result
2026-08-14 First invoice paid unrecorded — see D1
2026-09-08 Streak must start pending
2026-09-30 Adoption read pending
2026-10-31 School #2 signed pending

8. Critical path to 2026-09-08 (16 weekdays)

  1. ~~#322 fail-loud email (engineering)~~ — done 2026-08-17. Now blocked on the founder rotating the production Resend key; nothing else matters until a school can sign up. (WS-0)
  2. ~~#324.1 at-risk cron crash~~ — done 2026-08-17. The SQL was already fixed a month ago; the reporting hole and the missing drift guard were not. Both closed. (WS-0)
  3. ~~Honesty defects — fabricated badges, WhatsApp copy~~ — done 2026-08-17/18. A principal who catches the product lying once will not trust the term report. (WS-0)
  4. PILOT_SCHOOL_CODE set + metric semantics frozen — must be done before day 1 of the streak, not after. (WS-2)
  5. Mobile floor on the register only — the phone is the device. Not the whole app; the register. (WS-4)

Everything else waits. WS-3 and WS-5 are real debt but they do not move a September gate.

9. Frozen — do not start (and why)

  • Study Arena, all of it. Decision at the 2026-08-11 gate: separate option, Phase A, dark in production. It is no longer "the moat".
  • Study Arena end-to-end QA. Blocked on a valid AI key four times (07-22, 07-31, 08-06, 08-11). GOOGLE_API_KEY has an AQ.A… prefix; AI Studio issues AIza…. One valid key permanently unblocks it — but per the freeze, it is not on the critical path.
  • Coded term report, CSV streaming, admin school selector, vernacular pass — payment-gated or blocked on an unnamed owner/decision.
  • Never-build list (constitution): no foundation-model training, no standalone AI tutor, no "our AI is smarter", no single-provider coupling, no fabricated data shown to real accounts.