[RUNBOOK] Phase 2 — MVP rule set + token adapters #20

Description

@aram-devdocs

Summary

Ship the remaining 5 MVP rules (color/palette, radius/scale,
sibling/height, a11y/touch-target, edge/near-alignment), the full
config schema (color, radius, alignment, a11y), and adapters that
let teams reuse existing token sources — DTCG, Tailwind config,
CSS custom properties.

By the end of this phase, 8 rules operate end-to-end against real
design-system configs and plumb init can bootstrap from a
Tailwind project.

PRD references

  • PRD §11.2
  • PRD §11.3
  • PRD §12.2
  • PRD §12.3
  • PRD §12.4
  • PRD §13.2
  • PRD §15.3
  • PRD §15.4

Acceptance criteria

  • 8 rules emit findings on a dogfood fixture with zero false positives.
  • DTCG 2025.10 adapter round-trips a Tokens Studio export.
  • Tailwind adapter round-trips a real tailwind.config.ts.
  • plumb init detects Tailwind and scaffolds plumb.toml.
  • All 13 child PRs merged.

Batches

Gates run sequentially (every PR in Gate N must merge before Gate N+1 starts). Within a gate, batches are parallel. For each batch, a recommended dispatch strategy is shown — you can always pick a different shape if it fits. See .agents/rules/dispatch-strategy.md for the heuristic.

Gate Batches Tickets After
Gate 1 2A #21 #22 (initial)
Gate 2 2B, 2C #23 #24 #25 #26 #27 #28 #29 #30 Gate 1 merged
Gate 3 2D #31 #32 #33 Gate 2 merged

Gate 1

Batch 2A — Config shape — remaining sections + span-annotated errors

# Ticket Crate Effort Extras
#21 [color], [radius], [alignment], [a11y] sections + schema plumb-config M
#22 span-annotated validation errors via miette plumb-config M

Dispatch (bundle): same crate, similar effort — bundling keeps related changes atomic.

/gh-issue 21 22 --worktree

Advance to Gate 2 when: every PR in Gate 1 is merged.

Gate 2 after Gate 1

2 parallel batches (2B, 2C) — every batch below can run concurrently. Each batch still has its own recommended shape.

Batch 2B — Remaining MVP rules (5 parallel implementations)

# Ticket Crate Effort Extras
#23 rule color/palette-conformance (Oklab ΔE00) plumb-core L
#24 rule radius/scale-conformance plumb-core S
#25 rule sibling/height-consistency plumb-core M
#26 rule a11y/touch-target plumb-core S
#27 rule edge/near-alignment plumb-core M

Dispatch (cluster): mix of small and large — bundle 4 small, split 1 large to keep review <400 LOC.

/gh-issue 24 25 26 27 --worktree   # 4 small: one bundled PR
/gh-issue 23 --worktree   # L: rule-color-palette-conformance

Batch 2C — Token adapters — DTCG + Tailwind + CSS custom properties

# Ticket Crate Effort Extras
#28 DTCG 2025.10 token adapter plumb-config L security
#29 Tailwind config adapter plumb-config L security
#30 CSS custom-properties scraper plumb-config S

Dispatch (cluster): mix of small and large — bundle 1 small, split 2 large to keep review <400 LOC.

/gh-issue 30 --worktree
/gh-issue 28 --worktree   # L: config-dtcg-adapter
/gh-issue 29 --worktree   # L: config-tailwind-adapter

Advance to Gate 3 when: every PR in Gate 2 is merged.

Gate 3 after Gate 2

Batch 2D — Developer experience — JSON output, selector scoping, init

# Ticket Crate Effort Extras
#31 --format json deterministic key ordering plumb-format S
#32 --selector flag scoping lint to subtree plumb-cli S
#33 plumb init with Tailwind detection plumb-cli M

Dispatch (split): touches 2 crates — split so each gets focused review.

/gh-issue 31 --worktree
/gh-issue 32 --worktree
/gh-issue 33 --worktree

Phase gate follows — see below.

Phase gate

just validate green AND 8 rules produce findings with zero false
positives on the dogfood fixture AND plumb init scaffolds a usable
plumb.toml from a Tailwind project AND cargo xtask pre-release
green AND just determinism-check holds on JSON output.

Unblocks: phase-3

How to execute

  1. Create GitHub milestone v0.2-phase-2 if it doesn't already exist.
  2. Run bash create-issues.sh from this directory to create all child issues.
  3. Dispatch /gh-issue <child-number> for each batch in order; sessions within a batch run in parallel.
  4. Close this parent issue when every child is merged and the phase gate holds.

Generated

  • Generated at: 2026-04-24T13:16:33Z
  • Source spec: docs/runbooks/phase-2-spec.yaml
  • Repo: aram-devdocs/plumb

Metadata

Metadata

Assignees

No one assigned

    Labels

    kind:rfcDesign proposalphase-2V0 Phase 2 — MVP rule set + token adapters

    Projects

    No projects

    Relationships

    None yet

    Development

    No branches or pull requests

    Issue actions