Sprint 3 Meeting 1:
Deployed Sprint 2 progress
Uncovered bugs needing fixes
Working on additional thematic functionality
Working on web service integration
Working on product images for kiosk
Working on code documentation
Working on TTS & kitchen display fixes
Working on language translation fixes
Sprint 3 Meeting 2:
Product images for kiosk complete (AJ)
Language translation fix complete (Rodrigo)
Still finalizing additional thematic functionality, web service integration, and code documentation
Focused on fixing remaining bugs and completing outstanding functionality
Sprint 3 Meeting 3:
All Sprint 2 feature assignments completed
Deployment server set up and ready
Minor feature bugs identified
AJ assigned to fix minor issues
Sumit assigned to deploy Sprint 3 progress to server