Sprint 1 (September 30 to October 13), week 1 of 2. Reporting period: September 29 to October 5, 2026. Author: Matthew Feroz.
This report shows the project at one point in time and won't be edited after it's posted. Later changes will appear in future reports.
Sprint 1 is ahead of plan. The plan scheduled the first-run walkthrough (#9) and reconnect/cancellation validation (#10) for week 1. Both were completed in development, and so was the week 2 work on report access and publication (#11). Each produced targeted fixes and automated tests. Sprint dates and scope are unchanged.
What's left is acceptance and release:
- Public release. The validated changes were developed in the private development repository. They were opened for review as public pull request #14 on October 6 and are not yet merged.
- Hosted acceptance. Someone still has to sign in with a fresh real account on the hosted site and run a no-model worker check. The sign-in provider changed this week (see the decisions section), so the hosted site needs new configuration first.
Neither item currently threatens the October 13 end of the sprint.
✅ complete · 🟡 in progress or partial · ⬜ not started
| Feature | Started | Design | Development | Testing | Integrated |
|---|---|---|---|---|---|
| Worker setup and pairing, including the no-model worker check | ✅ | ✅ | ✅ | 🟡 automated tests pass; hosted check pending | 🟡 in development; public release pending |
| Evaluation configuration (harness, model, vendor, attempts) | ✅ | ✅ | ✅ | 🟡 browser smoke tests pass; hosted check pending | 🟡 in development; public release pending |
| Connected execution and recovery (reconnect, cancellation, partial results) | ✅ | ✅ | ✅ | ✅ real local worker test: Convex → daemon → Harbor/Docker | 🟡 in development; public release pending |
| Live monitoring | ✅ | ✅ | ✅ | ✅ | ✅ |
| Reports, sharing and publication (private, published and revoked links) | ✅ | ✅ | ✅ | 🟡 backend and export access tests pass; hosted check pending | 🟡 in development; public release pending |
| Studio chart and presentation editing | ✅ | ✅ | ✅ | ✅ | ✅ |
| Hosted sign-in (Clerk) | ✅ | ✅ | ✅ | 🟡 sign-in checks pass; live sign-in not yet tested | ⬜ hosted site not yet switched |
| Reproducibility evidence and public release checklist (#12) | 🟡 | 🟡 | ⬜ | ⬜ | ⬜ |
Sprint issues #9, #10 and #11 stay open until their hosted acceptance criteria pass. #12 is scheduled for week 2.
The project has one team member. Development is agent-assisted: Codex (GPT-6.1 Sol) through T3 Code, with Claude Code for orchestration and independent review.
Completed September 29 to October 5:
- Planned Sprint 1: four issues with completion criteria, a milestone, and a project board with automatic issue import.
- Finished the week 5 deliverables: UI prototypes, the architecture walkthrough, and the sprint plan.
- Merged 19 development pull requests:
- #9 (first run): restored the no-model worker check and clarified setup, recovery and onboarding guidance.
- #10 (reconnect and cancellation): verified results are kept when a run is cancelled, and added real worker tests for daemon restart and cancellation.
- #11 (report access): added tests that private reports stay private, published revisions don't change, and revoked or removed access fails.
- Sign-in: moved hosted sign-in from WorkOS to Clerk, with a mapping that keeps existing accounts' data.
- Reliability and performance: bounded report reads for large evaluations, reserved report storage, fixed model naming, pass labels and monitoring updates, and made task hashing and chart rendering faster.
Planned October 6 to October 12:
- Review and merge public release PR #14 after its checks pass.
- Configure Clerk for the hosted site, then run the hosted acceptance checks: sign in with a fresh account, pair a worker, run the no-model worker check, publish and revoke a report link.
- Close #9 to #11 once their evidence passes.
- Complete #12: reproducibility evidence and a public release checklist.
- Prepare the End-of-Sprint-1 status update for October 13.
As a solo developer, my collaborative work was with AI coding agents, done through threads and pull requests.
| Date | Activity | Purpose | Participants | Outcomes and follow-ups |
|---|---|---|---|---|
| Sep 30 | Sprint 1 planning | Turn the week 5 plans into a two-week sprint | Matthew Feroz, with an AI coding agent | Four issues, milestone and board created. 28 hours committed plus 4 hours contingency. |
| Oct 1 | Worker-check fix | Unblock a first run that needs no model credentials | Matthew Feroz; Codex in T3 Code | Merged the no-model worker check during setup. |
| Oct 3 | Validation walkthroughs for #9, #10 and #11 | Test first-run, recovery and report-access behavior and fix what failed | Matthew Feroz; Codex, orchestrated from Claude Code | Three pull requests with fixes and tests. Hosted acceptance checks still needed. |
| Oct 4 | Integration and review | Merge sign-in, reliability and performance work | Matthew Feroz; Codex in T3 Code; independent review by Claude Code | 13 pull requests merged after their checks passed. Follow-up: operator backfill of run summaries after deployment. |
| Area | Decision or change | Reason | Impact |
|---|---|---|---|
| Technology | Hosted sign-in moved from WorkOS to Clerk | Simpler setup and more reliable sessions | Needs Clerk configuration and account mapping before cutover. Adds a hosted sign-in acceptance step. WorkOS stays available for rollback during the transition. |
| Scope | Restored the no-model worker check during setup | Let new users verify a worker before entering provider credentials (#9) | Small addition within the sprint goal. Schedule unchanged. |
| Architecture | Saved run summaries and reserved report storage | Large evaluations could exceed backend read limits | Status pages stay fast for large runs. Older runs need a one-time operator backfill after deployment. |
| Approach | Develop in a private repository; publish to the public repository as reviewed patches | Keep private evidence, notes and branding out of public source | Public releases need a review step. Validation evidence is summarized publicly rather than copied. |
| Schedule | No change | — | Sprint 1 still ends October 13. |