The Baselines window manages the saved snapshots of the schedule: saving, renaming, choosing the active baseline and deleting.
Planning → ribbon group Baselines & progress → Save baseline… or Manage baselines… (both open the same window). Esc, Close, the close cross or a click outside the window closes; all changes in this window take effect immediately.
One row per saved baseline:
- Active — radio button; exactly one baseline can be active. The active baseline is the comparison basis for the baseline overlay in the Gantt and the variance report.
- Name — editable directly in the row.
- Created — the date the baseline was saved.
- Delete (trash can) — removes the baseline. If it is the active one, the window first asks for confirmation ("Delete the active baseline?"); after that the most recently saved remaining baseline becomes active, or none if nothing is left.
Without baselines the window shows "No baselines yet".
- Name field — pre-filled with "Baseline {n} — {date}"; adjust the name as desired.
- Save — records the start, finish and (for milestones) the date of every task and makes the new baseline active.
- Warning — if the schedule is out of date since the last calculation, "Schedule is out of date — recalculate first (F5)" appears: a hint, not a block. A baseline on a stale schedule would freeze the wrong dates.
- Baselines & progress — baseline overlay, variance report, progress and status date.
public/docs/en/ and docs/wiki/ — direct wiki edits are overwritten on the next release.
Open Planner Studio · LGPL-3.0 · part of the OpenAEC-Foundation
Open Planner Studio
Getting started
Guides
- Planning & WBS
- Relations & constraints
- Calendars & hour planning
- Resources, histogram & leveling
- Baselines & progress
- Critical path & advanced analysis
- Import/export
- Reports & printing
- Keyboard shortcuts & controls
Reference
- Task dialog
- Calendar dialog
- Resource calendar
- Leveling options
- Baseline management
- External links
- Codes & fields (structure)
- Filters
- Choosing columns
- Saving and loading layouts
- Project information
- Settings
- Managing and installing extensions
- Recovering after a crash
- Keyboard shortcut reference
Project