Sprint – Iteration 4

Sprint Duration: 06/12/2025 – 19/12/2025


Sprint Planning

Sprint Goal

Improve overall project quality by extending and completing existing acceptance tests and by addressing documentation issues previously identified during evaluation.
No new features were planned or implemented in this iteration.


Sprint Review

Video / Screencast Demo

N/A – This iteration focused on testing and documentation improvements rather than new functionality.


Results Summary

Iteration 4 focused on quality assurance and documentation refinement.
Existing acceptance tests were extended and completed for user stories up to and including S-044, and documentation issues identified during project evaluation were corrected to improve clarity, consistency, and accessibility.


Work Performed

Acceptance Testing

  • Existing acceptance tests were extended and refined for user stories from S-001 to S-044
  • Some missing acceptance test checks were completed

Documentation Improvements

The following documentation issues were addressed:

  • Updated unit test coverage references to reflect the correct iteration
  • Improved acceptance test documentation and traceability

Deliverables

Code & Documentation

  • Release Tag: v4.0.0
  • Extended acceptance test documentation (S-001 to S-044)
  • Updated unit test coverage references
  • Improved deployment and access documentation

Deployed Application

Access Credentials:

  • Username: admin@admin.com
  • Password: Admin!123

Product Backlog – Future Work

The following user stories were added to the backlog during Iteration 4 as future work.
These items were not planned or implemented in this iteration and represent potential future extensions if the project were to continue.

Backlog Items (Future Iterations)

  • S-054: Join match as a team
  • S-055: Create a Competition (Tournament or League)
  • S-056: Competition match result update
  • S-057: Invite teams to competitions
  • S-058: Find competitions
  • S-059: Join tournament as a team
  • S-060: Leave Competition
  • S-061: Cancel competition

Sprint Retrospective

Did Well

  • Successfully extended acceptance tests for user stories S-001 to S-044
  • Addressed all documentation issues identified during evaluation
  • Improved overall project completeness and presentation

Do Differently (Actions)

  • Extend acceptance tests incrementally during each iteration
  • Keep documentation continuously aligned with implementation changes
  • Verify links, test references, and environment access before closing each iteration

Puzzles

  • How can acceptance testing be further automated?
  • What level of acceptance test completeness should be enforced per iteration?
  • How can test documentation be better synchronized with development?

Technical Highlights

  • Extended and completed acceptance tests for user stories S-001 to S-044
  • Improved traceability between user stories, acceptance tests, and GitHub issues
  • Corrected documentation inconsistencies across the project
  • Ensured deployment environments include complete access information