L1 — Cross-project PDF infrastructure reuse (2026-05-27)

Finding: build_pdf.py v3.0 from archived ultrametric-tree-resistance reused with zero modifications. PDF rendered at 873,790 bytes.

L2 — Gate false positives from references section (2026-05-27)

Finding: Initial gate scan reported 42 straight double quotes, all in References (paper titles). Converted to curly quotes in one pass.

L3 — DOI placeholder in BOTH YAML and visible author block (2026-05-27)

Finding: Gate detected placeholder after YAML fix because visible author block had separate DOI field. Both must be updated independently.

L4 — Existing project board with 15 DraftIssues (2026-05-27)

Finding: Board #4 pre-existed with 15 DraftIssues (project-board-only). Supplemented with 5 standard Issues.