Adaptive Control and Drift Score

zhu1090093659 edited this page Jun 8, 2026 · 1 revision

Adaptive Control and Drift Score

Adaptive control is the workflow's closed-loop correction system. It exists because large implementation plans often become less accurate as execution reveals new complexity.

Spec-Driven Develop measures plan-vs-reality drift after each task and triggers corrective action when the plan no longer matches the codebase.

Control Theory Mapping

Control Theory Term Workflow Meaning
Plant The codebase being changed
Set point The Phase 2 confirmed task definition and S.U.P.E.R principles
Controller The Spec-Driven Develop workflow
Actuator The task executor agent or agents
Sensor Post-task telemetry collection
Error signal drift_score

What Telemetry Is Collected?

After each task, the agent records three signals.

Actual Effort

The workflow compares estimated effort with actual effort:

Effort Meaning
S Under 30 minutes, no unexpected issues
M 30 minutes to 2 hours, minor surprises
L 2 to 4 hours, significant unexpected complexity
XL More than 4 hours or fundamental rethinking

Only underestimated effort increases drift.

S.U.P.E.R Delta

If a task was supposed to improve S.U.P.E.R architecture quality but does not improve it, that counts as drift. Regression is more serious than neutral progress.

Unplanned Dependencies

The agent counts dependencies not listed in the task plan:

  • Unexpected files that needed edits.
  • Missing prerequisite tasks.
  • External API or library changes.
  • Hidden coupling discovered during implementation.

Drift Score Formula

task_drift =
  max(0, effort_delta)
  + 1 if S.U.P.E.R improvement was expected but did not happen
  + min(unplanned_dependencies, 2)

The cumulative drift_score is the sum of completed task drift in the current phase.

Thresholds

Thresholds are based on the number of tasks in the phase:

Drift Level Threshold Response
Mild At least 20% of phase task count Annotate the next task with a warning
Significant At least 40% Halt and re-decompose remaining tasks
Severe At least 60% Return to Phase 2 for scope re-evaluation

For a phase with 10 tasks:

  • Annotate at 2 drift points.
  • Replan at 4 drift points.
  • Rescope at 6 drift points.

Level 1: Annotate

Mild drift means the plan is still viable but the next task deserves caution.

In GitHub modes, the workflow can add a warning label and comment to the next pending Issue.

In local-only mode, it records a warning in the progress file.

Level 2: Replan

Significant drift means the remaining task breakdown is probably inaccurate.

The workflow should:

  • Halt current execution.
  • Mark the remaining unstarted tasks as superseded.
  • Re-enter Phase 3 for the remaining scope.
  • Use completed task telemetry to improve new estimates.
  • Keep completed tasks and their history.

Level 3: Rescope

Severe drift means the original scope or strategy may be wrong.

The workflow should:

  • Halt execution.
  • Summarize what changed.
  • Return to Phase 2.
  • Ask the user to re-confirm scope and priorities.
  • Re-plan the remaining work after confirmation.

Where Is Adaptive State Stored?

Mode Storage
GITHUB_FULL Milestone description plus Issue comments
GITHUB_STANDARD Milestone description plus Issue comments
LOCAL_ONLY docs/progress/MASTER.md

Why This Matters

Most project plans degrade when reality disagrees with estimates. Adaptive control gives the agent a rule for stopping, replanning, and asking for scope confirmation instead of continuing through a stale plan.