... but default can not have calendars.

That's absolutely not true. You can attach 1) a size-max-calendar to let the capacity vary over time and 2) an availability-calendar to set the working hours.

Let's make it easy, which is the resource type on an employee that work 30h/week and can only do 1 task/1unit at each time?

"can only do 1 task/1unit at each time" -> default type, as described on https://frepple.com/docs/current/examples/resource/resource-type.php

Replies: 3 comments 1 reply

Comment options

You must be logged in to vote
0 replies
Comment options

You must be logged in to vote
0 replies
Comment options

You must be logged in to vote
1 reply
@zipus
Comment options