ARCH-0001 risk register

Status: accepted — implemented. Date: 2026-09-11 · Issue: ARCH-0001 Phased repo split: core library, deploy targets, dashboard Owner: Capsize Games (maintainer) · Depends on: plans/arch-0001-migration-plan.md

Decision

Every cost identified in plans/repo_topology_plan.md §5 is carried forward with a concrete mitigation and a single accountable owner (Capsize Games, the maintainer). Additionally, the ARCH-0001 review surfaced six implementation-level risks (PR-1…PR-6) that are registered here because they can break the build or the release pipeline, not just the design.

Allowed status is accepted (mitigated and owned) or open (no mitigation agreed yet). No risk in this register is currently open.

Topology costs from the source plan

ID Risk Source Impact Mitigation Owner
SR-1 Version drift. Satellites, core, and the dashboard pin incompatible versions; a protocol change breaks client/server across repos. plans/repo_topology_plan.md §5 High compatibility.json records the satellite/core/protocol_version/dashboard triples; CI asserts every satellite pin matches the matrix; MAJOR protocol bumps require an ordered server-then-dashboard release (plans/arch-0001-packaging-versioning.md). Capsize Games
SR-2 CI and release overhead. Today's six jobs become per-repo pipelines; cross-repo changes need coordinated PRs and tags. plans/repo_topology_plan.md §5 Medium One reusable workflow definition parameterized by distribution; a single release.yml selects packages/<dist> from the tag prefix; no per-repo pipeline is created until its trigger fires (plans/arch-0001-decision-metrics.md). Capsize Games
SR-3 Test fixtures. Tests lean on spikeforge heavily and a relocation loses coverage or shared fixtures. plans/repo_topology_plan.md §5 Medium Tests move with their owning package; a thin cross-package integration suite stays with the protocol authority; the parity tests are explicitly retained (plans/arch-0001-migration-plan.md). Capsize Games
SR-4 Docs fragmentation. plans/ is one authoritative site; splitting repos means a docs repo or per-repo docs plus a hub. plans/repo_topology_plan.md §5 Medium plans/ stays authoritative in the core repo; satellites carry only a README linking back; the docs pipeline keeps globbing plans/*.md. Capsize Games
SR-5 Duplicated governance. LICENSE, NOTICE, SECURITY, CODE_OF_CONDUCT, CI scaffolding, and Docker files multiply. plans/repo_topology_plan.md §5 Low Create repositories from the shared templates at extraction time, not ahead; a sync check compares LICENSE/NOTICE hashes across repos at each release. Capsize Games
SR-6 Contributor friction. For a pre-1.0 project, a monorepo with clean distributions is friendlier than four repos. plans/repo_topology_plan.md §5 Medium Stay on Option 0 until a numeric trigger fires; keep CONTRIBUTING.md pointing at the packages/ workspace as the normal path; extraction is never scheduled on a date. Capsize Games

Implementation-level risks discovered in ARCH-0001 review

ID Risk Impact Mitigation Owner
PR-1 PEP 420 namespace collision. Two distributions shipping into one top-level root would silently merge. High Every distribution owns a distinct top-level import root; PEP 420 is explicitly not used (plans/arch-0001-target-topology.md); a CI check asserts the core wheel's top-level entries are disjoint from each satellite's. Capsize Games
PR-2 Blocked-deps blind spot. sitecustomize.py blocks the SDKs but not fastapi/pydantic/uvicorn, so a core import of the server stack would pass CI. High Extend BLOCKED with the server stack and add scripts/check_core_boundary.py (plans/arch-0001-core-boundary.md). Capsize Games
PR-3 Packaging-authority migration. tests/test_packaging_profiles.py reads setup.py text; introducing pyproject.toml silently drops that coverage. Medium Port the test to read packages/*/pyproject.toml in the same PR that adds the workspace; add a CI assertion that the set of extras and console scripts is unchanged by the migration. Capsize Games
PR-4 History rewrite during extraction. git filter-repo rewrites history and can corrupt a working clone. Medium Run it on a throwaway clone only; extraction is additive-then-subtractive; the pre-phase tag is the rollback point (plans/arch-0001-migration-plan.md). Capsize Games
PR-5 Console-script collision. A script name owned by two distributions fails install or shadows unpredictably. Medium The ownership table assigns each script to exactly one distribution; a CI check asserts no script name appears in two distributions' entry points (plans/arch-0001-packaging-versioning.md). Capsize Games
PR-6 Protocol drift after the split. The dashboard hand-edits generated types or the pydantic models diverge from the schemas. High CI regenerates TS types and fails on any diff; test_protocol_schema_parity.py asserts model-enum == schema-enum; the schema is the only editable authority (plans/arch-0001-protocol-contract.md). Capsize Games

Review cadence

This register is revisited at each of the following points, whichever comes first: a phase trigger firing, a protocol_version MAJOR bump, or a quarterly maintainer review of plans/arch-0001-decision-metrics.md. A risk may only move to open with a named owner and a dated decision recorded in this file.

Related decisions