Newly added phase doesn't take into account the updated endDates of a phase if milestone is extended #2467

@maxceem

Description

@maxceem

Expected behavior

A new phase has to be added after the latest end date of phases in the project.

Actual behavior

A new phase ignores end data of the phases which time was previously extended.

Steps to reproduce the problem

  • Create App type project http://local.topcoder-dev.com:3000/new-project/app

    image

  • Note, App Design phase has the latest end date Oct 6.

  • Active QA & Bug Fixes phase.

    image

  • Extend the first milestone of the phase QA & Bug Fixes by 3 days for 4 times. It has to ends on Oct 9 later than App Design phase.

    image

  • A a new phase, for example RUX Iteration. It has start date Oct 7 but expected start date is Oct 10.

    image

Environment

  • OS: All
  • Browser (w/version): All
  • User role (client, copilot or manager): All
  • Account used: pshah_manager

Related issue #2427

Aha! Link: https://topcoder.aha.io/features/TCCONNECT-437

Metadata

Metadata

Assignees

Labels

No labels
No labels

Type

No type

Projects

No projects

Milestone

Relationships

None yet

Development

No branches or pull requests

Issue actions