This document describes, per released version, what that release of Open Planner Studio
contains — the detailed, substantive counterpart to the short release notes. Every released
version has its own section (no gaps); the newest is at the top. It is deliberately not a
running archive of every individual commit: within a version there is a curated description,
grouped by whichever category applies (Added, Changed, Fixed, Documentation).
-
PDF report export is now vector-based with selectable text (issue #23). The export of the
Gantt report, the milestone overview and the variance report previously embedded the rendered
preview as a single raster image in the PDF file — sharpness depended on the canvas resolution
and nothing could be selected or searched. The export now draws directly as PDF vectors
(lines, fills and embedded, subsetted text) via
pdf-lib, so the result stays sharp at every zoom level and text is selectable/searchable — exactly as expected from a "real" PDF. This applies to Latin, Cyrillic and Greek text (embedded with the bundled Inter font, see below); documents with CJK text (Chinese/Japanese/Korean) or RTL text (Arabic/Persian) are detected automatically by the export and fall back to the old raster export — still perfectly legible, but not selectable. Vector CJK will come later via an extension; vector RTL follows in a later phase. (Under the hood, RTL shaping/bidi and CJK harfbuzz subsetting are already in place and exposed behind a font-provider extension API.) - Move project… — a feature that shifts the entire schedule to a new start date in one go, with a calendar-aware warning when the project end or the project duration ends up different than chosen (see the accompanying i18n fixes under Fixed).
-
Built-in benchmark tool — reachable via Settings; measures the compute time of the
scheduling engine (including
runCPM) on the user's own machine, as a frame of reference for the performance work below. App plumbing, no IFC impact.
- The print/export font for reports has changed from the system font stack to the bundled Inter. This belongs with the vector export above: the old preview/export measured text widths with whichever font the operating system happened to offer first in the stack, which differed per platform (and sometimes per machine). Now it is always Inter, so the layout is deterministic across Windows/macOS/Linux/browser. Side effect: existing exports may come out slightly differently on re-export — a slightly different text width can make a line wrap or run on, which in turn can shift the number of pages. Functionally identical, visually not necessarily pixel-equal to an export from before this change.
- Project data can now be undone. Name, description, author, company, start and end date, data date, progress mode, calculation options and the project-calendar choice were until now entirely outside undo. They are now in the snapshot and every change is an undo step, with an equality check in front of it so that saving-without-change does not produce an empty step. This immediately repaired two existing half-restore bugs: undo after deleting a calendar or saving the calendar library did restore the library but not the project calendar, after which the internal cache stayed pointed at the wrong calendar. A typed-in data date now costs one undo step instead of three (the date field commits on every keystroke).
- The large example project got a second construction stream. It showed multiple critical paths only thanks to the data error described under Fixed; with correct data there was one path left. Phase 7 has been expanded into a genuine parallel stream: as soon as the parking deck is poured, its own crew starts on the garage fit-out, which runs via the outdoor area with no float to the same delivery date as the towers. Bonus: the temporary construction road was previously torn up while the towers still had to go up — that order is now correct.
-
The IFC writer no longer writes the derived analysis properties. The pset
OPS_Analysis(interfering float, near-critical, float-path number) contained solely output of the scheduling calculation with no user input; all 589 tasks in the examples reproduced their stored values bit-exact after recalculation. That saves about 157 kB in the bundled examples — the web selection went from 726 to 567 kB — and roughly a fifth of every automatic intermediate save, which runs every 800 ms per open document. Existing files with these properties load unchanged; crash recovery now recalculates, just like every other load path. -
Performance of the scheduling engine (based on the new performance audit). Byte-identical
results, only faster:
CalendarEnginenow computes working days numerically/arithmetically with an allocation-freeisWorkDayinstead of day-by-day with date strings (the audit pointed to this as the main culprit, effectively O(n²) on large schedules); the summary rollup uses an id→taskMapinstead of a linearfindper task; and the undo snapshot is taken from the ordinary pre-mutation state instead of from the Immer draft.
- The calendar warning for "Move project…" contained an empty message. The warning fires on two independent symptoms — the project end shifts by a different number of calendar days than chosen, and/or the project duration in working days changes — but always named both. If only one occurred, it stated something meaningless: "the project duration goes from 177 to 177 working days", or the other way around "the end shifts 11 calendar days instead of 11". Both cases occur in practice; in a schedule without public holidays in the shifted window, "only the end shifts" is even the common case. Now three variants with their own text.
-
"Move project…" showed plurals for a single item. The warning lines wrote
"1 tasks have a hard Mandatory pin" and "1 external links"; the detail line turned it into
"1 deadlines". The five count keys now use i18next pluralization in all fourteen languages.
In the process a catch surfaced: if one plural category is missing in a language, i18next does
not fall back to the
_otherof that same language but tofallbackLng— a Polish user with two items would then see English text. Every language therefore has exactly the categories that CLDR prescribes (Polish four, Arabic six), guarded by the new batterycheck-i18n-plurals. The detail line was rebuilt from one sentence with five counts to "label: count", in which the label does not agree with the number; zero categories now drop out instead of showing "0 deadlines". -
Lag was lost in the backward hour calculation with a milestone predecessor. In the
finish-start relationship the boundary flags
predEndsBeginOfDay/succIsFinishMsdid double duty: alongside the finish normalization they also suppressed the lag, whereas the day calculation always applies the lag and lets the flags decide only about the day step. The result was a wrong total float and a wrong critical path in hour-based scheduling — the same schedule gavetf=1and non-critical in hour mode versustf=0and critical in day mode. Forward and backward calculation thus contradicted each other. Five new cases incases-hours-relations.jsoncapture it, including a negative lag (lead) and day-parity anchors. -
Day/hour asymmetry with a start-milestone predecessor. The hour branch pulled the day-start
anchor of a start milestone via
prevWorkInstantback to the previous band end, whereas such a milestone has no real finish instant and the day branch actually keeps the target-date label. Work-equivalent, but the milestone showed a late finish on the previous working day in hour mode. The day side was covered nowhere — existing milestone cases asserted early but no late dates — and now has a parity anchor. -
Completed tasks in the large example project appeared to overrun. The generator wrote
actual dates from hand-written working-day indices in which
finishDay − startDay == dur, whereas the index translation counts inclusively; moreover that translation only skipped weekends and no public holidays, causing a task to start on Good Friday. Every completed task therefore got a day of apparent overrun, which in the backward calculation stacked back up toTF=-4on the start milestone. Actual dates now come from the fully-computed, calendar-aware schedule and the data date is derived from the planned end of the crane erection instead of from a fixed day index. The example now has zero tasks with negative float. Two cases incases-progress.jsoncapture the underlying solver behavior (completed as planned ⇒ float 0; overrun ⇒ negative float). - The properties panel showed a different start date than the Gantt bar. Four surfaces (bar, tooltip, table, task dialog) show the computed date; the panel was the only one showing the raw anchor date. Measured across all 24 examples this ran up to 484 days of difference, and in the large example 246 of the 249 tasks diverged — the panel simply showed the project start date for almost every task. The field now shows the computed date and writes to the anchor only on a real change, with an explanatory hint in all 14 languages.
- The contractual project dates did not survive the IFC round-trip — the deliberately set project start/end date was not reliably read back on save-and-reload. Sealed and covered.
- Ribbon dropdowns went wrong after the portal fix. The RibbonDropdown panel (including the timescale) lost its width; dropdown menus such as Milestone were clipped by the ribbon itself; and the right-click menu fell below the window for milestones low in the task list. All three fixed.
-
Empty undo steps on delete actions.
removeSequence,deleteTask,removeResource,removeCalendaranddeleteBaselinepushed an undo snapshot before their filter, so a call with an unknown id left an empty step behind.
-
OFL-1.1 license text vendored with the bundled Inter (
src/services/pdf/fonts/Inter-OFL.txt- explanation in
src/services/pdf/fonts/README.md) — the Open Font License requires the license text to be bundled with the font; that obligation was still missing since Inter was vendored as a raw TTF in phase 0/1 of the vector-PDF export (issue #23).
- explanation in
- The guide Reports & printing (
gids-rapporten-printen, nl+en) has been updated for the vector export: an explanation that the PDF file now stays sharp at every zoom level and contains selectable/searchable text, plus the CJK/RTL raster fallback. - README provided with a badge bar (version/CI/deploy/suite/languages/license) and a download-counter badge; the performance & modularity audit has been recorded as a measurement report with a phased plan.
-
Opening and saving files in the browser. The web version was until now fully usable
except for file I/O — which sat behind a desktop check. That gap is closed:
- Open, save, save-as and export (IFC, CSV, MS Project, Primavera P6) now work in the browser as well.
- Browsers with the File System Access API — in practice the Chromium family (Chrome, Edge, Opera, Brave, Vivaldi, …): you open a file, edit it and save with Ctrl+S over the same file, exactly as on the desktop. The browser asks for write permission once.
- Browsers without that API — currently Firefox and Safari: a clean fallback, opening via a file picker and saving as a download. In-place overwriting is not possible there; nor is it suggested.
- The app looks at the capability, not the browser name (feature detection). If a browser rolls out the API later, in-place saving works there automatically — without a new version.
- Recent files can be reopened in browsers with that API (the reference to the file is kept, not just the name). If the support is missing, the list is hidden instead of showing non-working items.
- Auto-save and crash recovery now work in the browser too: on every change a (debounced) snapshot per open document is kept, and after a crash or accidental close the app offers to recover on startup. If you close the tab with unsaved changes, the browser warns first.
- The desktop version does not change as a result: it uses the same shared layer with the existing file-system behavior.
-
Construction-mode toggle — a construction-agnostic mode for use outside the construction
context (design:
docs/superpowers/specs/2026-07-13-bouwmodus-toggle-design.md).
-
Large cleanup round based on a modularity audit of the entire codebase. No
functional changes, but structurally fewer places where the same mistake can arise again:
one canonical document contract for per-document state (capture/restore/undo), a transaction
helper that replaces a pattern repeated 50×, one shared load path, a pset registry that couples
the IFC reader and writer, a declarative ribbon and settings registry, shared dialog primitives,
a stable extension facade with a central permission table, one relationship-math module, and
App.tsxreduced from 741 to 345 lines. - Test coverage expanded with batteries that permanently guard the just-closed gaps: IFC round-trip, document contract and Gantt-float visibility.
- Eight gaps through which data was lost on save have been closed. The storage contract now demonstrably round-trips completely (with a new test battery that permanently enforces this).
- Opening lost activity codes and custom fields. All open paths now run through one shared load implementation, so structural data no longer silently drops out.
- The fast save route in the browser dropped fields (activity codes, custom fields, baselines, calendar library). All state→IFC routes now build their data in one place.
- Float disappeared on horizontal scroll. The float band was skipped together with the task bar as soon as that bar scrolled off the left edge, even when the band itself was still clearly visible.
- Gantt dragging: dragging the bar edge now writes the correct (inclusive working-day) duration, and every duration is reachable — including the initial value.
- Non-working days were always shaded as Saturday/Sunday instead of according to the project calendar; crew and deviating calendars now display correctly.
- Crash when switching document after a recovery action (a frozen calendar list was mutated). Permanently guarded with a regression test.
- PDF export revised: multiple pages, page orientation and a preview that matches the result.
- View tab and title bar overlapped on a narrow window; the display options now sit in a 2×2 grid.
- Settings: cleaner layout, uniform checkboxes and working keyboard operation in dropdowns.
-
Security update:
serde_with3.18.0 → 3.21.0 (GHSA-7gcf-g7xr-8hxj). - Development environment: on a second dev server Vite watched all git worktrees along (could exceed the system limit for file watching), and conversely ignored all files when you ran the dev server from within a worktree — causing changes not to come through.
Completion of phase 2.10 (parts 4 and 5).
-
In-app documentation — a built-in help viewer with complete user documentation in
Dutch and English: a real quick-start, nine task-oriented guides (Planning & WBS, Relationships
& constraints, Calendars & hours, Resources, Baselines, Critical path, Import/export, Reports &
printing, Shortcuts & controls) and fifteen reference articles (R1–R15). A
verify:docsscript guards that the bundled content stays complete and consistent. - Three residential-construction showcases (SMALL / MEDIUM / LARGE) that together use all app features, including advanced schema extensions and an external (cross-project) link. They replace the earlier ad-hoc "large" examples with an ascending series that starts small and runs up to a fully filled schedule.
- "Export PDF" in the Report panel actually generated a PNG. The button now delivers a genuine PDF file, in high resolution.
- The progress line and the data-date line got their correct dash pattern and thickness back (equal to the today line, 4/4 pattern, 2 px), after a regression in which the progress line fanned out and the data-date line was drawn twice.
- False "hard pin violated" message in a showcase removed (data fix), plus the MEDIUM showcase leveling corrected.
- Small UX items: the context-menu item "Set constraint…" on the task bar removed, an invisible grab zone instead of a visible 5 px drag edge on the right panel, and the tour can be restarted from Settings with the tour tooltip inside the window.
Phase 2.10 (parts 1–3): controls, shortcuts and the first-start experience.
- Shortcut foundation with a central registry and store helpers, plus a shortcut overview dialog (Ctrl+/). Reorder runs via Alt+arrow (Ctrl+Alt+arrow collided with a GNOME workspace switch), with Alt+left/right as indent/outdent aliases.
- Context-menu expansion across the Gantt and table, and box selection: a drag frame that selects tasks by row intersection.
- Task notes — a free note field per task (on request from the field).
-
First-startup experience — a
WelcomeDialogon the very first start, followed by a 7-stepTourOverlaythat guides through the most important parts and ends at the feedback button. - Further UI building blocks: a shared ConfirmDialog (replaces separate
window.confirmcalls), a relationship-type popover, a resource dock andmoveAssignment.
- QA fix waves on the new controls: parent-move corruption on reorder, popover select behavior,
Enter in dialogs,
addTask.notes, and reveal-on-select that may only fire on a click in the left task list.
The bulk is phase 2.9; alongside that an important Windows updater hotfix.
-
Advanced CPM (phase 2.9) — the critical-path engine has been made complete relative to
Primavera P6 and MS Project, in both day and hour-based scheduling (design:
docs/superpowers/specs/2026-07-06-geavanceerde-cpm-design.md):- All constraint types in the calculation. Alongside the existing "soft" constraints, now also logic-breaking Mandatory Start/Finish pins: a pinned task is placed unconditionally on its date — even if a predecessor is then not finished on time — and the resulting negative float is driven upstream (to the predecessors) instead of through the pin. A secondary constraint per task (P6's primary + secondary), with live validation that rejects impossible combinations. Constraints now work hour-precise: a date-with-time is honored to the minute on an hour calendar, a date-without-time stays day-anchored.
- Hammock tasks (Level of Effort). A hammock derives its duration from the distance between its start driver and finish driver and stretches automatically when those drivers shift; it never counts in the critical path and puts no float pressure on its drivers.
- External (cross-project) links. Refer to a task in another file via a frozen anchor date (P6 External Dates), for all four relationship types and both directions. The external task shows as a ghost bar; anchors can be refreshed per link and project-wide, and a non-loaded source gets a "stale" mark. No live two-document recalculation.
- Near-critical analysis. A configurable threshold marks tasks with little float (an amber band between critical and normal; in the high-contrast theme with a block pattern). Off by default; when enabled the threshold is 2 working days and the display follows the duration unit (days or hours, fractional).
-
Multiple critical paths / float paths. Parallel chains are numbered (
floatPathper task) via driving-logic peeling or total-float ranking, with a configurable maximum. - Interfering float — the float a task can absorb without hitting the project end but which shifts intermediate tasks (total float − free float), drawn and fractional.
- Calculation-settings block on the project. A new project section for the calculation choices: lag-calendar choice, critical definition (float threshold or longest path), float-calculation method, open-ended-tasks-critical, near-critical threshold and float paths. On the project (not app-wide), so that the same file gives the same schedule everywhere.
- Interop. Task constraints now also round-trip in P6-XML and MSPDI (previously they were lost on export), including the hard/secondary extension; hammocks, external links and the Calculation block preserve their data via custom IFC property sets.
- Fully backwards-compatible: every new option defaults to exactly the existing behavior; documents from before 2.9 calculate and serialize byte-for-byte identically.
- The CPM regression suite grew along to 369 hand-computed cases (incl. FF/SF-hour and a completeness sweep), all existing cases unchanged green.
- Windows auto-update could not unpack the installer. The zip crate used a backend that could not read the NSIS updater zip; the deflate backend is now forced so that the Windows updater does unpack the package (updater hotfix, also merged back to main).
- A schedule opened on "today" instead of at its own project period (issue #16). On opening, fit-to-project is now applied and the view jumps to the project window; on selection, task bars are brought into view (reveal-on-select).
- The Calculation section committed live instead of via a draft — a half-filled choice could already take effect; it now works draft-based.
- The Columns dialog did not let all available fields be added; that is now possible.
- The working-time editor stayed hidden on some hour presets; it is now immediately visible on every hour preset, with an explanation at "Save as preset".
-
Hour-based scheduling (phase 2.8b) — scheduling becomes hour/minute-aware, on top of the
day-granular core of 2.8a (design:
docs/superpowers/specs/2026-07-06-uren-scheduling-design.md):- Main toggle Hour-based scheduling (Settings, default off): switches on the hour/ minute scheduling — an hour timescale, crews with working-time bands and hour-precise task bars. Off ⇒ the app keeps the byte-for-byte same day-granular behavior from before 2.8b. A separate setting "Allow mixed day/hour scheduling" for documents that combine both kinds of tasks/calendars.
- Working-time bands per weekday on the calendar: multiple bands per day (breaks), bands that run over midnight (night shift) and a full 24/7 form. Ready-made crew presets (day shift, 2 shifts, 3 shifts, night shift, 24/7) plus a band editor (add band, save as own preset, set per weekday, copy to all working days) with a live derived hours/day indicator.
-
Hour timescale in the Gantt: the already-present hour/quarter-hour tiers (
timelineTiers, dead until now since phase 2.7) are activated as soon as a calendar has hour data. - Three duration-display modes in the settings: automatic (own unit per task), always days, always hours — with a warning on mixed calendars in the task table and three separate duration input fields (days/hours/total hours) in the task dialog.
- Task-bar splitting at interruptions: configurable never/on selection/always, so that a task running over a break or night block can be shown visually as separate segments instead of as one continuous bar.
- Minute-precise interop: P6-XML, MSPDI and IFC now read and write sub-day duration and times losslessly (previously everything was rounded to whole days); documents without hour data round-trip unchanged.
- Date fields rebuilt: typeable day/month/year segments instead of a single text field, with a project-wide date-notation setting and accompanying calendar-dialog fixes.
- Fully translated in all 14 languages; the CPM regression suite reached 319 hand-computed cases.
- Deliberate limitations: a configurable lag-calendar option (P6's "Calendar for scheduling Relationship Lag") is phase 2.9; sub-day resource leveling (per-hour/per-shift capacity buckets) stays day-bucket-based; timezone/DST-aware scheduling and per-row Gantt shading on deviating task calendars follow later.
- The band editor no longer corrupted the
hoursPerDayof ordinary day calendars; typing over a filled date segment now replaces the content; in the calendar/wizard dialog Enter executes the primary action and Cancel reverts the changes (buffer model). The "fixed winter shutdown" toggle has been removed from the generator (it belongs in the public-holidays generator).
-
Calendar extensions (phase 2.8a) — the calendar becomes a first-class, multiple,
year-independent concept (design:
docs/superpowers/specs/2026-07-04-kalenders-design.md):-
Year-independent public-holidays engine (
src/engine/calendar/holidays.ts): rule-based instead of a hard-coded 2026 list, with an Easter algorithm and substitution rules (e.g. King's Day on Sunday → 26 April, UK public holidays that fall on the weekend → next Monday). Seven country sets: NL, Germany incl. all 16 Bundesländer, Belgium, France (+ Alsace-Moselle), United Kingdom (EN-WLS/SCT/NIR), Austria and Switzerland. Liberation Day (5 May) follows the lustrum rule: only in years divisible by 5 is it generated as a public holiday (in other years optionally selectable). - Construction holiday is now opt-in via the wizard choice (none/North/Central/South), with default none — the old default calendar silently baked three weeks of construction holiday (region North) into every new project, which in the phase-2.5 QA made a 5-day task look like a "stretched bar of four weeks". The regional construction-holiday dates come from a verified data table per year with an approximation fallback for years outside the table.
-
Calendar library: the resource-calendar registry (phase 2.5) has been promoted to the
project-wide library (
calendars: WorkCalendar[]) that project, tasks and resources all refer to — one central place instead of an implicit project calendar plus a separate resource registry. Existing documents migrate automatically (inline project calendar becomes library entry "Project calendar"). -
Task-specific calendars in the CPM: every task can get its own calendar
(
Task.calendarId, fallback project calendar); the solver computes duration, float and constraint snaps per task in its own calendar via an engine cache. Predecessor- calendar lag rule: the lag between two tasks counts in the calendar of the predecessor (P6 default), while the successor-derived start time snaps in the calendar of the successor — forward and backward pass mirror this split exactly, so that float stays symmetric. -
Wizard (
ProjectInfoDialog): country/region dropdown (Bundesland for Germany, country part for the UK, canton for Switzerland), the construction-holiday choice, a fixed-winter-shutdown checkbox (default off) and a compact public-holidays preview with an expandable list — replaces the old, year-bound 3-presets dropdown. - Calendar dialog as library management: a list of all library calendars with active/project-default marking, new/duplicate/delete, and a new "Generate public holidays…" button that opens the same country/region/construction-holiday generator as the wizard — also for existing projects, not only on creation.
- Gantt name label on multi-day holiday blocks: blocks wider than a few zoom pixels now show their name (e.g. "Construction holiday (North)") in the shading zone, so it is immediately visible which public holiday or vacation period is in the schedule.
-
IFC-reader gap closed: the work week and working hours now actually read back from
IFCRECURRENCEPATTERN/IFCTIMEPERIOD(previously a 6- or 7-day calendar silently fell back to the Mon-Fri default on reload). Multiple named calendars and the task-calendar link round-trip viaIfcRelAssignsToControland a new OPS pset (rule-set id/construction-holiday choice). -
Multi-calendar and task-calendar round-trip also in MSPDI (
Calendars+Task CalendarUID, made effective) and P6-XML (StandardWorkWeek/HolidayOrExceptions,CalendarObjectIdper activity). Loss matrix in the design doc §8.4. - Fully translated in all 14 languages; the test suite grew from 280 to 289 hand-computed
cases, all existing cases unchanged green,
verify:examplesbyte-identical. - Deliberate limitations: hour/minute-based scheduling and day/night crew calendars are phase 2.8b (the data model stays day-granular — an hour calendar now has no effect on the solver); per-row Gantt shading on deviating task calendars follows later (the global column shading stays on the project calendar, MSP behavior); a configurable lag-calendar option (P6's "Calendar for scheduling Relationship Lag") is phase 2.9 — 2.8a fixes predecessor calendar as an internal constant; weather/frost-dependent winter downtime is phase 4 (2.8a knows only a fixed, annually recurring winter-shutdown period); the construction-holiday table dates are advisory dates (Bouwend Nederland) that become less precise further into the future with an approximation fallback.
-
Year-independent public-holidays engine (
- Eight QA findings from the 2.8a walkthrough corrected, plus the 24/7-preset labels translated in the remaining languages.
-
Views (phase 2.7) — real, saveable views on the View ribbon tab (design:
docs/superpowers/specs/2026-07-04-weergaven-design.md):- Timescale repair: the until-now dead timescale choice has been replaced by a working dropdown (Year/Quarter/Month/Week/Day) that maps to zoom presets; the displayed label is derived from the actual zoom level (so it can never desync from the drawn axis again) and the viewport recenters on the midpoint of the current window when switching scale.
-
One shared visible-rows list (
computeViewRows) for table and Gantt: filter, grouping and sorting are henceforth computed in exactly one place, so that table and Gantt canvas can structurally no longer diverge (structural parity). - Column configuration in the task table: visibility, order and width per column, across builtin fields, activity codes, custom fields and a new resource column (comma-separated join via assignments, read-only in 2.7).
- Nested AND/OR filters with a P6-like editor (All/Any groups, field-type-aware value input: text/number/date/dropdown for codes/resources), including "show summaries" behavior (non-matching parents of a match stay visible, dimmed).
- Grouping up to 2 levels over any field (WBS, activity code, custom field, resource, task type) with a band header + count, and unlimited multi-key sorting (stable sort, respects the WBS hierarchy within tree mode).
- Structure locking outside tree mode: indent/outdent and task dragging are disabled as soon as filter/group/sort is active (structure mutations are only well-defined in pure tree mode); value mutations (cell edits, adding, deleting) always remain possible.
- Custom layouts: save/apply/rename/delete/manage, app-global (localStorage, not per document), with silent tolerance for fields that no longer exist in the current document.
- Presentation mode (F11) via the real Fullscreen API: all chrome (title bar, ribbon, document tabs, status bar, properties panel) disappears, only the Gantt full-bleed remains; Escape or the browser/OS fullscreen closes it.
- Split view within one document: two independent time windows side by side on the same shared rows and vertical scroll — for example a detail week next to a faraway milestone.
- Mini-map: a light thumbnail strip of the entire schedule with a draggable viewport frame.
- Auto-calculate setting (three surfaces: gear ⚙, Settings ribbon tab and backstage) plus the "Calculate" naming consolidated into one i18n key everywhere (ribbon, menu, properties panel).
- Fully translated in all 14 languages; the test suite grew from 256 to 280 hand-computed cases, all existing cases unchanged green.
- Deliberate limitations: the hour timescale waits on hour/minute scheduling (phase 2.8) — the data model is day-granular, an hour axis would mislead now; rollup totals per group band (sum duration/costs/units) follow later (phase 3.5/3.9); a split view with two different documents requires a store-singleton refactor and is deliberately later; layouts are app-global and do not round-trip in the IFC file (per-file layouts are deliberately later).
- QA findings 2.7: a unique Milestone label in the field catalog (was duplicated) and the Gantt tooltip via i18n.
-
Baselines & progress (phase 2.6) — data-date-driven CPM, real
progress tracking and unlimited baselines (design:
docs/superpowers/specs/2026-07-04-baselines-voortgang-design.md):- Data date (P6 data date) on the project: drives the CPM forward pass — completed tasks are clamped to their actuals, started-not-completed tasks place their remaining work from the data date, and not-started tasks cannot start before the data date. No data date set ⇒ the behavior is byte-for-byte equal to before 2.6.
-
Real progress tracking: percent-complete, actual start and
actual finish (the until-now dead
TaskTimefields) with enforced invariants (an actual finish implies 100%, 100% implies an actual finish, filling in a percentage automatically sets an actual start, actuals may never lie after the data date).remainingTimeis always derived from the percentage. - Retained Logic / Progress Override as project-wide progress mode: determines how the remaining work of a task that finished before its predecessor relates to the network logic.
- Out-of-sequence detection: tasks that show progress while their predecessor relationship (FS/SS/FF/SF) logically contradicts it, are marked and reported as a warning — blocks nothing, follows the chosen progress mode.
- Unlimited, named baselines (P6-style snapshots) with exactly one active; management via a baseline dialog (save/rename/delete/activate) in the Planning tab.
- In the Gantt: a data-date line, a baseline overlay (thin sub-bar per task against the recorded baseline dates) and a progress line (MSP zigzag that bulges out per row to the progress position) — all three separately toggleable.
- Variance report as the third report type in the Report panel: baseline vs. current start/end per task, delta in working days, status (on schedule/later/ earlier/new/removed) and a project-end summary.
- Round-trip through IFC 4.3 (actuals in the already-existing but until-now
unused
IfcTaskTimeslots 14-18 — spec-conform; data date/ progress mode inOPS_ProjectSettings; baselines double-track via a losslessOPS_BaselinesJSON plus.BASELINE.schedule headers for interop), MSPDI (full: Baseline0,<StatusDate>, actuals), P6-XML (best-effort: actuals + data date; P6 baselines are a documented loss) and CSV (new actual-start/-end columns, deliberately without baselines/data date). Golden rule preserved: files without 2.6 data round-trip bit-identically. - Fully translated in all 14 languages; the CPM regression suite grew from 240 to 256 hand-computed cases, all existing cases unchanged green.
- Deliberate limitations: no costs/work/Earned Value (SPI/CPI/BCWP) — that is phase 3.5; P6 baselines are not exported (best-effort, documented loss); setting the data date/progress mode is not undoable (same precedent as the project calendar — undo via clearing + recalculating).
- QA findings 2.6: the compact-ribbon overlap and F5/Ctrl+S from input fields.
-
Resources (phase 2.5) — resource management, load, overallocation and
automatic leveling (design:
docs/superpowers/specs/2026-07-03-resources-design.md):- Five resource types: labor (people), equipment (cranes, machines, scaffolding), material (concrete, steel, wood), subcontractor and crew. Crews bundle other resources; every resource has a maximum capacity, unit and optionally its own calendar.
- Time-phased capacity: the availability of a resource can change per period (availability steps) — e.g. three carpenters until week 10, five after that.
- Resource assignment to tasks with units per day and six distribution curves (uniform, front-loaded, back-loaded, bell, and ascending and descending), so that the deployment is spread realistically over the task duration. Assignment is only possible on workable (leaf) tasks.
- Load and overallocation engine in the calculation (F5 / Calculate): per resource the daily load is summed and compared with the capacity; overload is marked.
- Resource histogram as a strip under the Gantt, with a shared time axis, capacity line, red peaks above the line, a resource picker with overallocation badges and drill-down tooltip; the height is adjustable and persistent.
- Automatic resource leveling and smoothing: a serial placement algorithm (SGS) shifts tasks within their float to resolve overallocation, sorted by priority/float/start date. Leveling goes via a dialog with an up-front preview (shifts, new end date, remaining conflicts) and can be applied or cancelled with one click.
- Task priority (0–1000; 1000 = do not level) drives which tasks get precedence under scarcity.
- Resources ribbon tab with a management panel (resources + capacity steps + calendar link), an assignments section in the task properties panel, the histogram strip and the leveling dialog.
- Round-trip through IFC 4.3 (incl.
IfcCrewResource,OPS_Resource/OPS_Assignments/OPS_Levelingpsets, anIfcWorkCalendarper resource andIfcTask.Priority) and import/export via Primavera P6-XML and MS Project MSPDI — resources, assignments, curves and resource calendars travel along. Golden rule: files without resources stay bit-identical. - Fully translated in all 14 languages; the CPM regression suite grew from 202 to 231 hand-computed cases (incl. leveling and smoothing scenarios), all existing cases unchanged green.
-
Example projects in Backstage — a new section File → Examples
exposes the bundled example schedules (cards with name, description and
tags). Clicking opens the example in a new tab (no source file, so
saving becomes save-as). The list is data-driven via
public/examples/manifest.json, so new examples come in without a code change. Works in the web and desktop build. The section now shows two groups: the three showcase schedules at the top (badge "All features"), below them the simple examples (manifest fieldcategory). -
Example generator rebuilt (
npm run gen:examples) — the examples are now fully built by the app itself via the real store +runCPM()+writeIFC(instead of a hand-rebuilt IFC writer, which had drifted). Drift between the examples and the app is thereby structurally impossible. New:- Three showcase schedules (residential / infra / renovation) that together use all app features: all four relationship types + lags/leads/%-lag/ELAPSEDTIME, date constraints + deadlines incl. a deliberate conflict with negative float, start/finish/mandatory milestones, activity codes + custom fields, all five resource types with crew hierarchy, resource calendars, availabilitySteps, all six assignment curves, an overallocation solvable with leveling and a pinned task (priority 1000).
- Year-independent dates: projects anchor relatively ("first Monday of March, next year"); NL public holidays (incl. Easter derivatives) and the construction holiday are computed per year, so that regenerating always yields current dates.
- Twenty sector examples enriched with real phase overlap (SS/FF relationships, leads and %-lags on the phase boundaries) and varied calendars, so that a realistic critical path with float arises (55–86% critical instead of nearly everything). The two old, hand-built "large" examples have been replaced by the showcases.
-
Verification (
npm run verify:examples): every file goes through the realreadIFCwith asserts on counts, round-trip stability and present features.
-
Recovery dialog in the app itself — on startup after an unexpected
shutdown the recovery question now appears as its own, styled React dialog
(
RecoveryDialog) instead of a native OS dialog. The dialog shows, per document to recover, the project name, the file path (if known), the number of tasks and the timestamp of the last auto-save snapshot. Escape defers the choice without cleaning up the recovery files; the auto-save is postponed until the choice is made, so that the snapshots are not overwritten prematurely. (This was desktop-only at the time; since v2026.7.11 the browser build also has recovery, via IndexedDB.) - The default task priority is now an explicit value (500) instead of empty, so that priority weighs in predictably during leveling; an explicitly filled-in 0 is preserved (was previously silently corrected to 500 in the MSPDI export).
- Product/code-review findings on the resource features: an honest leveling preview with fresh
floats, first-class derived state and histogram refresh; validation, popover behavior, Y-scale,
explanation and a total column in the management panel; and the resource name that was
squeezed out in the assignment row. The IFC/P6 adapters got correct assignment keys, a
correct P6 rate, a spec-conform
IfcTaskand units as a fraction. - Collapsed subtasks appeared at the bottom of the table instead of staying hidden; the "parent task" field has been removed from the task dialog when editing.
- i18n final sweep: hundreds of translation keys in the twelve remaining languages filled in and an
orphaned key cleaned up (incl. a German
clearLevelinglabel that broke mid-word in the ribbon).
-
Milestones (phase 2.4) — start/finish milestones, mandatory milestones and a
milestone overview (design:
docs/superpowers/specs/2026-07-02-mijlpalen-design.md):-
Start and finish milestones (P6 Start/Finish Milestone) via a day-granular
boundary model: a start milestone anchors on a day start, a finish milestone on a
day end (end of working day F = start of the next working day). FS to a finish milestone lands
on the finish day itself; an FS/SS successor of a finish milestone starts the working day after.
undefined= automatic (the anchor follows the binding relationship side) — existing files calculate bit-equally. Golden invariant: an inserted milestone never shifts the chain. -
Mandatory (contractual) milestones:
mandatoryflag with a double-diamond in the Gantt; date guarding via the existing 2.3 constraints (FNLT/MFO → negative float). The ribbon milestone button is a menu: start milestone, finish milestone or inspection point (finish milestone + task type Inspection + mandatory). - Milestone overview as the second report type in the Report panel: a table with kind, date, constraint/deadline date, float, mandatory and status (on schedule / critical / late, color-coded), printable; a summary with mandatory and late counters.
- Round-trip through IFC 4.3 (
OPS_Milestonepset; automatic writes nothing) and P6-XML (activity typeStart/Finish Milestone, kind is preserved on import). - Test suite grown from 176 to 202 hand-computed cases (battery
cases-milestone-kinds.json), all existing cases unchanged green.
-
Start and finish milestones (P6 Start/Finish Milestone) via a day-granular
boundary model: a start milestone anchors on a day start, a finish milestone on a
day end (end of working day F = start of the next working day). FS to a finish milestone lands
on the finish day itself; an FS/SS successor of a finish milestone starts the working day after.
- Indent/outdent of tasks (MSP convention): Alt+Shift+→/← and buttons in Planning → Structure; indenting makes a task a child of its preceding sibling, outdenting makes it a sibling after its parent — subtrees ride along, WBS auto-numbering renumbers and it is one undo step.
- Resizable task table in the Gantt: drag the divider line (150–800 px, persistent); replaces the fixed width of 350 px.
- Compact ribbon mode: a small arrow at the bottom right of the ribbon (Word-web style) collapses the ribbon to a single row of 40 px instead of 94 px — for small screens; the state is remembered.
- The milestone checkbox in the properties panel now sets the duration to 0 and disables the duration field; the tables consistently show duration 0 for milestones (was: silent divergence).
- New milestones no longer get the task type Inspection by default (that is now reserved for the inspection point).
-
In-app updater on .deb installations (Ubuntu/Debian): .deb installs got only
manual update instructions, on the outdated assumption that the Tauri updater cannot replace .deb
in-place. The updater plugin (≥2.6; we run 2.10.1) does do that —
it matches the
linux-x86_64-debentry inlatest.jsonvia the bundle-type stamp in the binary and installs via pkexec/sudo +dpkg -i. The update dialog on .deb now shows the normal "Download and install" button; the manual copy-paste command and the download-page button remain as a fallback when the installation fails. -
Windows auto-update broke due to a draft URL in
latest.json: the re-sign step inrelease.ymltook over the download URL from the GitHub API while the release was still draft, causing thewindows-x86_64(-nsis)entries to point to anuntagged-…URL that 404s after publication (as happened in v2026.7.1). The workflow now builds the stablereleases/latest/download/URL itself from the asset name; thelatest.jsonof release v2026.7.1 was repaired in place (all URLs verified 200, signatures unchanged). -
Sharp app icon on Linux: the runtime window icon was 32×32 (first PNG in
bundle.icon), causing docks to show an upscaled blurry icon.icon.png(512 px) is now at the front, 256×256/512×512 fill the hicolor slots in the.deb/snap and all sizes have been regenerated from the 1024px vector source (incl.snap/gui/icon.png).
-
Constraints & deadlines (phase 2.3) — date constraints, deadlines and negative float
(design:
docs/superpowers/specs/2026-07-02-constraints-deadlines-design.md):- All 8 date constraints in CPM (ASAP, ALAP, SNET, SNLT, FNET, FNLT, MSO, MFO) with P6 soft semantics: constraints never break the network logic — early-side types are lower bounds in the forward pass, late-side types upper bounds in the backward pass; MSO/MFO work as P6's Start On/Finish On (both bounds at once); ALAP shifts to zero-free-float (P6 model, and the relationship then becomes correctly driving). Constraint dates snap to working days. The logic-breaking Mandatory pin is deliberately §2.9.
- Deadline per task (MSP model, soft): bounds only the late finish — bars never move; float is measured up to the deadline and negative on overrun.
-
Negative float: total float is now drawn (min of start and finish float,
MSP-safe) and
critical = float ≤ 0; missed deadlines and violated constraints propagate negative float through the predecessor chain (DCMA checks 5/7 as a frame). - Indicators: constraint pin on the bar edge (blue = early-side, violet = late-side, red = violated), deadline arrow on the deadline date (green/red), P6 asterisk after the date in the table, negative float red in the float column and warning counters in the status bar.
- Round-trip via
OPS_Constraintspset (IfcTaskTime has no constraint slots); test suite 159 → 176 hand-computed cases.
- Dependabot alert #12 (glib
VariantStrIter, RUSTSEC-2024-0429) assessed and dismissed as not used: the API is used by neither the app nor Tauri's gtk3 path and the fix (glib 0.20) requires GTK4 bindings that Tauri 2 does not use — revisit on a Tauri migration.
-
WBS & structure (phase 2.2) — the structure layer at a professional level
(design:
docs/superpowers/specs/2026-07-02-wbs-structuur-design.md):- Automatic WBS numbering (1.2.3.4 from the tree position): new projects number live on every structure mutation (on/off via Planning → Structure); existing files keep their free codes (MSP model) with an explicit Renumber WBS action. New tasks also get a derived code without auto, and pasting renumbers the pasted branch (no more code duplicates).
- Activity codes (P6 model): project-bound code types (e.g. Location, Discipline) with values (code + description + color), max one value per type per task; management via the new dialog Codes & fields, assignment in the properties panel and as table columns.
- Custom fields: typed user fields (text/number/integer/ cost/date/yes-no) per task, visible as table columns.
- Multiple WBS breakdowns: View → Group by shows table and Gantt as bands per code value (color strip + label, P6 Group & Sort style) — the industry standard for location × discipline without a second saved tree.
- WBS templates (Asta task-pools style): right-click on a summary task → Save branch as template (tasks + internal relationships incl. lag); inserting and managing via Planning → Structure → Templates. App-level (localStorage).
-
IFC 4.3 round-trip for all of this: definitions as
IfcPropertySetTemplate(+IfcPropertyEnumerationfor code types, declared viaIfcRelDeclares), values per task asOPS_CustomFields/OPS_ActivityCodespsets with typed values, project flag inOPS_ProjectSettings; lossless meta-JSON for own files and template fallback for third-party files. - Copy/paste of WBS branches already existed; the new fields ride along and
pasting now also preserves
lagUnit/lagPercentof internal relationships (fix).
-
Full dependencies (phase 2.1) — the relationship model has been brought to the level of
professional planners (design:
docs/superpowers/specs/2026-07-02-volledige-dependencies-design.md):-
Lag unit per relationship: working days (default) or calendar days (24/7, e.g. curing
of concrete) — IFC-conform as
IfcTaskDurationEnum(WORKTIME/ELAPSEDTIME); notation2dvs.3edin editors, CSV and MSPDI (LagFormat 8). -
Percentage lag (e.g.
SS+50%, MS Project semantics): percentage of the duration of the predecessor, re-evaluated on every CPM run; round-trips via IFC (IfcRatioMeasure) and MSPDI (LagFormat 19/20); P6 export bakes out to fixed hours (with a log message). -
Negative lag (lead) rounded: the clamp on the project start remains (P6/MSP-conform) but a
truncated lead is now marked, as is a lead larger than the predecessor duration;
leads serialize ISO-8601-conform (
-P2D) and the swappedIfcLagTimeattributes (LagValue ↔ DurationType) have been corrected — old files remain readable. - Driving/non-driving relationships (P6 definition: relationship free float = 0, ties allowed): solid vs. dashed arrows in the Gantt (red = critical driving line), ⚡ indicator in the properties panel and the relationship table.
- Relationship table — new ribbon tab Relationships: all relationships in one sortable, inline editable table (predecessor, type, lag, successor, driving, free float per relationship, warnings) + "new relationship from selection"; the Manage button on the Planning tab opens it.
- Path tracing (MSP Task Path style): trace buttons (predecessors/successors) on the Planning and Relationships tab + context menu "Trace path" — transitive predecessors gold, successors purple (driving chains darker), the rest dimmed; Escape stops.
- Relationships are now also editable in the properties panel (type + lag notation
2d/3ed/50%/-25e%); new store actionupdateSequencewith undo. - Test suite expanded: 129 → 159 cases (new batteries
cases-lag-advanced.jsonandcases-driving.json; harness knowslagUnit/lagPercent/drivingSet/truncatedLeadSet).
-
Lag unit per relationship: working days (default) or calendar days (24/7, e.g. curing
of concrete) — IFC-conform as
-
The manual
.debinstall command in the update dialog accidentally also matched theamd64.deb.sigasset, causing$urlto contain two URLs andcurlto fail with "URL rejected: Malformed input to a URL function". The grep now matches on the closing quote.
- In-app feedback button → GitHub issue with an optional screenshot and a full-screen annotation editor (inline text tool, OK confirmation before anything goes to GitHub). The feedback button got a rotating label to make it more visible.
-
Working snap packaging —
snap/snapcraft.yaml(core22, strict confinement, gnome extension) that repackages the release.deb, plus a restoredsnap.ymlworkflow that triggers on tag push andworkflow_dispatch, downloads the release deb instead of rebuilding the app, attaches the.snapas a release asset and publishes to the Snap Store once the store credential exists. - Auto-save on every change — the recovery snapshot is henceforth written on every mutation (debounced) instead of at fixed moments.
-
CPM correctness — seven verified issues from a new planning-correctness test plan:
CPM relationships, lag/lead, milestones and free float are now correct, the
scheduleStartdrift on recalculation is gone, and a review round sealed the IFC lead, WBS late rollup and various hang/robustness cases. - The canvas context menu now also closes on a click-outside (not only on Escape); the
clipboard image in the feedback tool is built via
Image.new(rgba,w,h)instead of from raw bytes; and the auto-assign workflow got theissues:writepermission.
- Test plan and findings for planning correctness (CPM/relationships/milestones/calendar) recorded, and the design + the to-do for working snap packaging.
A large leap of ~146 commits that took the app from a prototype to a genuinely extensible, self-updating product (highlights).
-
Cross-platform in-app auto-update (Tauri updater) on Windows, macOS and Linux — the
flagship of this release. The app checks silently on startup against the GitHub-release
latest.json, verified with a minisign pubkey; macOS got anapptarget and Windows a re-sign step so that the updater can install the package. -
Extension system (modeled on Open Calc Studio) — an extension is a ZIP or loose
.jsfile (manifest.json+main.js) that registers importers and ribbon buttons. Loader with IndexedDB storage and anew Functionsandbox, a scoped host API with permission checks and event bus, host events (host:project-loaded/-new/schedule-calculated), a real host SDK viarequire('open-planner-studio'), management via Backstage → Extensions / Import, an example extension and a public catalog repo. -
Multi-document —
documentSlicekeeps track of multiple opened projects (active at top-level, inactive as a payload snapshot); three switch styles (horizontal tabs / project rail / title-bar pill) with a shared project-overview overlay, per-document view/ undo/selection/dirty, shared clipboard,Ctrl/⌘ 1–9, multi-document recovery and a 3-way close confirmation (Save / Don't save / Cancel). -
New-project wizard (
ProjectInfoDialog) with name/client/start date, a calendar preset and a phasing template — with this Phase 1 is complete. - Copy/paste tasks (Ctrl+C / Ctrl+V) including subtasks and internal relationships.
- CAD-style zoom: cursor-anchored zooming with a tier-driven timescale header, week-start awareness and shortcuts (+/−/0/Ctrl+0 fit-to-project).
-
Debug terminal overlay, a shared settings unification across three surfaces, a
reusable themed Select dropdown, a work-calendar dialog, a self-test harness
(Tier 1 Playwright +
window.__OPS__, Tier 2ops-testchannel), Linux desktop-icon metadata and per-worktree isolation of port and recovery file so that multiple desktop builds can run at once.
- Modern UI overhaul — a cool "Soft-Depth" look across all surfaces (Phase 1 cool tokens, shadow/radius, AA control edge and fonts; Phase 2 across the whole app), on top of an OpenAEC stylebook alignment (fonts + tokens, theme reduction from 7 to 3 with migration).
-
Store architecture — the monolithic Zustand store has been split into ten slices
(
src/state/slices/);appStore.tsis now a composition root. No behavior change. -
Performance — O(n³)/O(n²) lookups in IFC nesting and the drawing of Gantt arrows
eliminated;
isTauri()centralized insrc/utils/platform.ts; CI to Node 24-compatible Actions versions; eleven of twelve Dependabot vulnerabilities patched.
-
Scheduler — the critical path is now correct (no more phantom float on predecessors) and
runCPMcan no longer freeze or crash on odd/invalid data. - Light-mode contrast improved (deeper tint, visible edges/lines, bright amber, WCAG AA).
-
Extension robustness:
minAppVersionis enforced, the own ZIP parser reads sizes from the central directory, and a failed activation cleanly cleans up its UI registrations;removeResource/unassignResourceclean up orphaned ids; XML-import detection more robust (P6 before MS Project; unknown format throws). - Various: the update-dialog grep accidentally matched the
.sigasset, the file extension is ensured on save (Linux/GTK), STEP entities are terminated with;(invalid IFC output fixed, incl. the example generator), the default end date follows the duration and theme names are translated in the theme picker.
-
CLAUDE.mdadded/updated (architecture, multi-worktree dev setup, i18n/settings/ Rust facts), the README architecture corrected, a to-do list and this changelog document set up, the UI-overhaul spec and the self-test-harness documentation recorded, andread_file/write_filein the Rust backend documented as a deliberate escape hatch.
First public release (seed). This is one squashed initial commit plus a handful of follow-ups; the granular history behind it is missing.
-
The core of Open Planner Studio — a construction-planning application with Gantt charts
(imperative on canvas), a CPM scheduler with a calendar engine and the native IFC 4.3
file format (reading and writing via
ifcReader/ifcWriter, no separate project format). Around the Gantt: a ribbon UI, an Excel-like table editor, an IFC code editor, a report panel with an inline live print preview, draggable task bars, collapsible WBS chapters and a right-click context menu. - Multilingual with 14 languages (i18next + OS-locale detection), a Settings dialog, a 4-theme system (Dark, Light, Blue, High Contrast) with CSS variables from which the canvas renderer also reads its colors, and a custom title bar with working window buttons.
- CalVer versioning (
YYYY.M.B), two bundled example IFC schedules and the release/CI plumbing (bundling, Azure Trusted Signing for the Windows installer).
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Getting started
Guides
- Planning & WBS
- Relations & constraints
- Calendars & hour planning
- Resources, histogram & leveling
- Baselines & progress
- Critical path & advanced analysis
- Import/export
- Reports & printing
- Keyboard shortcuts & controls
Reference
- Task dialog
- Calendar dialog
- Resource calendar
- Leveling options
- Baseline management
- External links
- Codes & fields (structure)
- Filters
- Choosing columns
- Saving and loading layouts
- Project information
- Settings
- Managing and installing extensions
- Recovering after a crash
- Keyboard shortcut reference
Project