Following my production example from: #564 (comment) |
Beta Was this translation helpful? Give feedback.
Replies: 3 comments 1 reply
-
|
Check out the first paragraph on https://frepple.com/docs/current/examples/resource/resource-type.php to understand which resource type matches your expectations |
Beta Was this translation helpful? Give feedback.
-
|
It's not clear for me. As seams that the correct is default, but default can not have calendars. |
Beta Was this translation helpful? Give feedback.
-
That's absolutely not true. You can attach 1) a size-max-calendar to let the capacity vary over time and 2) an availability-calendar to set the working hours.
"can only do 1 task/1unit at each time" -> default type, as described on https://frepple.com/docs/current/examples/resource/resource-type.php |
Beta Was this translation helpful? Give feedback.
That's absolutely not true. You can attach 1) a size-max-calendar to let the capacity vary over time and 2) an availability-calendar to set the working hours.
"can only do 1 task/1unit at each time" -> default type, as described on https://frepple.com/docs/current/examples/resource/resource-type.php